Draw up a schedule to plan your preparation of the bid

Assignment Help Project Management
Reference no: EM131260331 , Length:

The Circumstances

You are employed by a company in Australia and the CEO has decided that the company should bid for work in a new area of business. The CEO requires a briefing document to outline the risks of contracting for work in the new area, recommendations to minimise these risks where appropriate, and the anticipated costs, resources and timing to prepare a typical bid for a contract in this new area of business.

What Is Required In This Assignment?

You are to prepare a report to the CEO which will go to the company board as a briefing document. The briefing document must have sufficient background supporting data to give the CEO confidence about the result, but only the executive summary will go to the board.

The report will contain the following parts:

1. An executive summary to go to the Board.

2. A risk assessment summarising the major risks of contracting this work and your recommendations on how to reduce these risks.

3. An estimate of the costs to prepare a bid for a contract of this type and value.
The estimate is to be summarised in a table by department (rows) and work phase (columns & total).

4. A schedule (prepared in MS Project 2010 or after) for the bid preparation. The Schedule is to identify the work phase and department for each activity.

5. An appendix summarising your background research on three projects.
(A summary is required for each project and articles should be referenced rather than printed out. The summary is to focus on the risks encountered and how they were managed.)

You will research and examine three (3) projects for the type of work for which the CEO considers your company should consider bidding. The projects to be considered by the company must be of a similar type and size.You should choose projects that relate to the field of study for which you are enrolled (e.g. civil infrastructure, production engineering, electronics, etc.) and they are to be of a similar magnitude. A list of some suitable (mostly civil) topics is suggested in Item 2 below. That list is not extensive and you may choose other topics, provided you have the agreement of the lecturer.

For the purposes of this assignment you are to choose three (3) projects of the same type from a topic related to the course that you are doing.

Points to be taken into account when choosing projects and types:

1. The type of project that you choose must be agreed by email with the lecturer before you commence the assignment. The projects reported upon must have been constructed after 1990 and had significant risks to overcome or reported significant delays, cost overruns and other risk occurrences. There will be a limit to the number of students who will be permitted to choose the same topic and projects. So get your requests in early! First come first served.

2. Read carefully through all of this assignment and do some preliminary research before you choose a topic. To enable you to meet the requirements of this assignment you must make sure that you have sufficient background knowledge and/or there is sufficient information available on the topic that you want to select. If not, you need to choose another topic for which you can find more information.

Some Suggestions for Suitable Project Topics -

Infrastructure projects such as: Highway extensions and upgrades, Tunnels, Steel or concrete bridges, Ports (harbours), Long distance pipelines, Railways, Desalination plants, Earth/rock fill or concrete dams, Airports

Large scale property development such as: High rise buildings, Satellite townships, Sport venues,

Other project types (particularly in your own field of study) such as: Software development, Manufacturing plant, Product development, or as may be agreed with the lecturer.

Some key search words ‘construction' or ‘Project' with ‘cost overruns' and similar)

. This reference describes various categories of infrastructure and contains key words and references that you can use in a search engine such as "Google" to find details of projects. It also has useful references in the back of the report.

Various completed projects are described in detail in the Australian Constructors award for Project Insights going back to 2006, to be found at https://acaa.net.au/?page_id=91. Project values can be found in media releases at https://acaa.net.au/?page_id=94 or by searching. Note that these presentations put a favourable light on the projects and you should also search press articles and other more independent internet information such as delays, disputes or cost over runs.

Report on New Business Opportunities
The CEO has instructed you to prepare a detailed report to evaluate new business opportunities for contracts in Australia. When the CEO has reviewed your report and agrees with its content it will be presented to the company Board of Directors with recommendations to them to bid for this new work.

Your task is in parts, as detailed here:

Part 1: Executive summary to the Board
This part of the assignment is in the form of a 1 page (of text) summary plus suitable attachments summarising the significant risks (a before & after risk map and a list of risks with recommended mitigation) involved with executing this type of contract work, and a summary of the cost, and schedule (summary by department and work phase) to bid for the work. The attachments should not cover more than four pages and preferably just 2.

Part 2: Risk assessment summarising the major risks of contracting this work.
The risk assessment and recommendations for mitigation must be summarised and reference made to significant difficulties reported in the press about existing contracts of this type. The attachments to the report will include a professional risk assessment for a typical project in this area and include a risk management plan (of not less than 12 risks ranked by significance, showing the treatment of risks) and a before and after risk matrix (of the 5 most significant risks).

Part 3 & 4: Estimate of the costs and a schedule to prepare a tender bid for a contract of this type.
For this you need to establish a budget estimate on an ‘Excel' spread sheet for yourself (you are the bid manager) and project team involved in bid preparation:

Plan and schedule activities and resources to complete the report in the time allocated. Schedule to be prepared using ‘Microsoft Project 2010'or later software. (Available as 60 Day free trial, see the references).

Part 3 Estimate Preparation: Additional information for this item
You have been advised by other colleagues that generally for design and construct contracts of $200 to 500 million the total cost to prepare a bid may be expected to cost about $300,000 and take some 4 months to complete.

Establish a budget estimate on an ‘Excel' spread sheet:
- An hourly cost rate for each of the individuals and departments assigned to the report preparation is to be used as the basis for the estimate.

- Refer to the table below for a list of staff, annual salaries and resources on the team. Annual salary is the total paid salary per year excluding statutory superannuation payments.
- Each employee receives 4 weeks Annual Leave, 2 weeks Public Holidays, 2 weeks Sick Leave annually, plus a 17.5 % loading on their base salary during Annual Leave and long service leave (13 weeks after 10 years of service). Note that company policy is to make provision for the full amount for sick leave and long service leave even though employees may not take the full amount of this leave.
- Statutory loadings (superannuation (9.5%), payroll tax (4.25%), workers compensation insurance (1.35%), other insurance (4.75%) as a percentage of total salary paid to employee
- Ignore in the calculations any severance pay based on period of service
- Salaried employees do not receive site allowance or overtime payments
- Add business unit overheads at the rate of 19.25% of the direct costs.
- List any estimated costs for travel and accommodation separately.
- Note: As in most organisations, the costs for the CEO salary and Board of Directors fees are paid for out of company overheads and profit and so have zero cost in your estimate.

Description

No.

Name

Annual

Salary

Bid Coordinator

1

(Your Name)

$119,813

Bid production manager

1

Jane Snow

$52,352

Production assistant

1

Francis Ng

$51,096

Design Engineers (2 No.)

2

Design

$89,051

Construction Engineers (1 No.)

1

Construction

$88,336

Contracts (1 No.)

1

Contract

$85,217

Scheduler

1

Rick Parisalla

$76,255

Planning Engineer

1

Nasrin Abdi

$89,446

Lead Estimator

1

Nancy PEREZ QUINTERO

$124,808

Estimator

1

John Ball

$110,717

Estimator

1

Jill Pham

$105,289

Estimator

1

David Rodan

$79,287

Clerical Support

1

Bill Smith

$46,034

Chief Executive Officer & Board

1

CEO

NA

Part 4 Scheduling the Work
Draw up a schedule to plan your preparation of the bid, using the following information:

Planning the Bid Preparation
The bid is to be completed in four months. The team activities required to prepare the report are listed below and in the approximate sequence. You are to include site visits for project evaluation initially and prior to submission of the bid. (Refer to items 4 and 14 below).

You are to prepare a Gantt Chart schedule for these activities, assigning your best estimate of the duration that will be required for each. The above cost estimate that you prepare will also relate to this schedule. Some activities may have ‘Float' (called ‘Total Slack' in MS Project) and may overlap to meet the completion date specified:

Phase

Item

Activity

Key Dates

Scope Definition

1

 

 

 

2

Start date (request bid documents)

06-Mar-17

 

3

Receive bid documents & decide to bid (plan for bid)

 

 

4

Brief bid participants & stakeholders

 

 

5

Site Project Evaluation visit

 

 

6

Construction / Design prepare build strategy

 

 

7

Engineering prepare bid design & sizing

 

Estimation

8

 

 

 

9

Quantity take off and BofQ

 

 

10

Pricing standards for bid

 

 

11

Pricing of BofQ

 

 

12

Planning of Project

 

 

13

Risk assessment of Project

 

 

14

Set contingency & allowances

 

 

15

Prepare Draft Bid document

 

Review

16

 

 

 

17

Bid clarification meeting (on site)

 

 

18

Review bid with stakeholders

 

 

19

Convert Draft to Final Bid

 

 

20

Finalise bid for CEO Review

 

Submission

21

 

 

 

22

CEO Final Review

 

 

23

Finalise documents for bid submission

 

 

24

Submit Bid  by 12 Noon

03-Jul-17

Part 5: Background Research and Report (for Submission to the CEO):

What You are required to do in Part 6

To prepare the report you need to undertake a literature review of key aspects of this proposed new field of activity. Your report is to include brief information on three (3) substantially completed projects. All of the projects must be in Australia. The projects reported upon must have been constructed after 1999 and had significant risks to manage or demonstrated delays, cost overruns and other risk occurrences. They should also be of a similar size (largest to be less than three times the smallest cost) and complexity.

The purpose of this information is to inform the CEO of your company of the key aspects of the proposed new field of activity.

Background Analysis of the Projects

Prepare a brief analysis in your own words of each of the three (3) projects that you have chosen. Paragraphs of text copied and pasted from articles or downloaded from the internet are not acceptable.

The analysis should include for each project a summary of:
- Names of the Client, Project Manager and major construction companies
- a description of the project, location(s), start & finish date.
- Project delivery system(s) used (see Chapter 2.4 of your notes).
- Key construction methods & temporary infrastructure required to carry out the works.
- $ value of project, converted to today's dollars (Aust. Bureau of Statistics indices to be used for escalation over time).
- Risks encountered on the project such as risks that contribute to cost & time overruns and any contractor response to the risks.

The analysis should then list for each risk or group of risks,
- A description of the risks the project encountered
- the schedule, cost and other impact of each
- As best you can discover, what caused the impact and what could or should have been done to treat (mitigate, avoid, transfer etc.) the risk.

References are to be acknowledged in an appendix and cross referenced to the text.

This assignment is to be prepared and submitted by individual students. Although you may discuss this assignment with other students the work must be your own without receiving undue assistance.

The Swinburne University policy on plagiarism applies to this assignment and students are required to submit work which is of their own making. Undue assistance from current or past students work especially includes the application of ‘templates' from that students work.

Attachment:- Estimate on costs excel.rar

Verified Expert

The solution consists of 5 parts. 1st part is the executive summary, followed by risk assessment in the 2nd part and cost assessment in the 3rd part. The 4th part contains the activities followed by background research of the projects in the 5th part. The assignment has been done in Harvard referencing style.

Reference no: EM131260331

Questions Cloud

How does an employer balance their right to control : how does an employer balance their right to control and monitor e-mail and Internet use against employee's right to privacy? Do you agree an employer has the right to monitor e-mail and Internet use?
Matlab built-in vector operations : Write a function natlogApprox that takes scalar input arguments x and n, and returns the approximate value of ln(1+x). Note that your code should use MATLAB's built-in vector operations to solve this problem. Do not use for and while loops.
Compute the amount reported as cost of goods sold : Holiday Bakery owns 60 percent of Farmco Products Company’s stock. On January 1, 20X9, inventory reported by Holiday included 21,000 bags of flour purchased from Farmco at $18 per bag. Compute the amount reported as cost of goods sold in the 20X9 con..
Explain why each would be a good fit for you : Explain why each would be a good fit for you. Is the career choice secure within the future of the travel and tourism industry? Why or why not? Format your paper consistent with APA guidelines.
Draw up a schedule to plan your preparation of the bid : CSM80001 Project Costing - You are to prepare a report to the CEO which will go to the company board as a briefing document. The briefing document must have sufficient background supporting data to give the CEO confidence about the result, but onl..
How accountability for care delivery and nursing delegation : Provide a rationale for your choice of at least two of the members you invited to the committee. Describe two concepts and skills you will consider as part of your team leader role. What types of strategies will you include to facilitate cost-effecti..
Heat seekers and followers : Give your opinion as to whether "Heat Seekers" and "Followers" could coexist within the same organization. State the negatives and positives associated with both patterns of behavior.
Difficult aspects of implementing information security : One of the most difficult aspects of implementing information security policy is communicating policies throughout the organization. For this assignment, outline a communication plan for your project organization. Your outline should indicate how ..
Schedule daniels staff with the minimum number of barbers : Daniel's Barber Shop at Newark Airport is open 7 days a week but has fluctuating demand. - Schedule Daniel's staff with the minimum number of barbers.

Reviews

inf1260331

10/28/2016 8:13:02 AM

My friends got it done from outside but I have just selected your service just because you do it good and for a reasonable price. AS I'm giving it to you regularly, I'm paying now. Please make sure the work is neat and in the BACKGROUND research include harvard style referencing. and send the assignment to me. And i'm cautioning again please read the instructions carefully as it is very important assignment and present the executive summary very well as well as the other parts. It's like the projects has to be described very well with all the problems faced in the project and actions they took to rectify those problems and read the instructions in the assignment what else has to be mentioned in the Background research. There's no limit of words but projects has to be explained clearly and Use harvard style referencing. I have to go through the assignment and should ask back for any changes if required. For the other parts of the assignment Like "executive summary ", "Risk assessment ", "project scheduling " , "costing" .Assume a BUILDING Project.

inf1260331

10/28/2016 8:10:58 AM

These are the reference for the other two parts. BUt it's just the reference and please don't copy from it and do it better than the reference i sent.I dont have copy of EXCECUTIVE SUMMARY but please do it carefully by reading instructions about it. IT is very important so please give it to very much experienced expert 18974632_1Project1 1ref.pdf 18974632_2background research.docx

len1260331

10/28/2016 5:21:46 AM

very very important assignment,I need experienced expert to do this.There are 5 parts to be covered as mentioned in the assignment. The below two files attached for reference how it has to be done. Please do it by reading instructions carefully and don't copy any Risks from the Reference I sent.For the background projects I chose 1.)CBW office complex project located at Melbourne. 2.)Green square Office Park Located at Brisbane. 3.)ANZ centre Located at Melbourne.(14-storey building). Please read assignment clearly to write about those projects in "BACKGROUND RESEARCH". PLEASE PREPARE EXCECUTIVE SUMMARY CAREFULLY AS PER INSTRUCTIONS(it is very important). Consider a building project to carryout the required work. The expert must have knowledge in using EXCEL AND MS PROJECT.

Write a Review

Project Management Questions & Answers

  Create a work breakdown structure

Create a Microsoft Project file for the project that includes the following: Create a Work Breakdown Structure (WBS) that includes all project tasks (hierarchically grouped) and durations. Establish task precedence relationships

  Using the fixed-order quantity model

Using the fixed-order quantity model, which of the following is the total ordering cost of inventory given an annual demand of 36,000 units

  Describe the effects that the statistical information

Describe the effects that the statistical information on a specific race or ethnicity in the areas of health, crime, employment, or education may have in terms of being a predictor of behavior. Provide your opinion on the most likely effects these st..

  What is the expected value of perfect information on reserve

What is the value of imperfect information provided by the G&G? Is it more or less than the value of perfect information and why - What is the expected value of perfect information on reserves?

  Understanding of new learning in logistics management

Demonstrate an understanding of new learning in logistics management and how the supply chain supports the organization's business strategy - Your research paper will analyze how this organization aligns its business strategy with its supply chain ..

  What techniques do we use to define a product

In what ways is product strategy linked to product decisions? Once a product is defined, what documents are used to assist production personnel in its manufacture?

  Review an article related to why organizations adopt project

Discuss the meaning or implications of the articles contents and any flaws you find in the article. What could have made the article better? Was any information left out? How could the author expand on the results?

  Evaluate the use of complex models of project risk

Critically analyse the concept of risk; discuss how it can be measured and ranked and outline how a project risk management strategy may be constructed.

  Project management and risk

Both internal and external factors need to be addressed as well as the probability and impact that certain risks could have on a particular project.

  Explain how an organization can use the balanced scorecard

Explain how an organization can use the balanced scorecard to measure Enterprise Resource Panning (ERP) success?

  Finding maximum price that company willing to pay

If IRR is 15%, would you please tell me how to find out the maximum price that the company would be willing to pay for the new equipment? Ignore taxes.

  Write a comprehensive summary of the book

Write a comprehensive summary of the book Project Management and Risk Management in Complex Projects: Studies in Organizational Semiotics in 7500 words

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd