5-2 Earned Value Calculation

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule.  

Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.

Activity C is finished. It finished 2 weeks late. It cost $100,000. And it was planned to have cost $110,000.  

Activity D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It was estimated to cost $450,000 when finished. It is approximately 55% complete.  

Using this data, calculate the following.

1. What are the PV, EV, and AC for each of the activities and the complete project?

2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project?

3. Assess the project performance to date? Do you get to have the celebration?

Reference no: EM13252145

Questions Cloud

State prison system : For the month of January, Bay Accountants worked 2,000 hours for Lake Lumber, 600 hours for Marty’s Marina, and 1,000 hours for the State Prison System. Bay bills clients at $160 an hour; its labor costs are $60 an hour. A total of 4,000 hours were w..
Calculate the surface charge density of each sphere : two conducting spheres, one of radius 6.0 cm, and the other of radius 120 cm, each have a charge of 20 nC, calculate the surface charge density of each sphere
State what is the value of kp for the reaction : A 12.0 g sample of solic NH4Cl is heated in a 5.00 L container to a high temperature. At equilibrium, the pressure of NH3 (g) is 1.22 atm. What is the value of Kp for the reaction
Discuss the diversity-consensus dilemma : Discuss the diversity-consensus dilemma, including when it is most likely to occur and one possible strategy that a group leader can take to work through the dilemma.
Earned value calculation : Your project has four activities. Below is the current status of each activity. Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule
Find the magnetic deflecting force acts on the proton : A uniform magnetic field , with magnitude 1.2 mT, is directed vertically upward throughout the volume of a laboratory chamber. What magnetic deflecting force acts on the proton as it enters the chamber
Explain the octet and duet rule : Define the Octet and Duet rule and how it explains the charges on common ions and both covalent and ionic bonding (for representative elements only)
Calculate the random access memory : Calculate the random access memory (RAM) in megabytes necessary to store a multidimensional array that is 20 × 40 × 120.
Find the initial rate at which its temperature changes : A blackened, solid copper sphere that has a radius equal to 4.5 cm hangs in an evacuated enclosure whose walls have a temperature of 23°C. find the initial rate at which its temperature changes

Reviews

Write a Review

Other Subject Questions & Answers

  Some prejudice issues that african americans

What are some prejudice issues that African Americans have faced in the past?

  Apply and cite at least two relevant

Apply and cite at least two relevant and respected resources within the response and list the references at the end of the response. Use APA formatting.

  Cruise line operating truly luxurious ships

You are marketing director for a cruise line operating truly luxurious ships. These have superb service and cuisine. How would you proceed to identify the most promising distributors?

  Applied behaviour analysis by baer

Read the seminal article on applied behaviour analysis by Baer, Wolf, & Risley (1968). This was the first article published in the Journal of Applied Behaviour Analysis

  Purpose and main elements of part of working agreement

Define the purpose and main elements of each part of working agreement (Assessment, Goal Setting, Contracting, and Evaluation).

  What is main concern of schindlers about situation

According to Kohlberg’s theory, please briefly explain in Terri Schiavo case, what is the main concern of Schindlers (Terri’s parents) about the situation? Do you think they were right?

  Functional fixedness and stepping outside the box

what are thoughts on this persons story and did they do a good job with demonstrating functional fixedness and stepping outside the box.

  Explain how the structure of capillary walls

Explain how the structure of capillary walls differs from that of other blood vessels.

  Trace drop of blood to frontal lobe then back to the heart

Beginning at the Superior Vena Cava, trace a drop of blood to the medial palmer side of the fifth digit on the right hand. Fill in landmark sites. Starting in the left common carotid artery, trace a drop of blood to the frontal lobe then back to the ..

  Customer credit transactions

Customer credit transactions, Doing business with customers who may file for bankruptcy protection, Insuring company property

  Identify the hypothesis

Apply the sociological perspective to a variety of socioeconomic and political problems and use technology and information resources to research issues in sociology.

  Relationship of vagueness and due process clause

What is the relationship between "vagueness" and the due process clause? Be detailed.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd