The company has a demand of 45,000 components pa. They cost $4.50 each. There is no lead time between order and delivery, and ordering costs amount to $100 per order. The annual cost of holding one component in inventory is estimated to be $0.65.

A 0.5% discount is available on orders of at least 3,000 components and a 0.75% discount is available if the order quantity is 6,000 components or above.

a) what is the company’s EOQ?

b) What is the minimum TMC?

c) How much time will elapse between orders?

d) How many orders per year will be place?

Reference no: EM131368713

Questions Cloud

What is contract and three general types of contracts : Discuss variations in contracts and its causes, results and pricing? Bespoke vs Standard contracts. Discuss andcompare and contrast the advantages and use of each type ? Discuss the procurement four processes in light of the Pmbok? What is a “CONTRAC..
Why does workplace violence occur : Why are some people more affected by stress than others? What job characteristics are most likely to result in high levels of stress? Why should organizations be concerned about employee stress? Why does workplace violence occur?
Blue collar supply chain management process : Discuss at least three different activites that Honda (Civic) has to deal with in their "blue collar" supply chain management process (ie. Suppliers, assembly line workers, raw ingredients, resellers, forklift drivers, trucking companies, etc.) Expla..
Collaborative project procurement arrangements : Discuss the collaborative project procurement arrangements, its needs and advantages compared to the traditional procurement system. Give examples of the project collaborative arrangements procurement?
How much time will elapse between orders : The company has a demand of 45,000 components pa. They cost $4.50 each. There is no lead time between order and delivery, and ordering costs amount to $100 per order. The annual cost of holding one component in inventory is estimated to be $0.65. Wha..
How does personal selling affect the final consumer : How does Personal Selling (Relationship Selling) affect the final consumer who buys your product (Honda Civic). What kind of 'white collar" sales efforts from ALL the different suppliers was required to created the final product?
What will be our average number of boxes on hand : Our home construction company buys nails in 15-pound boxes. We use an average of 2008 boxes a year. The vendor that makes the nails can produce 45 boxes per day while our usage is 4 boxes per day. It costs $2.00 to place the typical order. Annual car..
What is the statistical safety stock : If the standard deviation of demand is six per week, demand is 50 per week, and the desired service level is 95%, approximately what is the statistical safety stock? what is a system theory and how can it be used to effectively integrate an organizat..
Make a kanban of finished good products : Jerry is trying to decide how large to make a Kanban of finished good products for a high paying customer so he can fulfill the orders quickly. This customer places orders totaling an average 500 pieces per month (4-week period, 5 days per week). Jer..

Reviews

Write a Review

Project Management Questions & Answers

  Determine the best action to take using the laplace

Check for dominance and determine the best action to take using the Laplace, Hurwicz(show graph), maximin, minimax regret and maximax.

  What is the annual cost of measurement

117345 Project Draw a timetable for measurement, selection and offspring birth for each selection strategy and What is the annual cost of measurement in each scenario?

  Explain how your business could use the internet

Explain how your business could use the Internet to give customers an opportunity to provide feedback to management.

  Find the operating cash flow for project

Operating cash flow for the project - what is the operating cash flow for this project?

  What is the projected project cost and duration

What is the projected project cost? What is the projected project duration? What is the critical path (or paths)? What task or tasks were crashed?

  Project procurement and contract managementpurchasing

project procurement and contract managementpurchasing functionsintroductionin a large organization a specialized

  Break-even pointdollar sales volumeproject effectrocky

break-even pointdollar sales volumeproject effectrocky mount metals company manufactures an assortment of wood-burning

  Which country will export steel and which will export corn

Review the arguments both pro and con on NAFTA. What is the empirical evidence so far?- Which country will export steel? Which will export corn? Explain.

  Explain a recent project identify the problems associated

explain a recent project. identify the problems associated with the project and show how project management principles

  Computing payback period-npv and irr

The tax rate is 37 percent, and the cost of capital is 13 percent. Compute the payback period, the NPV and the IRR.

  Prepare a plan to adjust the termination time of the

prepare a plan to adjust the termination time of the project to accomodate the issues presented.during the

  Business communication what role does conflict play in

business communication what role does conflict play in group communication?explain what role does conflict play in

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd