Internet case-cranston construction company

Assignment Help Business Management
Reference no: EM131249315

Internet Case - Cranston Construction Company

Cranston Construction Company

The Cranston Construction Company is a small Mississippi construction company that undertakes building projects of a medium-to large-scale nature based on local and statewide needs. Although the company is capable of operating outside of its native state, it usually does not bid on out-of-state business. It maintains an office with a small staff and usually has several construction projects going on at the same time. Cranston has just received the contract for construction of a new humanities building on the campus of Northern Mississippi State University. 

Although the university and the State Building Commission are pleased to have completed negotiations for the new building, a significant task lies ahead for Mr. Daniel Cranston, the president of Cranston Construction Company. He must select a project manager and arrange for allocation of necessary resources for construction. He must then work with the project manager to develop a schedule for constructing the building in order to assist in the timely decision-making that involves financial needs and shifting of equipment from other job sites. 

Mr. Cranston decides that the detailed planning, layout, and scheduling can be provided by his project manager. The project manager will further be delegated total authority for the construction operations, the execution phase of the project. Based on past experience, Mr. Cranston makes up a job breakdown with approximate costs (shown in Table 1). Since the bid was for over $1 million, these costs represent company targets and are confidential. Although Cranston does not have significant experience with critical path analysis, he also makes up the activity list and time allowances (shown in Table 2). These time allowances represent the span between the earliest date he thinks each activity can begin and the latest date by which each should end. 

TABLE 1 Job Breakdown, Humanities Building

NumberActivity

1.Sales tax, bond, and insurance$22,000

2.General conditions25,000

3.Site work8,000

4.Reinforcing steel57,000

5.Concrete footings17,000

6.Concrete grade beams14,000

7.Structural concrete115,000

8.Structural and miscellaneous steel21,000

9.Masonry (includes stone)125,000

10.Roofing and sheet metal and insulation16,000

11.Doors and frames2,000

12.Architectural and miscellaneous metal and accessories5,000

13.Metal windows2,000

14.Lath and plaster24,000

15.Ceramic and marble5,000

16.Millwork34,000

17.Hardware9,000

18.Resilient floor10,000

19.Glazing and store front20,000

20.Acoustic ceiling10,000

21.Painting10,000

22.Elevator19,000

23.Carpet8,000

24.Finish grade and site work10,000

25.Clean up and move out4,000

26.Miscellaneous labor and materials20,000

Total Contract Price$612,000

TABLE 2 Project Activities and Duration

NumberActivityTime Allowed (days)

1.Sales tax, bond, and insurance35

2.Move in, tool house general conditions35

3.Clean, clear, excavate, and grade28

4.Reinforcing steel217

5.Concrete footings35

6.Concrete grade beams35

7.Structural concrete framing and slabs35

8.Structural and miscellaneous steel210

9.Masonry and stone231

10.Roofing and sheet metal80

11.Metal doors and frames203

12.Architectural and miscellaneous metal and accessories266

13.Metal windows231

14.Lath and plaster154

15.Ceramic tile and marble30

16.Millwork234

17.Finish hardware133

18.Resilient floor161

19.Glazing and store front203

20.Acoustic ceiling35

21.Painting161

22.Elevator119

23.Carpet35

24.Finish grade and site work28

25.Clean up and move out49

With these initial efforts, Mr. Cranston calls in Mr. Henry Nolton to discuss his appointment as project manager. After a lengthy discussion, Mr. Nolton accepts the appointment but makes the following statement to Mr. Cranston: 

"Your cost targets are probably reasonable; however, your time estimates and activity list do not really provide believable information. According to your figures, the project will be finished in less than 370 days and, therefore, you will not incur any penalty costs. However, if most of your time estimates are close to being correct, then I believe that the project will take longer than 370 days. As an example, let me point out that your duration times look like total time allowances rather than activity times. Take the activity of "architectural and miscellaneous metals." I'd say that this would take about two weeks to complete and could be one of the last items accomplished, probably following completion of all the stairwells." 

"Another major problem with your listing is that we'll be using reinforcing steel with all of the concrete work and, since it's a three-story building with a penthouse, we'll be doing concrete activities floor by floor. Thus, in order to schedule and control this job, I need to decide on an activity list which is based on the actual sequence of construction, floor by floor. floor concrete, the middle-floor columns and then the middle-floor concrete framing may be completed similar to the first-floor logic. After framing is complete, middle floor door frames, upper-floor concrete and lath and plaster activities can start. Lower floor masonry and middle-floor door frames must be complete before middle floor masonry can begin. Following lath and plaster, ceramic tile and marble can be placed. After the stairwells are complete, hardware, architectural, and miscellaneous metals can be installed." 

"As with the first two floors, upper-floor columns are emplaced following the upper floor concrete work. Next, upper-floor concrete framing can be completed. At this juncture, upper-floor door frames, roofing, and elevator activities can begin. Once these three activities are completed, plus completion of middle-floor masonry, the upper floor masonry, penthouse work, and ceiling work can be started. Following ceiling work, painting can begin and must be finished before tiling and carpeting which follow millwork. The millwork and finish grading start after upper-floor masonry and penthouse activities." 

Upon hearing this, Mr. Cranston decides to modify the activity list to make it more useful and more accurate. Working together, Mr. Cranston and Mr. Nolton put together Table 3 which gives all the relevant information. 

Table 3. Revised List of Activities and Times

LabelActivity Immediate

Predecessors Duration (days) 

ALayout, Excavate, and Grade - 28

BTax, Bond, & Insurance - 21

CMove In Tool House, General Conditions - 7

DGrade Beams A, B, C 11

EFoundation, Concrete footings A, B, C 11

FLower Floor Concrete D, E 10

GLower Floor Columns F 21

HLower Floor Frame G 35

IMiddle Floor Concrete H 12

JMiddle Floor Columns I 23

KMiddle Floor Concrete Frame J 37

LUpper Floor Concrete K 14

MUpper Floor Columns L 23

NUpper Floor Concrete Frames M 37

OUpper Floor Door Frames N 14

PRoof Slab, Beams, Sheet Metal N 21

QElevator N 21

RLathe & Plaster K 21

SUpper Floor Masonry, Interior Doors O, P, Q, II21

TPenthouse Steel, Concrete, and Masonry O, P, Q, II21

UCeilings O, P, Q, II42

VPaint U 42

WMillwork S, T 42

XFinish Grade, Sitework S, T 28

YTile & Carpet V, W 21

ZClean Up, Inspect, and Move Out X, Y, AA, CC, FF, GG2

AACeramic Tile & Marble R 14

BBStairwells H 35

CCHardware, Architectural and Miscellaneous Metals BB 14

DDLower Fl. Door Frames H 14

EELower Floor Masonry & Interior Doors DD 35

FFExterior Doors H 21

GGGlazing & Store Front H 35

HHMiddle Floor Dr. Frame K 14

IIMiddle Floor Masonry, Interior Doors EE, HH 35

1.Acting as Mr. Nolton's administrative assistant, draw a network to represent this project.  Then develop a table showing the activities from Table 3, their durations, their earliest start, earliest finish, latest start, latest finish, and slack times.  Identify the activities on the critical path.

2.Write a report to Mr. Nolton addressing the problems of project duration and specifying which activities may require the closest management attention. If it appears that the project will not be finished on time, identify the activities which might be considered for crashing if relevant time and cost information could be found.

Reference no: EM131249315

Questions Cloud

Contingency planning in strategy evaluation : Describe the seven-step process of effective contingency planning in strategy evaluation.
Why cyber defense should be taken more seriously : "Why cyber defense should be a priority" or "Why cyber defense should be taken more seriously", both on a personal and national level
Managed care approaches : Describe the alternatives "managed care approaches" a Medicaid agency could use to address cost, access and quality?
Models of organizational performance : Choose two models of organizational performance and compare and contrast them by evaluating their differences and similarities. From the first e-Activity, suggest ways performance measurements might be used by a company or an organization to evalua..
Internet case-cranston construction company : The Cranston Construction Company is a small Mississippi construction company that undertakes building projects of a medium-to large-scale nature based on local and statewide needs. Although the company is capable of operating outside of its nativ..
Why does gawain keep the green girtle and not pass it : Why does Gawain keep the green girtle and not pass it on to his host as agreed between them? Should he have kept the green girtle or given it to the host and gone willingly to meet his death at the Green Knight's hands
Write a review of one movie you have recently viewed : Write a review of one movie you have recently viewed. Include discussion of the following elements in your film review:- The literal and symbolic elements in the film.
Explain pressures associated with ethical decision making : How did corporate culture, leadership, power, and motivation affect Thomas' level of managerial hubris? Relate managerial hubris to ethical decision making and the overall impact on the business environment. Explain the pressures associated with ethi..
Write a critique presentation speech about the article : Write a critique 5-10 minutes presentation speech about the article including a PowerPoint. (5 pages speech). A minute about the writer (1/2 - 1 page). The rest of the presentation about the article.

Reviews

Write a Review

Business Management Questions & Answers

  Synopsis of the attention video

Provide a one page (12-pt. font, double-spaced) synopsis of the "Attention Video" referenced above. You are to try and incorporate some of the concepts gleaned from your text with what was observed in the video.

  How can bjc capitalize on its huge brand name recognition

What can it do to keep this information proprietary, given China's shoddy record of protecting intangible property rights? How can BJC capitalize on its huge brand name recognition and technological superiority?

  What do the implications of the challenges identified

What do the implications of the challenges identified in the case have for Burger King's strategy today and in the future?

  Calculate the number of no-swivel chairs produced in a day

The company wants to determine how many of each model should be produced on a daily basis to maximize net profit. Let X1 be the amount of swivel model to be produced in a day, and X2 be the amount of no-swivel model.

  Money in the conventional sense

Folks turning into our neighborhood would smile to see the beauty of that space, all the while feeling gratitude for the preservation of the sanctity of our neighborhood. It wouldn't make money in the conventional sense, but there is always more t..

  Explain why corporate governance fails

Explain why corporate governance fails, List some of the "indulgences" other than golden parachutes, poison pills, stock options, bonuses, pension plans, etc. (which are Provided to managers by the BOD) some managers have provided to themselves.

  How would you go about making given decision

Suppose that you. as founder of a business.- How would you go about making this decision? Would you pro-mote your son?

  Should the drama club cover explicit and implicit costs

Should the drama club cover explicit and implicit costs? Imagine that you are asked to consult with a drama club that puts on a play every year. The club asks you how much should we charge for tickets if we want to cover our costs?

  Explain can a nation gain from international trade

How do you support these assumptions? Can a nation gain from international trade even though not everyone is better off? How could this occur? The paper should be a minimum of two pages with a minimum of two references and associated in-text citati..

  Business department secretary

While she calls on the business faculty at General University her first stop is to chat with Frank the business department secretary

  Decision tree analysis-to undergo or not to undergo surgery

The transplant operation however, is a serious surgical procedure. 5% of patients die during the operation, with an additional 45% dying during the first year. 20% survive for 5 years, 13% survive for 10 years, and 8%, 5%, and 4% survive, respecti..

  Global economy caused or is causing price fluctuation

Give one example of Elucidate how the US economy or GLOBAL economy caused or is causing price fluctuation, also/or marketing strategy changes on a Product or Service.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd