Assignment 1
1) Following are elements of a WBS for a project to build a bunk bed. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.
Cost($)
Rate ($/hr)
Time (hrs)
Research:
Jimmy' time
1
2
Dad's time
25
Materials:
Lumber 200
Hardware 45
Power equipment rental 65
Jimmy's time to acquire materials
3
Dad's Time to acquire materials
15
Construction:
Jimmy's time
8
20
Inspection:
Mom's time
10
0.5
2) Following is a listing of items to be considered in costing a PC game development project. Use this data to develop a parametric estimate of the cost of the project.
Cost ($) Rates($/hr) Time (hr)
Resources: Designers 30 100
Artists 25 200
Programmers 25 1000
Work Station 3000
Contracted Testing Group 50 100
Marketing Materials 1500
Fringe benefits: 30% of Direct Wages
Overhead: 70% of (Direct Wages + fringes)
3) For the table below
Task
Predecessor
Duration (in days)
Latest start
Earliest start
Float (slack)
A
Start
5
B
A,D
C
13
9
D
6
E
12
F
G
7
a) Create a PERT/CPM chartb) Identify the critical path and compute project durationc) Compute Latest Start, Earliest Start, and Float (Slack)
Verified Expert
The task file answered three problems related to project management. Work breakdown structure, project cost estimation and timeline were depicted in the answers. All three problems were resolved completely,
functional pure project and matrix team structuresthere are three different team structures. they are functional pure
Using the data provided in the Excel template develop an activity network diagram. Note an example is created for you in Excel that you can alter.
draw a project network from the following informationactivity predecessor durationa none 2b a 4c a 3d a 2e b 3f c 6g c
ITC505 - ICT Project Management Assignment. As a team, brainstorm and identify all stakeholders to the project. Then develop an appropriate communication plan
A moving block slides to a stop on a table due to friction. Is the momentum conserved? Why? Suppose that an object moving 5 m/s faster than a second object collides elastically with that second object. Now how much faster is the second object movi..
the it department is implementing a new crm solution to its corporate offices. the hardware currently in use is out of
Your task is to research and find appropriate tools for the clients listed above, developing a review of potential technologies that may be appropriate for each industry area and client in particular.
All the equipment that bands bring to the stage will need to be checked by fire marshals
Why are deliverables such an important output of project execution? What are some of the typical problems that project teams face during project execution?
Outline how you will approach your outsourcing project through developing a WBS. For each task or work package show the expected duration and the role and organisation that will perform each task.
Draw a circle around the most frequently occurring connections in your diagram. What did you learn about how college students view marketing?
What is the firm's projected days sales outstanding (DSO)?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd