Perform critical path analysis-minimum project duration

Assignment Help Other Subject
Reference no: EM13256211

1. Consider the following precedence chart. The start date for this project is March 15, 2013.

 

Phase

Activity

Preceding

Activities

Duration (days)

Phase 1

A

--

5

Phase 1

B

--

6

Phase 1

C

--

3

Phase 2

D

A

5

Phase 2

E

A

4

Phase 2

F

B

4

Phase 3

G

D,E

5

Phase 3

H

F

5

Phase 4

I

H

3

a) Perform critical path analysis by hand. What is the minimum project duration?

b) Compute the total slack for each activity using the forward pass and backward pass approach.

2. A network consists of the following activities. Times are given in days.

 

Phase

Activity

Preceding

activities

Optimistic

Most likely

Pessimistic

Phase 1

A

--

5

9

15

Phase 1

B

--

3

6

9

Phase 1

C

--

5

12

15

Phase 2

D

A

3

5

7

Phase 2

E

B

4

6

12

Phase 2

F

C

6

8

10

Phase 3

G

D, E,F

2

5

6

Phase 3

H

F

3

4

9

Phase 4

I

G, H

5

5

5

a) Perform critical path analysis by hand. What is the minimum project duration?

b) Now use MS Project software and perform critical path analysis. Start date for this project is March 15, 2014. We use a standard calendar. When should we complete this project? Compare results from question (a) and question (b).

c) Use MS Project software and perform critical path analysis when we are introducing a lag of 3 days at the start of D and a lag of 4 days at the start of H. We are introducing a lead of 3 days at the start of F. We use standard calendar. Start date for this project is March 15, 2013. Mark I as milestone activity. When should we complete this project?    The deadline is set as May 1, 2014. Can we finish this project by the deadline date? Support your answers with printouts from MS-Project software.

d) What are the WBS codes for A and G. Hint: Go to task information and find WBS codes.

Reference no: EM13256211

Questions Cloud

Compare financials across competitors or over time : Do you believe it would be more important to compare financials across competitors or over time? Explain your choice, giving examples.
Local political picnic : At a local political picnic there are 20 male republicans, 15 male democrats adn 12 female democrats. a raffle is held to give away a nice coleman picnic cooler what is the probability that either a male of a republican will win the prize?
Use of chemicals and solvents in an industrial environment : How does the concept of permissible exposure limit affect the use of chemicals and solvents in an industrial environment?
Operator of a summer camp-excel employment agency : In May, Mike, a 17 years old college student, was introduced to Dover, the operator of a summer camp, through Excel Employment Agency. Mike and Dover entered into a written agreement whereby Dover hired Mike as a camp counselor during the summer vaca..
Perform critical path analysis-minimum project duration : Perform critical path analysis by hand. What is the minimum project duration? Compute the total slack for each activity using the forward pass and backward pass approach.
A solution calorimeter has a heat capacity : A solution calorimeter has a heat capacity of 94.82 J/K. It contains 100mL of a solution that is 3.0 M in H2SO4 and 0.02500 M in Fe2+. This solution has a heat capacity density of 0.232 J/K mL. 0.07900 g of powdered KMnO4 (FW=158.034 g/mol) was intro..
Scope and limitations of its own power : Though the U.S. Constitution provides for checks and balances that limit the power of each of the three branches of U.S. government, which branch can essentially decide for itself the scope and limitations of its own power?
A dsDNA molecule is found : A dsDNA molecule is found to be 14% cytosine. What are the proportions of the other three bases?
A fuel oil is burned in a boiler furnace : A fuel oil is burned in a boiler furnace, releasing 2*10^7 J/hr of heat, of witch 90% goes to produce saturated steam at 1500 kPa from liquid water at 30 C. at that rate in kg/hr is steam produced?

Reviews

Write a Review

 

Other Subject Questions & Answers

  Describe the processes involved in development

Describe strategies which teachers can use to stop students from misbehaving in class What do you understand by the term development Describe the processes involved in development

  Conflict with their obligation to themselves

Health care providers are obligated to provide for those entrusted in their care. To what extent do they meet this obligation? How might their obligation to others conflict with their obligation to themselves?

  The fee-for-service and capitation payment cycles

The fee-for-service and capitation payment cycles. Include the relationship among provider, patient, and payer in your presentation, and their roles in the process.

  Study of conformity-compliance-obedience or acceptance

The study of conformity involves why people are likely to change their behaviors or beliefs as a result of real or imagined group pressure. There are three types of conformity.

  Compared to the population of the state

Compared to the population of the state, which of the following groups is over-represented in the Texas legislature?

  Description on the method of perception

Illustrate your thoughts on the content of this description below as it relates to perception.

  Develop a unique proposal that describes health care system

Develop a unique proposal that describes a new health care system. Consider the current U.S. health care system’s strengths, weaknesses, and challenges

  Explain deep-ocean trenches at subduction zones

At one time it was believed that deep-ocean trenches at subduction zones would be good place for disposal of high level radioactive waste. Why is this not good idea?

  Personal accountability in public administration

David, your boss, shares with you his experiences with his new administrative assistant. He says, "You know Abdul, my administrative assistant, who joined me a few months ago.

  Describing the elements for a valid contract

After the concert, Gerard tells Kids Care that he has decided not to donate the receipts to the organization. Is Gerard's promise enforceable despite the lack of consideration? Explain.

  Evaluate the social responsibility approach

Select an organization that you are interested in researching. Evaluate the social responsibility approach of that company with regard to one of the following social issues: a) environmental protection, b) worker health and safety, or c) product s..

  Revolutionary republicanism

Did Puritan thought affect revolutionary republicanism or had views of power changed so much between the puritans and the American revolution that there was no influence?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd