Elements of a potential wbs

Assignment Help Basic Computer Science
Reference no: EM13938180

Q1: Level 1 WBS Elements With reference to the referenced example job drawings list at least 5 Level 1 Elements of a potential WBS.

Q2: Level 2 WBS Headings Select 5 of the Level 1 Elements from Q1 and list potential Level 2 Headings under each. Use of the example DPTI WBS can be made for typical headings, however relevance to the example drawings must be maintained.

Q3: Level 3 WBS ItemsSelect at least 2 of the Level 1 Elements and their respective Level 2 Headings and make a comprehensive listing of Level 3 Items under each that exist on the drawings.

Q4: Referencing the source of your answers

Mark up the specific drawing detail / note (on the drawing) with a reference and include this in the table of answers to demonstrate the source of the your answers to questions 1-3.

Q5: Progress Claim Format

One of the uses of a well structured WBS is the recording and valuing of progress on the project. Research the format that this valuation may take and complete this format with a maximum of 20 cost items (Level 3 items). It is expected that you will need to research the following in preparation for your answer

  • What is the purpose of a progress claim
  • What key information should be included
  • What summary information should be presented

NOTE: The cost items only need to be examples of a format and no specific accuracy of 

Complete a WBS and quantity measurement for drainage elements (structures and culverts only) including appropriate units from the drawing "SEMP-J150-L1-001 Rev C". 

Further complete a WBS and quantity measurement for signage elements including appropriate units from the drawing "SEMP-J150-L1-003 Rev C".

Q7: Earthworks Calculation

For the given table of measured cross sections calculate the total cut and fill quantities.

The answer should incorporate a complete tabular calculation.

Calculate the cut to fill quantity and the import / export volumes.

Q8: Site inspection

Source and provide photos of a typical urban intersection (plan and street view). By viewing the photos of the site list at least 5 scope items that may be required that are not described on the design drawings and describe your basis for including them.

Q9: Summary of Project Scope for Review purposes

The effective briefing of management participants in tender reviews is an important skill. The success of the review process in the workflow may depend upon the summary of scope and existing conditions. With reference to the example drawings from Tutorial 1 and the above photos prepare a one page summary to brief the review teamList the different resource types commonly used in first principle estimates and provide at least 5 examples of resources for each type. For 2 of the 5 examples of each type describe the work activity / role that this resource may play in a typical civil construction project.

Q11: First principle estimate

Prepare a first principle estimate for the following activities

The following client provided WBS is to be used as the basis of pricing

Item Description Qty Unit Rate Amt

1 General Civil Works

1.1

Excavation to stockpile of soil 

materials, lead = 1km 500 m3

1.2

Supply and place 250mm of PM1/20 

gravel to hardstand 10,000 m2

Subtotal - General Civil Works

PROJECT TOTAL

Assume the following cost rates for resources

Resource Name Resource Descriptionf 6

Q10: Resource Types

List the different resource types commonly used in first principle estimates and provide at least 5 examples of resources for each type. For 2 of the 5 examples of each type describe the work activity / role that this resource may play in a typical civil construction project.

Q11: First principle estimate

Prepare a first principle estimate for the following activities

The following client provided WBS is to be used as the basis of pricing

Item Description Qty Unit Rate Amt

1 General Civil Works

1.1

Excavation to stockpile of soil materials, lead = 1km 500 m3

1.2

Supply and place 250mm of PM1/20 gravel to hardstand 10,000 m2

Subtotal - General Civil Works

PROJECT TOTAL

Assume the following cost rates for resources

Resource Name Resource Description Cost Unit lab Labour 50.00 hr exc30 Excavator 30t 130.00 hr grader Grader 140 equiv 140.00 hr truck Tandem tipper 85.00 hr roller 12t smooth drum 95.00 hr w/c 12,000l water cart 100.00 hr PM2/20 Quarry Rubble 15.00 tonne

Q12: Types of risk

Briefly y describe the difference between inherent and contingent risk.

List and describe a contingent risk that may apply to the first principle estimate in Q11.Q13: Inherent Risk Ranging

Provide 3 example direct cost items (Level 3) and insert into the example layout provided. Undertake ranging of the quantity and rates with discussion of the basis of this ranging. Calculate statistically possibly L-ML-H amounts for each item.

Q14: Contingent Risk Identification

Provide 3 example examples of contingent risk items for a roadworks project. Insert a range of costs for each (just insert "example" data) and discuss the basis of this ranging. 

Indicate a percentage likelihood for each item based upon your approach to the ranging and the nature of contingent risk item selected.

Reference no: EM13938180

Questions Cloud

Responsibility of the engineer project manager : Discuss the above statement and the role and responsibility of the Engineer Project Manager in advising the client through the overall strategic decision process in order to select the most appropriate procurement system for either a private or pu..
How pressure changes help with inhalation and exhalation : Trace the pathway of air through the respiratory system. Discuss how pressure changes help with inhalation and exhalation.
How would lowering the estimate of warranty liability affect : How would lowering the estimate of warranty liability affect the current ratio? How should Jim respond to his boss? Given that Jim's employer is a publicly-traded corporation, what safeguards should be at Jim's disposal?
Analyse the threat or opportunity : Describe any biases that are relevant and need to be avoidedEvaluate the financial impacts of the decision (or of not making the decision) in terms of costs, revenue and/or service levels
Elements of a potential wbs : Q1: Level 1 WBS Elements With reference to the referenced example job drawings list at least 5 Level 1 Elements of a potential WBS. Q2: Level 2 WBS Headings Select 5 of the Level 1 Elements from Q1 and list potential Level 2 Headings under each. ..
Prepare the journal entry to record the purchase : Prepare the journal entry to record the purchase. By how much did this purchase increase or decrease the excess of current assets over current liabilities?
Investment where you receive a cashflow : Consider an investment where you receive a cashflow of +$400,000 per year for the first 5 years (times 1,2,3,4,5) and then $300,000 per year for the next 5 years (times 6-10), then $200,000 per year for the next 5 years (times 11-15) and then $100..
Can you find a bug in this program : Can you find a bug in this program and then fix it so that it won't have an infinite loop?
Understanding or analysing the knowledge situation : What are the possible models for understanding or analysing the knowledge situation. What is the knowledge or intellectual capital that needs to be managed or process

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Demonstrate an understanding of existing strategic impact

Demonstrate an understanding of existing and emerging information technologies and strategic impact on organizational operations. Explain how to develop reasoned responses to the major forces shaping the role of IT in organizations competing in a ..

  Provide an explanation of hashtables

Provide an explanation of hashtables, including a description of a realistic scenario that could be solved with the application of a hashtable

  Problem regarding the constrained optimization

A company produces and sells four grades of industrial solvents - A, B, C, and D. The selling price per gallon of each grade of solventis $6.40, $5.00, $4.20, and $3.50 respectively.  Because of demand limitations, the company can sell at most 100..

  Components-protocols to support management of certificates

A Public Key Infrastructure (PKI) is a collection of components and protocols to support the management of certificates that bind a user name to a public key.

  Collaboration systems at isuzu australia limited

Summarize the main reason(s) that prompted Isuzu Australia Limited (IAL) to use collaboration technologies. Identify the platform that IAL chose as an online portal and content management system, and describe the main reason(s) why IAL chose such ..

  Probability-first game joe enters is fourth game of season

Joe Coledge is the third-string quarterback for the University of Alatoona. What is the probability that the first game Joe enters is the fourth game of the season?

  Explain how to generate array of random numbers

For some general variables L and U, write a comment that explains how to generate a 1 x N array of random numbers whose values are between L and U.

  How many and what type of domain controllers

How many and what type of domain controllers do you recommend for each campus? How would you justify this recommendation?

  Set the character variable r=0

Write a small program that will set the character variable R=0

  Summarize the different types of data storage technology

Discuss common input / output technologies. Summarize the different types of data storage technology.

  Prove the identity of the following boolean equations

Prove the identity of the following Boolean equations, using algebraic manipulation: AB + AB' +A'B' = A + 'B 2). Reduce the following Boolean expression to a minimum number of literals: A' B( D' +C' D) + B(A + A'CD) NEED HELP WITH THIS TWO QUESTIO..

  Display each of these constants in decimal

Display each of these constants in decimal, in hexadecimal, and as a character usingcout. Your program will have a total of ninecoutstatements.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd