The good homes construction

Assignment Help Management Theories
Reference no: EM131100441

Reconsider Prob. 10.5-4 involving the Good Homes Construction Co. project to construct a large new home. Michael Dean now has generated the plan for how to crash this project (as given as an answer in the back of the book). Since this plan causes all three paths through the project network to be critical paths, the earliest start time for each activity also is its latest start time. Michael has decided to use PERT/Cost to schedule and control project costs.

(a) Find the earliest start time for each activity and the earliest finish time for the completion of the project.

(b) Construct a table like Table 10.10 to show the budget for this project.

(c) Construct a table like Fig. 10.15 (by hand) to show the schedule of costs based on earliest times for each of the 8 weeks of the project.

(d) Now use the corresponding Excel template in your OR Courseware to do parts (b) and (c) on a single spreadsheet.

(e) After 4 weeks, activity A has been completed (with an actual cost of $65,000), and activity B has just now been completed (with an actual cost of $55,000), but activity C is just 33 percent completed (with an actual cost to date of $44,000). Construct a PERT/Cost report after week 4. Where should Michael concentrate his efforts to improve cost performances?

Prob. 10.5-4

Good Homes Construction Company is about to begin the construction of a large new home. The company's President, Michael Dean, is currently planning the schedule for this project. Michael has identified the five major activities (labeled A, B, . . . , E) that will need to be performed according to the following project network.

He also has gathered the following data about the normal point and crash point for each of these activities.

These costs reflect the company's direct costs for the material, equipment, and direct labor required to perform the activities. In addition, the company incurs indirect project costs such as supervision and other customary overhead costs, interest charges for capital tied up, and so forth. Michael estimates that these indirect costs run $5,000 per week. He wants to minimize the overall cost of the project. Therefore, to save some of these indirect costs, Michael concludes that he should shorten the project by doing some crashing to the extent that the crashing cost for each additional week saved is less than $5,000.

(a) To prepare for analyzing the effect of crashing, find the earliest times, latest times, and slack for each activity when they are done in the normal way. Also identify the corresponding critical path(s) and project duration.

(b) Use marginal cost analysis to determine which activities should be crashed and by how much to minimize the overall cost of the project. Under this plan, what is the duration and cost of each activity? How much money is saved by doing this crashing?

(c) Now use the linear programming approach to do part (b) by shortening the deadline 1 week at a time from the project duration found in part (a).

Reference no: EM131100441

The journal of finance made its content available

The Journal of Finance made its content available on the Internet starting in July of 2005. The table below shows the number of times a monthly version was downloaded and th

Explain how you see or detect the differences

Identify and research an organization that operates like a 20th century organization but has adopted a structure that manifests 21st century characteristics. Please ensure t

Describe the reasons and the causes that have led to the fai

Create a PowerPoint presentation to describe the reasons and the causes that have led to the failure of teamwork in organizations. Also, describe the reasons and the cause

Explain how would you describe craig jelineks personality

How would you describe Craig Jelinek's personality? What terminal and instrumental values are likely to be especially important to him as a manager? How would you describe Cos

Challenges of allowing users to port business applications

What are the challenges of allowing users to port business applications to their personal devices? What are the challenges of allowing users to connect to corporate systems

Was the trial court correct in the given case

In a suit brought by Scott against Purser, the trial court held in favor of Purser, because Scott presented no evidence indicating that Purser was negligent. Was the trial c

List promotional mix elements used inrefresh campaign

List all the promotional mix elements used in the Pepsi Refresh campaign. What grade would you give PepsiCo on integrating these elements into an integration marketing commu

Discuss john stuart mill

Discuss John Stuart Mill and the Utilitarian view from the standpoint of economic distribution, worker participation (Principles of Political Economy), and greater equality of

Reviews

Write a Review

 
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd