PMI chapter meeting

You are attending your local PMI chapter meeting. Fortunately, it draws project managers from many different industries, not just technology. In fact, several members have experience managing projects across industries.

Respond to the following questions to join in the discussion:

How important is it for a project manager to have expert judgment in the subject matter of the project?

Must an IT project manager be an expert in the technology that is being implemented?

Be prepared to support your position, whether you agree or disagree.

Reference no: EM1343127

Questions Cloud

Cost in project management : Cost in Project Management - Why is it important for management to understand the forecasted cost at completion (FCAC)?
What does the term maturity mean in project management : Ensuring Success on Projects - What are some issues that project managers need to be mindful of during the final stages of projects?
Manager versus leader : Explain what do you feel are the most important qualities for a leader to possess to be effective and do you feel that a person can be both a leader and a manager, or are they mutually exclusive roles
How the project will be measured for success : Project charter: Using the above scenario, prepare a project charter. Include the problem statement, justification for the project, and how the project will be measured for success.
Expert judgment in the subject matter of the project : How important is it for a project manager to have expert judgment in the subject matter of the project and Must an IT project manager be an expert in the technology that is being implemented?
Duration estimation techniques in project management : In a short response, describe the advantages and disadvantages for each of the five techniques. Include an example of when it is appropriate to use each technique.
Explain how should a project manager handle a situation : Explain how should a project manager handle a situation in which the functional manager or employee appears to have more loyalty to his profession, discipline, or expertise than to the project
What happens if one contractor has higher salary levels : What difficulties can occur if the contractors have decided on work assignments, and what changes may be necessary if problems occur?
Find all risks and rate each risk : Find all risks and rate each risk - Select two of the highest risks. Describe why these are considered high risk, and explain their potential effect on the project.

Reviews

Write a Review

 

Project Management Questions & Answers

  Calculate annual project free cash flow

Evaluate the project's annual project free cash flow for each of the next five years

  Pros and cons to the systems view approach

What are the pros and cons to the systems view approach?

  Constructing a decision tree

Sue will see a loss of $90,000. of course, she could always decide not to build the retail store. Construct a decision tree.

  Determining earliest-latest and slack times for activity

The following are activity times for the project. Find the earliest, latest, and slack times for each activity. Then Find the critical path.

  Critical path and critical project requirements

Critical path and critical project requirements could indeed be separate issues. This is why you need to determine Priorities (Constrain, Enhance, and Accept) as we discussed last week.

  Preparing a business case for a project

What is involved in preparing a business case for a project?

  Project life cycles differ among organizations

What is a project life cycle? How do project life cycles differ among organizations? To what degree does the structure of the project lifecycle used by the organization affect the project manager's job?

  Form of business organization

What form of business organization would you choose for this venture, and why? Outline the advantages and disadvantages of each of the three major types of business in this particular context.

  Preparing a responsibility matrix

Prepare a responsibility matrix and clarify all roles.

  Advantages of using a high-moderate-low risk

What are the advantages of using a high-moderate-low (or red-yellow-green) risk designation as opposed to assigning quantitative numbers to each cell and risk level ?

  Impact of risk on a project

Explain how risk has impacted a project that you have been associated with as a team member or project leader.

  Ways in which project selection affects risk

What are some ways in which project selection affects risk? How can these risks can be reduced?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd