A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000 and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI.

Reference no: EM13960322

Questions Cloud

Using the eight steps for developing selection measures : Using the eight steps for developing selection measures outlined in your book, develop a time line for creating a new selection measure. If you were to begin today, explain when your new selection measure might be ready for use. Be realistic in your ..
What does literacy mean to douglass : Why is Douglass so upset in this excerpt from his narrative? What does literacy (reading and writing) mean to Douglass? Give at least two examples of Douglass's resourcefulness
Determine the ten day optimal production mix : Baba Furniture Company employs four carpenters for 10 days to assemble tables and chairs. It takes two peron-hours to assemble a table and 5 person-hour to assemble a chair. Customers usually buy one table and four to six chairs. Determine the 10-day..
Describe possible standards that might be used : Briefly describe possible standards that might be used for: The use of control constructs in C, C#, or Java;
Find the cost and schedule variances and the cpi and spi : A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000 and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI.
Gill manufacturing uses a predetermined : Gill Manufacturing uses a predetermined overhead allocation rate based on a percentage of direct labor cost. At the beginning of the year, Gill estimated total manufacturing overhead costs at $1,010,000 and total direct labor costs at $840,000. In Ju..
Deliverables are currently-risk of falling behind schedule : Team Failure A virtual team's deliverables are currently at risk of falling behind schedule. The virtual team leader must determine whether the poor team performance is due to individual team member performance or cultural differences. Discuss the va..
Dunber distribution markets cds ofnumerous performing artist : Dunber Distribution markets CDs ofnumerous performing artist. At the beginning of March, Dunbar had in beginning inventory 3,713 CDs with a unit cost of $10. During March, Dunbar made the following purchases of CDs
Describe what occurs in the fetch-execute cycle : Describe what occurs in the fetch-execute cycle of a von Neumann machine. Explain what part the system clock plays in this and how this has limited improvements in the performance of processors.

Reviews

Write a Review

 

Operation Management Questions & Answers

  Main factors contributing to the global economic growth

One of the main factors contributing to the global economic growth has been that more third world countries have joined the global market. We know there are economical gains but need to specify what these political gains are. There are still some cou..

  Reimbursement and the revenue cycle

Reimbursement and the Revenue Cycle- Describe what reimbursement means to this specific healthcare organization. What would happen if services were provided to patients but no payments were received for these services

  Project management-product design-process strategy

Investigate the degree to which human resources are related to the other factors (project management, product design, process strategy, location decisions, layout decisions, etc.). Identify inefficiencies in the way that human resources are utilized ..

  What is the storage space constraint

Profit for each big shelf is $300 and for each medium shelf is $150. What is the storage space constraint?

  What are the minimum number of servers required

customers per hour and an average service time of 18 minutes per customer. What are the minimum number of servers required to avoid an overloaded system?

  What is the current multifactor productivity

What is the current multifactor productivity?

  The optimal order quantity

A mail-order house uses 18,000 boxes a year. Carrying costs are 60 cents per box a year, and ordering costs are $96. The following price schedule applies - The optimal order quantity.

  Identify goods-producing or service-providing organization

Identify a goods-producing or service-providing organization and discuss how it might make aggregate planning decisions

  A company manufactures a product using two machine cells

A company manufactures a product using two machine cells. Each cell has a design capacity of 250 units per day and an effective capacity of 230 units per day.

  Starbucks refines the customer experience

Starbucks the Seattle-based company that popularized the "coffee culture" is brewing up higher sales through new beverages and new cafes in global markets. A stop at Starbucks has become part of many consumers' daily routines. Some are attracted by t..

  What are the upper and lower control chart limits

The defect rate for a product has historically been about 2.4%. What are the upper and lower control chart limits for a p-chart, if you wish to use a sample size of 100 and 3-sigma limits?

  Basing request on explicit or implied support from superiors

Basing a request on explicit or implied support from superiors is known as using the principle of:

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd