Problem 1: Consider the following project network and activity times (in days):

1327_project network and activity.jpg

Activity

A

B

C

D

E

F

G

Time                                      1

3

2

5

5

6

2

2

The crashing data for this project are as follows:

 

Times  (days)

Cost ($)

Activity

Normal

Crash

Normal

Crash

A

3

2

800

1400

13

2

1

1200

1900

C

5

3

2000

2800

D

5

3

1500

2300

E

6

4

1800

2800

F

2

1

600

1000

G

2

1

500

1000

a. Find the critical path and the expected project completion time.

b What is the total project cost using the normal times?

Problem 2: Refer to Problem 1. Assume that management desires a 12-day project completion time. Formulate a linear programming model that can be used to assist with the crashing decisions.

b. What activities should be crashed?

c. What is the total project cost for the 12-day completion time?

Problem 3: Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:

 

 

Immediate

Time (weeks)

Cost ($1000s)

Activity

Description

Predecessor

Normal

Crash

Normal

Crash

A

Plan needs

-

10

8

30

70

B

Order equipment

A

8

6

120

150

C

Install equipment

B

10

7

100

160

D

Set up training lab

A

7

6

40

50

E

Conduct training course

D

10

8

50

75

F

Test system

C, E

3

3

60

-

a. Develop a project network.

b. Develop an activity schedule.

c. What are the critical activities, and what is the expected project completion time?

d. Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.

e. Develop an activity schedule for the crashed project.

f.  What added project cost is required to meet the six-month completion time?

Reference no: EM13837052

Questions Cloud

Why is behavioral tracking such an important ethical dilemma : Why is behavioral tracking such an important ethical dilemma today? Identify the stakeholders and interest groups in favor of and opposed to behavioral tracking
Questionnaire based proposed research problem : The questionnaire outlined below, consist of 10 multiple choice questions that is designed to develop a better understanding in the overall reduction in student attendance.
Explain a variation on the consumption function : Draw the function Y = F(K,L ¯) in terms of Y and K, for some fixed L. On the same graph, plot the cost function for renting a certain amount of capital at a rental price of R, i.e. RK. For a profit maximizing firm, illustrate graphically how much ..
Prototype of a new action-oriented computer game : As Justin works on the prototype of a new action-oriented computer game, he is engaging in which phase of the new-product development process
Problem regarding the project network and activity times : Problem 1: Consider the following project network and activity times (in days):
Production manager of a large cincinnati manufacturing firm : The production manager of a large Cincinnati manufacturing firm
What is the moral point of view and why is it important : What is the moral point of view and why is it important
Discuss the method of quantitative : What is quantitative easing. Hasn't the Fed already tried quantitative easing. When. What were the results. Discuss the method of quantitative easing used by the Federal Reserve during the most recent U.S. recession, including any criticisms of th..
Organizational behavior case study : Organizational Behavior Case Study

Reviews

Write a Review

Business Management Questions & Answers

  Pitfalls of job evaluation methods

Pitfalls of Job Evaluation Methods

  What volume at standard conditions

2000 mL/min of air sampled for 30 min at 18oC and 103 kPa equals what volume at standard conditions of 25oC and 1 atm: a) In liters b) In m3

  Leadership behavior with triarchic modelgiven that emotions

leadership behavior with triarchic modelgiven that emotions often play such a big part in leadership do you think that

  Computing the break-even volume

William start his own business which produces shirts for special occasions. He has just started this business and rents space and machine from a local fabric maker when require.

  Adjusting timing of salesyou are new accountant at the

adjusting timing of salesyou are new accountant at the company and your boss orders you to backdate several sales

  Should federal statutes pre-empt state constitutions

Discuss explain why the legal system in the United States ensures which federal law pre-empts state law. Some questions to keep in mind are: Illustrate what are the advantages of having one set of laws, like federal law.

  Directors officers and controlling shareholders

Directors, Officers and Controlling Shareholders -Give an instance or scenario of how a manager could effectively utilize the Business Judgment Rule.

  Discuss in detail the ethical, negligence

Discuss in detail the ethical, negligence

  Types of information in pre-departure training

In your pre-departure training, what types of information should you get?

  Question about opening a business

Assume you and your two college roommates have discussed plans to open a restaurant. You intend to attract college age learners who are health and fitness minded to your restaurant.

  Capture the complexity of motivating individuals

Prepare a mini-scenario that captures the complexity of motivating individuals in a diverse workforce,and use a real situation from workplace.

  Projecting pedex and ups stock prices

Projecting PEDEX and UPS stock prices - Prepare a graph from the historical data and forecast on the same graph.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd