Garden City Pots, Inc. manufactures large flower pots for city and urban settings. It sells its large flower pots to cities, municipalities, and large businesses to be used it their landscaping designs. Garden City Pots has developed the following per unit standard costs for 2016 for each large flower pot:

Standard Costs:                    

Direct Material                                    15 lbs. resin                 $5.00 per lb.   

Direct Labor                                        2.0 hr.                          $13.00 per hr.

Variable Manufacturing Overhead     2.0 hr.                          $?per hr.

Fixed Manufacturing Overhead         2.0 hr.                          $?per hr.

2016 Budgeted Data:
Budgeted production, 2,000 large garden pots
Denominator Hours, 4,000 DLH. (Garden City Pots, Inc. applies overhead on the basis of direct labor hours.)
Budgeted variable overhead, $24,800.
Budgeted fixed overhead, $23,600.

2016 Actual Results:
Direct material purchases were 30,230 lbs. of resin which cost $157,196.
Direct material used was 29,830 lbs. of resin.
Direct labor costs $54,720 for 4,560 direct labor hours actually worked.
Total variable manufacturing overhead was $28,272.
Total fixed manufacturing overhead was $23,484.
Actual production was 1,900 large flower pots.

REQUIRED:

1. Calculate the following variances:
a. materials price and quantity variances.
b. labor rate and efficiency variances.
c. variable overhead spending(rate) and efficiency variances.
d. fixed overhead budget and volume variances.

2. Add a separate sheet within your excel workbook and change the name of the sheet to "Journal Entries". On this new sheet, prepare journal entries for:
a. material price and quantity variances.
b. labor rate and efficiency variances.

3. Add a separate sheet within your excel workbook and change the name of the sheet to "Causes". For the material price and quantity variances and labor price and efficiency variancesin the Analysis Report, state 3 reasons that could explain why each of these variances occurred. Use complete sentences and detailed explanations that is specific to your variance results. Do NOT use a "bullet point" format. If you just use a bullet point format without any explanation referencing the specific problem and variances you calculated, you will not receive ANY extra credit for this part of the assignment.

What IF Problem & Data :

WHAT IF ANALYSIS:
Check Figure: MPV: $6.000 Favorable
VOH EV: $0 No Variance

The "What If" part of the assignment will help you determine whether you have correctly used cell referencing in your spreadsheets. Change your date in the heading to: "For the Year Ended December 31, 2017."

In the actual costs portion of your data block page make the following changes (The standard data has NOT changed from the previous year.):

1. Due to a supplier going out of business, Garden City Pots, Inc. was able to
purchase material (resin) at a significant discount. They purchased 30,000 lbs. of resin at a total cost of $144,000.

2. Direct material (resin) used in production was 32,010 lbs. of resin

3. Factory management has replaced its aging machinery that was prone to breakdowns
with new computerized equipment. The new equipment has contributed to an overall
improvement in theefficiency of its production workers. However, Garden City Pots, Inc.also negotiated a new 2 year contract with the union shop which increased the actuallabor wage rate. Total direct labor hours for 2017 are 4,400 hours at an overall higher cost of $59,400.

4. Total actual variableoverhead for 2017 is $26,400.

5. Insurance and depreciation costs have increased due to purchasing the new
manufacturing equipment. Total fixed overhead for 2017 is $23,980.

6. Due to an increase in demand, total production for 2017 has increased to 2,200 unitsin 2017.

Your spreadsheet should automatically recalculate using the new data. You should not have to change any of the cell references or formulas for any of the variances. You are only changing the data block page.

Reference no: EM131298540

Razar sharp company purchased equipment on july

Razar Sharp Company purchased equipment on July 1, 2014, for $50,490. The equipment was expected to have a useful life of three years, or 7,560 operating hours, and a residual

What was the 2010 earnings per share

for 2010, ford corporation reported net income of $15000, net sales $200000; and average share outstanding 6000. there were no preferred stock dividends. what was the 2010 e

Determine the amount of total income tax expense

Roth Inc. has a deferred tax liability of $68,000 at the beginning of 2011. At the end of 2011, it reports accounts receivable on the books at $90,000 and the tax basis at zer

Create plan to reduce tax impact on foreign sourced income

Examine the income source rules discussed in the textbook and suggest at least two (2) legislative proposals that would prevent the manipulation of the source rules to elimi

Journal entry to record the issuance of the bonds

Prepare journal entry to record the issuance of the bonds and the related bond issue costs incurred January 1, 2009 Prepare a bond ammortization schedule up to and including J

Indicate a preference for pepsi

Each student was asked to indicate a preference for PEPSI versus other soft drinks, with the following results: 44 of the 125 at MIT indicate preferen

Snap repair service accepted the sellers counteroffer

On February 7, Snap Repair Service extended an offer of $75,000 for land that had been priced for sale at $85,000. On February 21, Snap Repair Service accepted the seller's co

Manufacturing overhead budget

Construct the company's manufacturing overhead budget for the upcoming fiscal year. Compute the company's manufacturing overhead rate (including both variable and fixed manu

Reviews

Write a Review

 
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd