Reference no: EM131031220
Long-Term Construction Contracts:
Forman Company has contracted to build a dam over a period of 4 years for $3,000,000. Information relating to the performance of the contract is summarized as follows:
1. a. Compute the profit or loss for each year of the contract under the percentage-of-completion method. Enter losses as a negative number.
2013
|
2014
|
2015
|
2016
|
$
|
$
|
$
|
$
|
b. Compute the profit or loss for each year of the contract under the completed-contract method. Enter losses as a negative number.
2013
|
2014
|
2015
|
2016
|
$
|
$
|
$
|
$
|
2. a. Prepare the relevant sections of the income statement for each year under the percentage-of-completion method
|
2013
|
2014
|
2015
|
2016
|
Construct Revenue
|
$
|
$
|
$
|
$
|
Construction Expense
|
|
|
|
|
Gross Profit (loss)
|
|
|
|
|
Prepare the relevant sections of the ending balance sheet for 2013 under the percentage-of-completion method.
Balance Sheet
|
Partial
|
12/31/13
|
Current Assets
|
XXXXXXX
|
XXXXXXXX
|
Accounts Receivable
|
XXXXXXXX
|
$
|
Inventory
|
XXXXXXXX
|
XXXXXXXX
|
Construction in progress
|
$
|
XXXXXXXX
|
Less:Partial Billings
|
$
|
XXXXXXXX
|
Costs and recognized profit not yet billed
|
XXXXXXXX
|
$
|
Prepare the relevant sections of the ending balance sheet for 2014 under the percentage-of-completion method.
Balance Sheet
|
Partial
|
12/31/13
|
Current Assets
|
XXXXXXXX
|
XXXXXXXX
|
Accounts Receivable
|
XXXXXXXX
|
$
|
Inventory
|
XXXXXXXX
|
XXXXXXXX
|
Construction in progress
|
$
|
XXXXXXXX
|
Less:Partial Billings
|
$
|
XXXXXXXX
|
Costs and recognized profit not yet billed
|
XXXXXXXX
|
$
|
Prepare the relevant sections of the ending balance sheet for 2015 under the percentage-of-completion method.
Balance Sheet
|
Partial
|
12/31/13
|
Current Assets
|
|
|
Accounts Receivable
|
|
$
|
Inventory
|
|
|
Construction in progress
|
$
|
|
Less:Partial Billings
|
$
|
|
Costs and recognized profit not yet billed
|
|
$
|
b. Prepare the relevant sections of the income statement for each year under the completed-contract method. Enter losses as a negative number.
Income Statement (Partial) Years 2013 through 2016
Prepare the relevant sections of the ending balance sheet for 2013 under the completed-contract method.
Current Assets
|
|
|
Accounts Receivable
|
|
$
|
Inventory
|
|
|
Construction in progress
|
$
|
|
Less:Partial Billings
|
$
|
|
Excess of Costs over related billings
|
|
$
|
Prepare the relevant sections of the ending balance sheet for 2014 under the completed-contract method.
Current Assets
|
|
|
Accounts Receivable
|
|
$
|
Inventory
|
|
|
Construction in progress
|
$
|
|
Less:Partial Billings
|
$
|
|
Excess of Costs over related billings
|
|
$
|
Prepare the relevant sections of the ending balance sheet for 2015 under the completed-contract method.
Current Assets
|
|
|
Accounts Receivable
|
|
$
|
Inventory
|
|
|
Construction in progress
|
$
|
|
Less:Partial Billings
|
$
|
|
Excess of Costs over related billings
|
|
$
|
What is the breakeven point in dollars
: An entrepreneur, Mike Smith, is getting ready to launch a company that offers professionally recorded, five minute videos of Karaoke performances. Mike anticipates the recording equipment to cost $225,000 and the material and labor to come to $16 per..
|
There are seven mistakes when managing processes
: There are seven mistakes when managing processes, arguing that failure to manage processes is ultimately a failure to manage the business. In 2-3 sentences for each mistake, define/explain any 4 of the 7 mistakes.
|
Given that projects are modeled as networks or flows
: Given that projects are modeled as networks or flows, what makes project flows the same or different from other processes we have studied in operations? There are many examples of projects that occur in our lives. Come up with an example of a project..
|
Patient is classified either resident patient or outpatient
: Given the information below, create the fully labeled Crow's Foot ERD using a specialization hierarchy where appropriate (use Visio). The ERD must contain all primary keys, foreign keys, and main attributes. Business rules are defined as follows: At ..
|
Forman company has contracted to build a dam over
: Forman Company has contracted to build a dam over a period of 4 years for $3,000,000. Information relating to the performance of the contract is summarized as follows:
|
Statements is best about process management
: Which one of the following statements is best about process management?
|
How many different teams of3students are possible
: There are6students in a small class. To make a team, the names of3of them will be drawn from a hat. How many different teams of3students are possible?
|
Statements about planning projects is false
: Which one of the following statements about planning projects is FALSE?
|
Demings work in the area of quality assurance
: Which of the following statements best describes the underlying philosophy of Deming’s work in the area of quality assurance?
|