Draw the network flow diagram

Assignment Help Project Management
Reference no: EM13805703

The following project data in the dependency table was provided by ABC Ltd IT manager; it relates to a new ICT project to be undertaken.

Activity

 

Duration (Days)

 

PrecedingActivities

 

Start Date

A

 

4

 

-

 

1/06/15

B

 

7

 

A

 

5/06/15

 

C

 

7

 

A

 

12/6/15

D

 

6

 

A

 

19/6/15

E

 

2

 

C

 

25/6/15

F

 

5

 

C

 

27/6/15

G

 

9

 

C

 

02/07/15

H

 

6

 

B, E

 

11/07/15

J

 

6

 

D, F

 

17/7/15

K

 

9

 

H, G, J

 

23/7/15

You are required to:

(i) draw the network flow diagram.

ii) Identify the Critical path and its duration.

(iii) Draw Gantt chart to illustrate the project.

Reference no: EM13805703

Questions Cloud

Central bank directly controls both inside and outside money : Central bank directly controls both inside and outside money. Outside money is that part of the money supply produced by the private banking system. Inside money refers to the quantity of notes and coin in the economy.
General syntax of an sql : In a VBScript SQL Query statement, what Boolean operator can be used to test a set of conditions whereby all conditions must be true?
Amortization of premium affect amount of interest expense : What is the meaning of the following sentence: "Amortization affects the amount of interest expense." How does amortization of premium affect the amount of interest expense? How does amortization of discount affect the amount of interest expense?
Responsibility in implementing change in the department : What is the manager's role and responsibility in implementing change in the department? How should a manager successfully handle staff resistance to change?
Draw the network flow diagram : Draw the network flow diagram - Identify the Critical path and its duration.
Effects of errors in inventory valuation : Show the effect, if any, of each of the following errors on ending inventory, cost of goods sold, gross profit on sales, and net income by placing the appropriate symbol in each column. In use is the periodic inventory system. Use the following symbo..
Strategic concept of a joint venture : Define the strategic concept of a Joint Venture, provide an example of a successful JV and an example of a failed JV somewhere in the world -what are the leadership lessons learned from each example?
Dominant form of institutional venture capital firms operate : The dominant form of institutional venture capital firms operate as?
About the refunding analysis : Mullet Technologies is considering whether or not to refund a $175 million, 13% coupon, 30-year bond issue that was sold 5 years ago. It is amortizing $8 million of flotation costs on the 13% bonds over the issue's 30-year life. Mullet's investment b..

Reviews

Write a Review

Project Management Questions & Answers

  Define the term product

Using a relevant product within the hospitality or tourism sector answer the three following questions. Define the term product. Describe the four main product levels that applies to your chosen product.

  As the project manager for an it department

As the project manager for an IT department, you have been assigned to manage the project of deploying a new VoIP phone system to the company's campus. The campus consists of three (3) different buildings, each with twenty to fifty (20 to 50) worksta..

  Communication management plan address

Explain what items should a communication management plan address and how can a stakeholder analysis assist in preparing and implementing parts of this plan?

  Differentiating characteristics of projects from routine

Define key deliverables and workflow, along with roles/responsibilities for their realization and work out a benefits realization strategy for post-project confirmation that benefits are being accrued

  Explaining critical path of a pert chart

In terms of creating a timeline, what is meant by the critical path of a PERT chart?

  What is the utilization rate for the bin area

what is the utilization rate for the bin area? what is the probability that there are more than three tucks in the system at any given time?

  Analyze and develop project schedules

Analyze and develop project schedules with appropriate techniques and software tools and prepare strategies to manage project resources to include human resources, capital equipment, and time.

  Evaluate which factor is influencing the team dynamics

Mastering Virtual Teams - Evaluate which factor is influencing the team dynamics and why

  Choice of an epistemological perspective or stance influence

In what ways does the choice of an epistemological perspective or stance influence the formulation of a management research problem?

  You are a project manager in the marketing department for a

you are a project manager in the marketing department for a county funded hospital. the hospital is launching an

  Compute the product costs per unit

Compute the product costs per unit assuming that Tiger Furnishings uses direct labor costs and machine-hours to allocate overhead to the products. (Do not round the direct-labor cost rate in your intermediate calculations. Round your answers to..

  Project management critical pathsplease help me to solve

project management critical pathsplease help me to solve the following problemyou are working on a project that has 12

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd