The following represents a project that should be scheduled using CPM:
Times (DAYS)
Activity Immediate Predecessors a m b
A. - 1 3 5
B - 1 2 3
C A 1 2 3
D A 2 3 4
E B 3 4 11
F C,D 3 4 5
G D,E 1 4 6
H F,G 2 4 5
a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?
why do we want to create measurement devices early in the strategy process? how do metrics allow us to track the
Which ethical theory did the company use in making its decision. Was it the best. Why or why not. Which ethical theory should the company have used. Why. What is the ideal relationship between bad or suffering and profit.
The company has incurred fixed costs of $2,800,000 to set up its manufacturing operation.If company plans to produce twice as many fishing boat as ski boat respectively with propotion 2:1:1
Describe what the Limits to Growth archetype is in your own words, then give a one page example of a real world event that involves archetype LIMIT TO GROWTH.
A shopping centre is available for purchase for $8 million. The lender agrees this is a fair value for the property. There is 70 000 sq ft of rentable area in the building and tenants are paying $20/sq ft. annually; Debt coverage ratios required by f..
you were hired as a consultant to giambono company whose target capital structure is 40 debt 15 preferred and 45 common
What role does knowledge creation and knowledge management play in organizational learning?
There are three equally likely states of nature (High, Medium, and Low demand). If the Build a large factory option will post profits of $90,000, $30,000, and - $30,000, respectively, in the three states of nature, what is the EMV of the option? Find..
Select a Law of the Fifth Discipline we covered and discuss how you have seen, or experienced it’s success. Then select a second and different law, and discuss where you may have seen it, or are experiencing it currently, and how you might change the..
Discuss what management could have done in terms of risk management to have prevented the events that lead to the lawsuit. Discuss the ethical considerations reflected in the laws applicable to this case.
What are the major business benefits organizations can realize by providing employees with wireless mobile devices? What are the hardware, software and other challenges organizations face in providing their employees with wireless mobile dev..
Facility building is paramount after cities win a bid to host the Olympic Games. What is one of the biggest concerns, outside of construction costs
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd