Q. The subsequent information is available about a project:
Activity Activity Time (Weeks) Immediate Predecessor(s) A 3 ---- B 4 ---- C 6 A D 9 B E 6 B F 10 C,D G 8 D,E H 9 G,F
a) Draw the network diagram.
b) Find out the critical path also estimate the project's completion time. Explain why is it important for a project manager to identify the critical path?
c) Compute the slack for each activity. Explain why is it important for a project manager to know the slack of activities?
Illustrate what is the break-even point. Explain how many units must be sold to make a profit of $6000.00. Explain how many units must be sold to average $25 profit per unit? $50 profit per unit? $150 profit per unit.
Due to variations in processing times due to the size and length of the bracelets, it has been decided to keep 25 percent of the needed inventory as safety stock. Explain how many kanbans card sets are needed.
This solution describes the concepts of shadow price and maximization problem, differences between graphical and computer-based methods of solving LP problems differ, and sensitivity analysis in decision making process.
The investor hires a researcher who randomly samples 19 warehouses that are for sale and finds that the mean price per square metre is $316,70, with a standard deviation of $12.90. If the researcher uses a 5% level of significance, what statistica..
The last event, although forecasted to have 1,000 participants, resulted in the attendance of only 950 participants. Illustrate what are the utilization and efficiency of the conference facility.
subsequent tabulations are actual sales of units for 6 months and a starting forecast in January. Compute forecasts for remaining 5months using simple exponential smoothing with.
Discuss whether Starbucks would be considered a premium brand. Comprise competitors in your analysis. Is Starbucks' strategy one of product or experience.
Job shop makes products in batches ranging from 1 unit to 1 hundred units. Assuming capacity is not a limitation on either machine, on which batches should Machine Center B be used.
Illustrate what is the yearly setup and holding cost for this item. Assume instead of small bolts we were talking about a bulky item such as packaging materials. Illustrate what problem might there be with your analysis.
Explain how do vision and mission statements of rating organization affect explain how they view social responsibility.
Write a five-page paper discussing "Global Operations Management, Global Operations Manufacturing. What are the benefits/downsides of creating manufacturing operations outside the United States?
This was expected to cost a total of $8,501,000. To date they have spent $5,001,000 on the superstructure. Computes the schedule variance, schedule performance index also cost performance index for the project to date.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd