Q. A Project was planned utilizing PERT with three time estimates. The expected completion time of the project was found out to be 40 weeks. The variance of the critical path is 9.
(a) Illustrate what is the probability that the project will be finished in 40 weeks or less?
(b) Illustrate what is the probability that the project takes longer that the project takes longer than 40 weeks?
(c) Illustrate what is the probability that the project will be finished in 46 weeks or less?
(d) Illustrate what is the probability that the project will take longer than 46 weeks?
(e) The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. Thus there would only be a 10% chance the project would take longer than this due date. Illustrate what should this due date be?
Why do you Assume that Best Buy, rather than one of Best Buy's big suppliers such as Sony or Panasonic, is considering eliminating rebates.
List key physical attributes of the services cape also their impact on customer service also value. Describe how the services cape sets the behavioural setting for your example.
llustrate what reasons might there be for using a single measure also illustrates what reasons might there be for using multiple criterions.
Briefly describe DIMCO's supply chain, What are the advantages that DIMCOO can gain by implementing supply chain management?
Give an example of a good decision you made that resulted in a bad outcome or an example of a bad decision you made that had a good outcome. Why was the decision considered good or bad?
You are required to produce a management report from the perspective of a consultant, reporting back to your client - the CEO of an overseas museum.
The coffee breaks are staggered, starting at 90 min into every shift. Meal breaks also staggered starting 3.5 hrs into every shift. Create a simulation model of this system. In the simulation, draw a simple layout of the above system.
Illustrate what is the percent change in multifactor productivity if Upton can reduce the energy bill by $1,000 per day without cutting production or changing any other inputs.
Compute average cycle time also normal time for each element. Then, calculate standard time for entire task. Decision Science Institute (DSI) promotes its annual national conference by mailing thousands of letters to various recipients.
Customers purchase the workstations every 3 years at an average cost of $1,500.00. Decide the average value of a loyal customer.
Many times a resource can become overloaded during a human resource project. State the resources you believe have been overloaded in your organization also give your opinion explain why resources become overloaded. Suggest some solutions to solve..
From reviewing historical information, you know which approximately 70percent of the patients will be on diets which allow brownies. Of those, 85percent will likely select the brownies. Approximately explain how many brownies should be forecast.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd