Draw up a backward schedule under the following conditions

Assignment Help Civil Engineering
Reference no: EM131128769

International Door Slammers has an order to deliver 500 door slammers on day 130. Draw up a backward schedule under the following conditions:

a. Only one machine is assigned to each operation.

b. Schedule one 8-hour shift per day for 5 days per week.

c. All parts are to move in one lot of 500 pieces.

d. Allow 8 hours between operations for queue and move times

A slammer consists of three parts. Purchased components C and D form subassembly A. Subassembly A and component B form the final assembly. Part B is machined in three operations. No special tooling is required except for part B, operation 20. It takes 24 hours to make the tooling. Material is available for all parts.

Standard times for the lot of 500 are as follows:

1183_368f8065-547c-4800-9ff7-a2578d1f8ff7.png

Reference no: EM131128769

Questions Cloud

Discuss the program and what led to its implementation : Briefly discuss the program and what led to its implementation. In general, what are the different types of program evaluation available to a manager? What are the advantages and disadvantages of each one?
Discuss business reasons for employee monitoring : Discuss the requirements of OSHA and how it is enforced. Distinguish between employee privacy in the public and private sectors. Discuss business reasons for employee monitoring. Explain an employer’s obligations to employees engaging in union activi..
Are the federal and state income taxes : Are the federal and state income taxes withheld from employee paychecks a payroll tax expense for the employer? Explain your answer.
What happens to the energy of catalysis : An enzyme is complementary to the transition state - not to the substrate.- What happens to the energy of catalysis (DGcat) when an enzyme is truly complementary to its substrate?
Draw up a backward schedule under the following conditions : A slammer consists of three parts. Purchased components C and D form subassembly A. Subassembly A and component B form the final assembly. Part B is machined in three operations. No special tooling is required except for part B, operation 20. It t..
What were some of specific steps used to evalaute program : What were some of the specific steps used to evalaute the program? What has the program manager discovered about the program based upon an evaluation?
Which amount should a company record as wages : What is the difference between gross pay and net pay? Which amount should a company record as wages or salaries expense?
What is the free energy cost of pumping calcium ions : What is the free energy cost of pumping calcium ions out of a cell when the cytoplasmic concentration is 0.4 uM, the extracellular concentration is 1.5 mM, and the membrane potential is -60 mV?
Time management for effective results in your studies : Write an persuasive essay on the topic  "Time management for effective results in your studies"

Reviews

Write a Review

Civil Engineering Questions & Answers

  Define when the oil will be free of contamination

An oil storage area abandoned 19 yrs ago had oil spilled on the ground and saturated the soil at a concentration of 400mg/kg of soil. A recent soil sample shows a concentration of 20mg/kg.

  Discuss the effects of stacking fault energy

Discuss the effects of stacking fault energy on the deformation of a ductile solid

  Explain what is all about hydrated cement

Explain what is all about hydrated cement

  How much will paycheck be worth when withdraw it in 40 years

If you place $600 from your first paycheck into a Roth IRA earning 4.00 percent annual interest, how much will it be worth when you withdraw it in 40 years

  Determine the volume of stone required for each filter

a two stage high rate trickling plant is to treat a municipal wastewater having a flow of 2.0mgd. pertinent data: influent BOD5 = 200mg/l, BOD5 removal by primary clarifier = 33%, filter bed depth = 5 to 7ft

  Determine the rate of total heat generation

Take the heat of vaporization of water to be 2430 kJ/kg.

  Determine the forward acceleration a of the mower

The mass of the mower and attached bag is 50 kg with center of mass at G. Assume that the operator does not push on the handle, so tha P = 0.

  Coefficient of friction between the dam and foundation is

concrete weights 23.5 knm3 and water weights 9790 nm3. coefficient of friction between the dam and foundation is 0.55.

  Measure the horizontal distance lengths of traverse

Measure the horizontal distance lengths of traverse legs using pacing, surveyor's tape and total station - familiarise with the use of GPS to measure coordinates and other computations (i.e. Slope and horizontal distances, area, perimeters etc.)

  What true stressis necessary to produce a true plastic

A coal mine's entry and breakthrough centers are set at 60ft with 20ft-wide openings.  The 6ft coal seam lies 1,000ft below the suface, and the specific gravity of the overburden is 2.4.  If the compressive strength of 4in.

  What will be the total cost per lane-mile per inch depth

If an alternative base material is available for $5,791.50 per lane-mile per inch depth, to use it, the minimum depth for asphalt has to be increase to 6 inch with no change of base and subbasedepth. What will be the total cost per lane-mile per i..

  What is the expected background color

In Example 14.10, if we switch the transformation functions between the red function and the green function, what is the expected color for the area pointed to by the arrow, and what is the expected background color?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd