A project was planned using PERT with three time estimates. The expected completion time of the project was determined to be 40 weeks. The variance of the critical path is 9.
a) What is the probability that the project will be finished in 40 weeks or less?
b) What is the probability that the project takes longer than 40 weeks?
c) What is the probability that the project will be finished in 46 weeks or less?
d) What is the probability that the project takes longer than 46 weeks?
e) The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. Thus, there would only be a 10% chance the project would take longer than this due date. What should this due date be?
The planning for the community building session is almost complete. The last details are how to conduct the plenary sessions for sharing information across groups to develop key priorities and themes that will need to be addressed.
In a four- to- five- page paper (excluding the title and references page), address organizational processes and change. Write a paper using the five steps in the organizational process found on page 200 in the text. In your paper, you must
The specification limit for a bag of C&A s jelly beans is 16 ounces and 13 ounces. A process that produces the jelly beans has a mean of 14.5 ounces and a standard deviation of 0.75 ounces. What conclusion can be drawn regarding C&A s bagging proc..
Examine why sabermetric-based player evaluation is such a shock to other executives in baseball. Evaluate why Beane is much more effective in his success by constructing a matrix of pitfalls and heuristics that highlight the differences between Be..
you will need to name the type of company you will be creating a plan for and the basic information on that company
Inventory and Littles Law
If an employee had low self-esteem? How can managers shape behavior? Bring into your discussion the concepts of reinforcement, punishment and extinction.
Illustrate what would be the average length of the waiting line. Illustrate what would be the average time which a vehicle must wait to get through the system.
Using one of the theories on motivation, describe how you would motivate an employee who is not being productive and does not display the drive to move forward?
Counterproductive behaviors consist of those employee behaviors that intentionally hinder organizational goal accomplishment. Routine task performance involves employee responses to task demands that are novel, unusual, or, at the very least, unpredi..
So that you need can better be met in the future, please complete the online survey about your recent flight with Southwest Airlines is an example
As the work of your risk management team (from the first discussion question) continues, the discussion of your team's risk management plan outline moves on and considers the following questions: Who should do the prioritization of the project risks?..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd