Prepare an updated project management plan

Assignment Help Other Engineering
Reference no: EM131445169

Question 1

Earned Value Management

Question 1 (a) --- Project 1

You are managing a project that is scheduled to take 12 months to complete and has a budgeted actual cost (BAC) of $1,500,000.

At the Status Date, the project has the following characteristics:

Planned value (PV)

$450,000

Actual cost (AC)

$520,000

Percentage of work completed

28%

Calculate the following quantities: 28%

Earned Value (EV)

Cost Variance (CV)

Schedule Variance (SV)
Cost performance index (CPI)
Schedule performance index (SPI)

Using your results, apply the three (3) formulae listed in Section 7.4.2.2 of the text to the calculation of the Estimate at Completion (EAC) of the project.

These formulae are as follows:

 EAC=AC + (BAC - EV)

 EAC=BAC/CPI

 EAC= AC + [(BAC-EV) / (CPI x SPI)].

Question 1 (b) --- Project 2

You are managing a second project that has the same time and cost specifications as those in Question 1 (a), but which is 40% complete at the Status Date, when Actual Costs are $550,000.

Its specifications are below

Budgeted Actual Cost (BAC): $1,500,000. Schedule time to complete: 12 months

At the Status Date, the project has the following characteristics:

Planned value (PV)
Actual cost (AC)
Percentage of work completed

Calculate the following quantities:

Earned Value (EV)

Cost Variance (CV)
Schedule Variance (SV)
Cost performance index (CPI)
Schedule performance index (SPI)

Using your results, apply the three (3) formulae listed in Section 7.4.2.2 of the text to the calculation of the Estimate at Completion (EAC) of the project.

These formulae are as follows:

 EAC=AC + (BAC - EV)
 EAC=BAC/CPI
 EAC= AC + [(BAC-EV) / (CPI x SPI)].

Question 1 (c)

Compare the two projects from the point view of project performance, paying particular attention to the following:

Cost Variance (CV) (2 marks per project)
Schedule Variance (SV) (2 marks per project)
Cost performance index (CPI) (2 marks per project)
Schedule performance index (SPI) (2 marks per project)
Estimated Actual Cost (EAC) of the project (2 marks per project)

A brief assessment of the overall project performance, including any necessary measures required to successfully complete the project

Total Marks per project 15 marks per project

SUB- TOTAL FOR Question 1 (c)

Question 1 (d)

There has been considerable discussion about Earned Value Project Management in the literature. Using at least two (2) literature sources to support your discussion, discuss your views about at least two (2) positive aspects of Earned Value Management and at least two (2) potential issues with its use as a project control tool. Form an opinion about the value of Earned Value Management as a project management tool.

Marking:

Positive aspects of Earned Value Management

Issues with the use of Earned Value Management

Development of opinion

Use of references to support your answer

Question 2

Developing a Revised Project Management Plan and Report to Management

Background

You have recently been appointed as a project manager in a large engineering organisation. Some examples of such an organisation include, but are not limited to:

- Consultant
- Government organisation
- Construction company
- Installation company
- Asset management provider
- Maintenance services provider
- Other.

The organisation may be operating in one or more engineering disciplines, such as civil, mechanical, electrical, environmental, mechatronic, biomedical, or other discipline, or in construction or surveying.

Your organisation has asked you to review the management of a medium sized project (up to $5 million in value), which is to be completed within two (2) years of its commencement. The project has at least 20 main activities.

The project commenced eight (8) months ago. The first six (6) weeks were spent developing the project charter and preparing the original project management plan. Project execution (carrying out the work) commenced immediately the project management plan was completed and approved.

There will be a one (1) month project closing period at the end of the project. During this time, equipment will be tested and commissioned (if relevant to your project), and the project will be finalised.

The project deadline is firm, subject to any justifiable contingencies.

The existing business case and project charter are not detailed. Similarly, the project management plan, including a basic Gantt chart and high level budget is not well detailed or described.

There are a number of issues with the project:

1. To date, the project is two (2) months behind schedule. Part of this delay has resulted from poor understanding of lead times for delivery of particular project components. There are no other significant factors that should impact on project delivery.

2. Because there is only a quite basic project plan and time schedule, there is poor sequencing of critical activities. They do not have clear scheduled completion dates.

3. There have been delays in procuring some critical project resources. There may be alternative suppliers.

4. While there were a number of specialised personnel for particular aspects of the project available at the start of the project, they were not booked ahead of when they were required.

Most of these resources are now booked for several months ahead. Few alternatives are available.

5. As a result of the influence of a number of stakeholders, there has been significant scope creep, which with the current rate of progress will delay delivery by one (1) month. This scope creep also threatens to impact on the project's business case.

6. Some components of the project have not been delivered or built to the required quality specification. Consequently, there have been delays while defects have been rectified.

7. Communication between project manager, project sponsor, stakeholders, contractors, consultants and other key personnel has not been good. There are therefore a number of cases where key information has not been communicated well. This poor communication has impacted on project progress.

You have been charged with delivering a revised project management plan to deliver the project on time; and with providing a report to the Project Sponsor explaining the actions you have taken.

Your Task

Question 2 (a) Developing a Revised Project Plan

(maximum 2500 words)

1. Define your organisation and project.

Nominate an organisation of your choice, and the engineering discipline or disciplines in which it is operating.

Nominate a suitable project (for example, road development, subdivisional development, power station, mobile phone network, mining, provision of industrial equipment, installation, maintenance, surveying) to use as an example.

2. Prepare a revised project charter, including an updated business case. This document should include an executive summary of the revised project charter.

3. Prepare an updated project management plan for completing the project within its original timeline.

The project management plan should include plans for all phases/stages of the project based on the following Project Management Knowledge Areas:

- project integration management
- project scope management
- project time management
- project cost management
- project quality management
- project human resource management
- project communications management
- project procurement management.

Notes:

- The project charter should include a revised business case for the project and link the project with your organisation's strategic plan. On the basis of this business case, the project sponsor will make a decision about the future of the project.
- You may assume that the project sponsor has allowed the project timeline to be increased by one (1) month to allow for the scope creep already approved. However, further scope creep is not permitted.
- The project scope management plan should include a Work Breakdown Structure and a section on controlling scope creep. Normally three (3) levels should be sufficient for the Work Breakdown Structure.
- The project time management plan should include a Gantt chart showing the major project activities (up to about 30 activities).
- The project cost management plan should include all costs reasonably expected to be incurred in delivering the project. These costs may include estimates for ensuring completion of the project.

SUB- TOTAL FOR QUESTION 2 (a) 200 MARKS

Question 2 (b) Report to Project Sponsor

Write a report to your Project Sponsor that:

- succinctly outlines the steps you have taken to deliver the project within its original timeframe (as extended by permitted scope creep of one (1) month)
- explains why they have been taken
- demonstrates how they will enable the project to be completed within its original timeframe
- discusses the additional costs that will be incurred to achieve this target

Written Communication

Abstract and table of contents
Structure
Language, style, spelling
Completion in within word count
Setting out and referencing

SUB- TOTAL FOR WRITTEN COMMUNICATION 50 MARKS

Verified Expert

The solution contains total 4500 words and done by using the Harvard Referencing. The solution has two parts. The first part involves working on some calculations while the 2nd part considers the project work of a real world company.

Reference no: EM131445169

Questions Cloud

Determine the molar mass of the unknown acid : Use the Ksp values to calculate the molar solubility of each of the following compounds in pure water. MX (Ksp = 1.30×10-38)
Analyze the relative costs of each strategy you present : Draft a set of company policies that would help to avoid the loss of more than one key executive in a single crisis. Describe the relative costs of each strategy you present.
What specific needs does the agency attempt to meet : SOCW 2361 : Provide a brief description of the agency. Include the name of the agency, address, phone number and contact person.What specific needs does the agency attempt to meet? How does the agency identify these needs (observations, client ..
Calculate the ph of the solution : Calculate the pH of the solution that results from each of the following mixtures.
Prepare an updated project management plan : ENG8208 Advanced Engineering Project Management - Prepare an updated project management plan for completing the project within its original timeline and Prepare a revised project charter, including an updated business case - Define your organisation ..
What is the end behavior of the graph : Consider the leading term of the polynomial function. What is the end behavior of the graph? Describe the end behavior and provide the leading term.
How can connect transnational motherhood to globalization : How can you connect transnational motherhood to globalization and how do you think the inequality that shapes the experiences of transnational mothers can change?
Physical chemistry-quantum mechanics : "Briefly and clearly define each of the following and explain the significance. If you use an equation in your answer, define in words each symbol you use."
Calculate the morality : Calculate the morality of H2SO4 (aq) that results after 10.0 mL of H2O are added to 25.0 mL of 0.500 M H2SO4 (aq) in preparation for the following reaction. Assume the volumes are additive.

Reviews

inf1445169

4/20/2017 6:06:25 AM

I will utilize your services once more, and I have learnt the significance of reaching the expert regardless of the fact that its lone to make proper acquaintance, with keep away from any false impressions that outcome in additional work for the author.

len1445169

3/30/2017 8:33:38 AM

11. Applications for extensions of assignment submission must be made in writing to the Course Examiner together with accompanying documentation as specified in the Assessment of Compassionate and Compelling Circumstances Procedure. The application and all supporting documentation must be submitted electronically. An Assignment submitted after the deadline without an approved extension of time will be penalised. The penalty for late submission without a pre-approved extension will be specified in the assignment instructions. At the very least, the penalty for late submission is a reduction by 5% of the maximum Mark applicable for the Assignment, for each University Business Day or part Business Day that the Assignment is late. An Assignment submitted more than ten Course Examiners may refuse to accept Assignments for Assessment purposes after Marked Assignments and/or feedback have been released. If Compassionate and Compelling Circumstances appear to exist, Course Examiners must consider these before refusing to accept an Assignment.

len1445169

3/30/2017 8:33:19 AM

7. It is expected that your written answers will be produced using electronic word processing. The ‘.pdf’ format is preferred for written answers. 8. Calculations for the project budget should be clearly explained. 9. Assignments will be submitted electronically via the Study Desk. 10. Please note that if plagiarism or cheating is detected in this assignment it will result in no marks for the assignment. Students should ensure they clearly understand the meaning of plagiarism and cheating. In particular, students should understand that while they may collaborate with other students on the conceptual ideas in their assignments, the final written report submitted by each student must be unique, and must not contain the written material of (a) any other student in the course, or (b) by any other person without due acknowledgement. Assignments are expected to be submitted to plagiarism detection software at the time of submission.

len1445169

3/30/2017 8:33:06 AM

1. Answer all questions, and ensure that your answers have the coverage, and are in the format, requested. 2. Present your own ideas. 3. Your answers should be properly referenced and reflect that you have undertaken research outside the study material. You are to use the Harvard AGPS referencing system, information which is available from the USQ Library webpage: 4. You will require a table of contents for your answer to Part A. 5. You will require an abstract and table of contents for your answer to Part B. 6. You should include a word count for each of Part A and Part B of Question 1. Word counts exclude the List of References.

Write a Review

Other Engineering Questions & Answers

  Draw both the given cases on the given graph

EEN 1200- Follow steps of part A-1 to hook up the 7408 of Quad 2-Input AND gate, then connect input A to SW7 and input B to SW6 then generate a truth table below by measuring output Z using voltmeter. Draw both cases on the graph below.

  New keynesian model with technology shocks

Discuss the real output and in ation expressions verbally - New Keynesian model with technology shocks

  Design equipment which apply simple shear

Design two equipment, one is to apply simple shear and the other one to apply biaxial compression to a spinal cartilage (intervertebral disc)

  What total load will steel shore be able to carry

What total load will a AS 550 steel shore be able to carry if the outside diameter is 2.5 inches and a wall thickness of 0.154 inches

  Some purpose such as modeling or curve fitting

Use a For Loop to create an array containing 100 elements between 0 and 500.

  Review energy use and develop an energy plan

Your organization is about to review its energy use and develop an energy plan, including as many renewable power sources as possible. You have been asked to prepare a presentation for upper management about fossil fuel, nuclear energy, and altern..

  Find the characteristic polynomial

a. Find the characteristic polynomial, a(z), for this system. b. Find the input polynomial, b(z) for this system.

  How many nmos transistors are needed in the nor decoder

For the column decoder shown in Fig. 16.26, how many column-address bits are needed in a 1-Mbit-square array? How many NMOS pass transistors are needed in the multiplexer? How many NMOS transistors are needed in the NOR decoder? How many PMOS tran..

  Device for instance stethoscopeand talk

Pick any Medical device for instance stethoscopeand talk about it in 2 pages for example introduction, and how it works, advantages and its cost like that.1- cover page2- some picture of the device.

  Calculate the theoretical no-load gain of the circuit

Simulate the circuit in Multisim verifying measured values (Make at least one statement comparing simulated values to measured values.). Calculate the theoretical, no-load gain of the circuit.

  Liquid of unknown density pf

A right circular cone of base radius R, height H, and known density ps floats base down in a liquid of unknown density pf. A height h of the cone is above the liquid surface.

  What controls the electrical properties of the atom

What controls the electrical properties of the atom? The valence electron is referred to as a ______? When silicon atoms combine to form a solid, they arrange themselves into an orderly pattern called ____________ ?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd