Moore housing contractors

Assignment Help Project Management
Reference no: EM13713918

Project Topic 1: Moore Housing Contractors 

Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in late winter or early spring when the weather begins to moderate and build through the summer and fall. The summer months are a busy time for the realty company, and it believes it can sell the houses almost as soon as they are ready or sometimes before. The houses all have similar floor plans and are of approximately equal size; only the exteriors are noticeably different. The completion time is so critical for Countryside Realtors that it is insisting a project management network accompany the contractor's bid for the job with an estimate of the completion time for a house. The realtor also needs to be able to plan its offerings and marketing for the summer. The realtor wants each house to be completed within 45 days after it is started. If a house is not completed within this frame, the realtor wants to be able to charge the contractor a penalty. Mary and Sandy Moore, the president and vice president of Moore Housing Contractors, are concerned about the prospect of a penalty. They want to be confident they can meet the deadline for a house before entering into any agreement with a penalty involved. If there is a reasonable likelihood they cannot finish a house within the 45 days, they want to increase their bid to cover potential penalty charges. The Moores are experienced home builders, so it was not difficult for them to list the activities involved in building a house or to estimate activity times. However, they made their estimates conservatively and tended to increase their pessimistic estimates to compensate for the possibility of bad weather and variations in their workforce. Following is a list of the activities for building a house and the activity estimates: 


Activity Description Predecessors Time (days) 
a m b 
A Excavation, pour footers - 3 4 6 
B Lay foundation A 2 3 5 
C Frame and roof B 2 4 5 
D Lay drain tiles B 1 2 4 
E Sewer (floor) drains B 1 2 3 
F Install insulation C 2 4 5 
G Pour basement floor E 2 3 6 
H Rough plumbing, pipes E 2 4 7 
I Install windows F 1 3 4 
J Rough electrical wiring F 1 2 4 
K Install furnace, air conditioner C, G 3 5 8 
L Exterior brickwork I 4 6 10 
M Install plasterboard, mud, plaster J, H, K 6 8 12 
N Roof shingles, flashing L 2 3 6 
O Attach gutter, downspouts N 1 2 5 
P Grading D, O 2 3 7 
Q Lay subflooring M, N 3 4 6 
R Lay driveway, walks, landscape P 4 6 10 
S Finish carpentry Q 3 6 12 
T Kitchen cabinetry, sink, and appliances Q 2 4 8 
U Bathroom cabinetry, fixtures Q 2 3 6 
V Painting (interior and exterior) S, T, U 4 6 10 
W Finish wood floors, lay carpet S, V 2 5 8 
X Final electrical, light fixtures V 1 3 4 
1. Develop a CPM/PERT network (draw the network, find expected completion time, variances, ESTs, LSTs, EFTs, LFTs, and slack for each activity, and expected project completion time and critical path). 
2. Determine the probability that the contractors can complete a house within 45 days. 
3. Does it appear that the Moores might need to increase their bid to compensate for potential penalties? 
4. Indicate which project activities Moore Contractors should be particularly diligent to keep on schedule by making sure workers and materials are always available. 
5. Indicate which activities the company might shift workers from as the need arises. 

The Moores also developed the budget for building a house. The budget estimates before project start is provided in the table below: 

Activity Total budgeted cost ($) 
A $20,000 
B $21,000 
C $25,000 
D $5,000 
E $6,000 
F $4,000 
G $15,000 
H $11,000 
I $8,000 
J $7,000 
K $6,000 
L $13,000 
M $6,000 
N $3,000 
O $2,500 
P $3,500 
Q $8,000 
R $11,000 
S $9,000 
T $8,000 
U $4,000 
V $6,000 
W $8,000 
X $2,000

6. Develop budgeted cost estimates per day from the start of the project until its completion using both ESTs and LSTs of each activity. 

In the 12th day of the project, the Moores wanted to know the status of the project. Activities A, B, C, D, and E have been finished and incurred costs of $19,000, $24,000, $25,000, $4,000, and $8,000, respectively. Activity G is 80% finished with incurred costs of $13,000, activity H is 60% finished with incurred costs of $7,000, and activity F was just started (5% completed) and incurred a starting cost of $600. The other activities have not been started. 
7. Is the project of building the first house on schedule? 
8. What is the value of work completed? 
9. Are there any cost overruns? 

Suppose the Countryside Realtors wanted to have each house finished in 35 days. Moore Contractors has a plan developed for this type of situation, as well. This plan includes adding extra resources such as equipment and people to each of the activities A - X needed for building a house. The crash time and crash cost for each activity are presented in the table below: 

Activity Crash time Crash cost 
A 3 $28,000 
B 2 $26,000 
C 3 $31,000 
D 1 $6,500 
E 1 $7,000 
F 3 $5,000 
G 2 $18,000 
H 3 $12,000 
I 2 $10,000 
J 1 $7,500 
K 3 $9,000 
L 3 $19,000 
M 6 $8,000 
N 1 $4,000 
O 1 $3,000 
P 2 $4,000 
Q 3 $10,000 
R 4 $13,000 
S 3 $12,000 
T 3 $9,000 
U 2 $6,000 
V 5 $9,000 
W 4 $9,000 
X 1 $4,000

10. Calculate the project crash cost under this scenario. 
11. Using the crash time and crash cost in the table above, calculate the shortest possible delivery time and its cost.

Reference no: EM13713918

Questions Cloud

Define at what temperature of krypton occupy a volume : At what temperature (in oC) does 11.25 g of krypton occupy a volume of 5.44 L at a pressure of 1.07 atm? Report your answer to 3 significant figures and do not include units in your answer.
How is ethics and ethical behavior apparent : How is ethics and ethical behavior apparent in corporate culture. What is the relationship between law, values, and ethical behavior
Rsa with public - private key pair : RSA with three primes would also work: n = pqr, ?(n) = (p?1)(q?1)(r?1), gcd(e, ?(n)) = 1,
Explain what temperature of krypton occupy a volume : At what temperature (in oC) does 11.31 g of krypton occupy a volume of 9.66 L at a pressure of 1.91 atm
Moore housing contractors : Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in late winter or early spring when the weather begins to moderate and build through t..
Generate the random private key : Show that p and q are primes and q|(p ? 1) - Generate the random private key x and compute the public key y.
What temperature change will be needed to change the volume : A gas occupies 4.78 L when the temperature is 45.0oC and at 1.08 atm of pressure. What temperature change (in K) will be needed to change the volume to 6.50 L at constant pressure. Report your answer to 3 significant figures and do not include uni..
Draw a block diagram of the scheme : Suppose a variant of the OFB mode by which we only feedback the 8 most significant bits of the cipher output.
Calculate the mass to three significant figures : When aqueous solutions of K2SO4 and Pb(NO3)2 are combined, PbSO4 precipitates. Calculate the mass, in grams, of the PbSO4 produced when 1.74 mL of 0.154 M Pb(NO3)2 and 3.64 mL of 0.75 M K2SO4 are mixed. Calculate the mass to 3 significant figures.

Reviews

Write a Review

Project Management Questions & Answers

  Macro and micro project risk managementdescribe the

macro and micro project risk managementdescribe the difference between macro and micro risk management. think of a

  What is the critical path when normal activities are used

What is the critical path when normal activities are used and evaluate the minimum total direct cost for each of the following project durations

  Risks introduced by change in plans

What are the risks (adverse effect) that are introduced by this change in plans?

  Type of organizational form fosters teamwork

Which type of organizational form fosters teamwork in the best manner?

  Discuss the differences between closing a project

Analyse and discuss the differences between closing a project that has met its objectives and closing one that was terminated early. Look at both administrative closure and associated contract closure. Give reasons for stating the differences betw..

  Budget for development of news letterflyer- wand projectyou

budget for development of news letterflyer- wand projectyou are required to get a budget together you need an estimate

  Project charter and project schedule and rough cost estimate

Project Charter and project Schedule and Rough Cost Estimate - include project title, date of authorization, project manager's name, brief scope statement, planned approach for managing the project, roles and responsibilities matrix, sign-off secti..

  How to construct a cpm diagram in microsoft word

Can you please give me with step by step instructions on how to construct a cpm diagram in microsoft word?

  Stages of project portfolio management

Explain the four stages of the project portfolio management process and give at least three specific activities which occur in each step.

  Communication in the virtual team environment

Communication in the virtual team environment - virtual arena particular as it relates to cultural differences.

  Justifying the influence of stakeholders

Justify the influence of stakeholders in the project management plan and their role in communication planning.

  Reducing project durationcritical path and critical project

reducing project durationcritical path and critical project requirements could indeed be separate issues. this is why

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd