Consider a project consisting of four activities A, B, C, and D.
a) A and B, the first activities of the project, can be started simultaneously.
b) C can be started only after A is completed.
c) D can be started only after B is completed
Suppose the activity times for the activities are A = 2 weeks, B = 2 weeks, C = 2 weeks, D = 2 weeks.
a) How long does the project take to complete?
b) We ask the engineer working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineers tell us that activity A takes 1 week 50% of the time, and 3 weeks 50% of the time. How long does the project now take to complete (on average)?
c) We now also ask the engineer working on activity B to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineer now tell us that activity B takes 1 week 50% of the time, and 3 weeks 50% of the time. How long does the project now take to complete (on average)? [ASSUME THAT BOTH ACTIVITY A AND ACTIVITY B ARE UNCERTAIN]
Also indicate whether the items in error will be overstated
: The balance sheet as of February 28. Also indicate whether the items in error will be overstated or understated.
|
Nonprofessionals can do the work of professionals
: If we believe nonprofessionals can do the work of professionals, aren't we setting them up for failure?
|
The emission or absorption of visible light
: An imaginary atom has just 3 energy levels: 0 eV, 1 eV, and 3 eV. Draw an energy-level diagram for this atom. Which portions involve the transitions involve the emission or absorption of visible light
|
Write an essay on the topic dr google health risk
: Topic : Dr. Google Health Risk
|
How long does the project take to complete
: How long does the project take to complete? We ask the engineer working on activity A to factor in uncertainty in activity times and to provide better estimates of the activity times. The engineers tell us that activity A takes 1 week 50% of the time..
|
The balance in the unearned fees account
: The balance in the unearned fees account, before adjustment at the end of the year, is $38,375. Journalize the adjusting entry required if the amount of unearned fees at the end of the year is $17,200.
|
Calculate the circular velocity of jupiter
: Calculate the circular velocity of Jupiter and the Earth in units of km/s. (use .67 x 10-11 m3/kg/s2, kg, .2 AU, and .0 AU)
|
Calculate the amount of heat flowing per second
: Calculate the amount of heat flowing per second through a cross-section of the bent part if the total heat taken out per second from the end at 100°C is 130 J.
|
What is socialization
: How does an organization ensure a fit between its associates’ values and its organizational culture? How does an organization choose groups or teams? (a) What is socialization? (b) Describe a situation in which you were socialized into an organizatio..
|