Find network diagram and identify all the path

Assignment Help Project Management
Reference no: EM1343312

Network diagram and identify all the path

Given the information in the following table

Activity Duration Predecessor
a 4 None
b 6 a
c 4 a
d 2 c
e 4 b
f 5 b, d
g 3 c
h 4 f,g
i 2 e, h

a. Construct the network diagram

b. Identify each activity's EST, EFT, LST adn LFT

c. Find all paths. Which path is the critical path?

d. Determine the slack each activity?

e. How long will it take to complete the project?

Reference no: EM1343312

Questions Cloud

Find the critical path : Quantitative analysis - Networks, PERT What is the Critical Path and what is the expected completion time
Show the aspects of project management : Aspects of project management and the most time consuming - In your organization, what aspects of the change management process are the most time-consuming?
How project managers can control projects : List and describe the different levers that project managers use to exert control over projects and provide an example of how each lever can be used in project control.
Prepare a project file for the project : Prepare a project file for the project and make any necessary changes to the Environment options and choose a calendar for the project
Find network diagram and identify all the path : Find all paths. Which path is the critical path and determine the slack each activity and how long will it take to complete the project
Construct the network diagram : Construct the network diagram and find each activity's EST, EFT, LST adn LFT
Describe how a work breakdown structure can be useful : Describe how a work breakdown structure can be useful during the estimating of a project budget
Relational database management system : explain advantages to using a Relational Database Management system
Calculate economic order quantity : Calculate economic order quantity - How many tires should Rocky Mountain order each time it places an order

Reviews

Write a Review

Project Management Questions & Answers

  Explain general plan and steps involved to project success

Explain the general plan and the steps involved to achieve project success and show the critical elements of the plan and what the key success factors will be for the project success.

  Developing a schedule for introducing a new product

You just have been instructed to develop a schedule for introducing a new product into the marketplace.

  Characteristics of effective project manager

Fully explain and describe the functions and necessary characteristics of an effective project manager.

  Cultural norms affect project from a positive perspective

How did the cultural norms affect this project from a positive or negative perspective?

  Advantages and disadvantages of inspection

What are the advantages and disadvantages of workers having more control over the inspection of their own work?

  Cost in project management

Cost in Project Management - Why is it important for management to understand the forecasted cost at completion (FCAC)?

  Process of identifying and assessing project risks

What is a risk matrix and how can it help with the process of identifying and assessing project risks?

  Show the project management skill

what will work most effectively with them is a good skill or talent for a leader to have. Why is this, especially for a project manager?

  Write paper on inventory management system

Write paper on Inventory Management System.

  Selecting project as a risk averse investor

Assume the risk-free rate of return is 2% and the market risk premium is 8%. If you are a risk averse investor, which project should you choose?

  Evaluate the use of complex models of project risk

Critically analyse the concept of risk; discuss how it can be measured and ranked and outline how a project risk management strategy may be constructed.

  Constructing a network for activities

The activities that are necessary to build one of these experimental weed-harvesting machines are listed in the following table. Construct a network for these activities.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd