Suppose you calculated the mean and the standard deviation of the critical path (longest path) as mean = 100 days, standard deviation as 10 days. The mean and the standard deviation of the second longest path are 95 and 12 days, respectively. Which of the following statements is true?
I. The second longest path can be longer than the critical path
II. Simulation and PERT would give very similar answers for the 90th percentile of the project duration
III. PERT bias would be insignificant (negligible) for this problem
a) I
b) II
c) III
d) II & III
e) None of them is correct
Keeping them organized sounds easy but what advice would you offer on addressing their various perspectives and without marginalizing them into clusters or groups with similar concerns?
Discuss the key factors that have contributed to the evolution of operations and supply chain management. Describe the benefits and costs of good quality, and the costs of poor quality. Define the quality tools and the DMAIC methodology in problem so..
Which kind of consumer-goods market testing involve consumers who initially try the product at no cost then who are reoffered the product, or a competitor's product, at a slightly reduced price.
A major producer of passenger tires has launched an advertising campaign in which it is trying to market windshield wipers to the public under its brand name, which has been highly successful in the passenger tire market. Explain why the passenger ti..
Explain how these demographics determine or affect the cultural dynamics where you live. For example, types of restaurants, specialty grocery items, entertainment offerings, public housing requirements, and education offerings.
michael porter was a business researcher who made popular the concept of a value chain that is common to most business
e-commerce is the trend that most companies are going toward now a days. you are to select one business that does not
introduced a new way to explain structural configurations by "clustering various functions into groupings and showing their relative size and clout in response to different missions and external challenges" (Bolman & Deal, 2009, p. 78). Other auth..
What generation are you a member of and what motivates you to work? What characteristics about your co-workers "get under your skin", figuratively speaking?
Annual carrying costs are approximate d at $0.60 per pot per year and ordering costs are $20 per order. Illustrate what additional cost is shop incurring by using this current order size rather than economic order quantity.
Explain the differences between outsourcing and off shoring. When is it appropriate for a firm to outsource and/ or offshore its production functions?
Select three types of pre-employment testing and discuss the purpose, effectiveness in the selection process, legal parameters for use of the testing, costs associated with administration of the testing, and recommendation for the use of the testing.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd