5) The marketing department at Bodnar Industries is developing a promotional campaign to introduce a new product. A listing of the various activities required, their immediate predecessors, and estimates of their times (in days) is given below.
a) Draw the precedence diagram for this network.
b) Identify the critical path and the expected project completion time.
c) Calculate the expected slack time for each activity. Also compute the slack time for each path relative to the critical path completion time.
d) What is the probability that the critical path will be completed in more than 65 days?
e) How many days should the marketing manager allow for completion of the critical path if he wants to be 99% sure that the critical path will be completed within this allowed time?
Activity
Description
Immediate Predecessors
Optimistic Time
Most Likely Time
Pessimistic Time
A
Rough brochure layout
--
2
3
5
B
Review brochure
6
8
10
C
Final brochure layout
4
D
Final brochure artwork
7
11
E
Design display
12
15
20
F
Rough display artwork
G
Review display
H
Revise display
I
Final display artwork
F,H
1
J
Make display plates
18
23
26
K
Make brochure plates
D,I
13
16
L
Make and ship displays
14
M
Print and ship brochures
Consider the "Alternative Approach" to combating five consumer products (alcohol, tobacco, guns, motor vehicles, and junk food) and determine whether you agree or disagree with the approach suggested.
nternal customers in organizations, Distribution resource planning (DRP), Electronic data interchange (EDI), Stocktaking, inventory policy, Shelf life of products, Limited storage space
What is the difference between risk identification and risk control in the context of protecting information systems?
A short discussion on the elements considered necessary for research to be considered good research.
For this Discussion Forum, please document all of the steps needed to create a specific strategic group map for the beer industry. Then create a strategic group map, based upon the following industry definition:
Mathematical Programming and Optimisation: Build and describe a prototype model Use your model to recommend a schedule of burning and, if required buying fuels
Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.
Determining potential methods of researching the issues, identifying the root causes of the issues, and determining the appropriate research instruments to collect data are all discussed. Examples are provided with the explanations.
The solution offers step by step guidance on how to formulate the problem mathematically. It comprises a solution to problem instance using Excel Solver.
The solution discusses an ethical problem in workplace environment and solutions to solve the problem by using the Ethical Decision Model is as well explained. Also discussed is an opinion on how employee compensation should be determined based on..
The dean of the Western College of Business must plan school's course offerings for the fall semester. Student demands make it necessary to offer at least 30 undergraduate and 20 graduate courses in the term.
marketing strategy, turnover in terms of revenue, Paid out rate
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd