Problems 5-1 through 5-2 (Graded)

5-1 Earned Value Calculation

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.

Activity C is finished. It finished 2 weeks late. It cost $100,000. And it was planned to have cost $110,000.

Activity D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It was estimated to cost $450,000 when finished. It is approximately 55% complete.

Using this data, calculate the following.

1. What are the PV, EV, and AC for each of the activities and the complete project?

2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project?

3. Assess the project performance to date? Do you get to have the celebration?

Reference no: EM13273401

Questions Cloud

Fantasy sex normal or problematic : Most of us have from time to time fantasized about sexual events they we really do not want to occur. For example research tells us that over 30% of females fantasize about being raped, forced top have sexual intercourse or sexually assaulted. Where ..
Technology and globalizationgen : Technology and GlobalizationGEN499 wk5 dq1
Discuss how managed care sales and marketing : Discuss how managed care sales and marketing have evolved over recent decades, and how these may possibly evolve over the decades ahead.
Same time increasing accessibility of healthcare services. : Discuss which strategies you think will be effective in eliminating waste, control the costs of health services, while maintaining quality of those services and at the same time increasing accessibility of healthcare services.
Earned value calculation-what are the PV-EV and AC : Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule. Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete...
The sistine chapel appears in present-day culture : Consider how and where imagery from the Sistine Chapel appears in present-day culture. How has some of the imagery in the chapel become pop-culture icons?
What is general and special revelation : What is general and special revelation? What is the purpose of revelation?
Statements taken in violation of the miranda rule : Statements taken in violation of the Miranda rule may be used to impeach a defendant that testifies inconsistently with his confession. However, an involuntary confession cannot be used for impeachment. What justifies the distinction between these tw..
Stringmethod compareto to compare two strings : Write an application that uses Stringmethod compareTo to compare two strings i

Reviews

Write a Review

 

Other Subject Questions & Answers

  Media reporting of terrorist activities

Review at least four popular media sources—newspaper, radio, television, the Internet, and so on—and review the reports of terrorist organization activities and events.

  Just given a new project to pilot and rollout

Your department was just given a new project to pilot and rollout to your organization. The project involves assembling a cross-organizational team that will be given the responsibility for reviewing different payroll systems that Faraday Enterprises..

  Perspective on culture and diversity

According to the developmental theory, how do the interactions between culturally diverse groups affect their ethnocentric perspective of the other?

  Memory-perception-retrieval

Describe primary memory? What are the characteristics of primary memory?

  At a certain temperature-highest power possible

At a certain temperature T1, a (1.717x10^2) mm rod of a copper-nickel alloy has a resistivity of (2.7000x10^-7) ?-m. For pure copper, the resistivity at 0°C is 1.58 x 10-8 ?-m and the change in resistivity per degree increase in temperature is 6.50 x..

  Eliminate experimental bias based on both experimenter

In explaining study to physicians also nurses who will participate, what steps should researcher take to eliminate experimental bias based on both experimenter expectations also participant expectations.

  Where was all the hydrogen in the universe formed

Where was all the hydrogen in the universe formed?

  Racial or ethnic group

How are males and females viewed differently among your racial or ethnic group?

  Contemplating a process of environmental self-audits

Consider that the company you work for is contemplating a process of environmental self-audits that they expect you to develop and implement.

  Research on brain development

Explain how this research on brain development can be of use to child development professionals as a group and to your own future work with young children and families.

  Popular culture course

Provide a rationale explaining why your pop culture interest is appropriate for a popular culture course.

  Gaba-benzodiazepine receptor complex

Describe in detail the GABA-Benzodiazepine Receptor Complex.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd