3. The following represents a project that should be scheduled using PERT. 
Activity Immediate Predecessor(s) Times (Days)
a m b
A None 1 3 5
B None 1 2 3
C A 1 2 3
D A 2 3 4
E B 3 4 11
F C, D 3 4 5
G D, E 1 4 6
H F, G 2 4 5

(a) Draw the AON project network. Only nodes and directed arrows are required in the network for full credit. 

(b) Calculate the expected activity time for each activity. 

(c) Calculate the variance of the activity time for each activity. 

(d) List all paths and calculate their expected completion time. 

(e) What is the critical path? 

(f) What is the expected project completion time? Please give the reason. 

(g) What is the variance of the project completion time? Please provide at least one step of calculation and the correct answer for full credit. 

(h) What is the probability of completing this project within 16 days? Please provide the formula for calculating the z value, at least one step of calculation, and the correct probability for full credit. 

Reference no: EM13755610

Questions Cloud

Revenue from possible lower enrollment : Explain the process of revenue at NSU, focusing on the relationship between the increased revenue from students enrolling at NSU despite the higher tuition and the lost revenue from possible lower enrollment.
Financial calculator given in investor risk preferences : The intrinsic value of an asset: a.Changes through time as new information is needed b.Is the price at the asset can be bought or sold at a given point in time c.Can be easily determined with a financial calculator given in investor risk preferences
What types of disaster recoveries have been documented : A plan must be tested to determine its likely effectiveness. Do an Internet search on "disaster recovery" and share your findings. Look for something fascinating and unique on which to report. What types of disaster recoveries have been documented? W..
Describe three or more distinct market segments : Identify and describe three or more distinct market segments within a specific industry, such as erospace or automobile manufacturing. Identify and describe a potential ethical dilemma that a marketer might face when segmenting. How might this concer..
Draw the aon project network : (a) Draw the AON project network. Only nodes and directed arrows are required in the network for full credit. (b) Calculate the expected activity time for each activity. (c) Calculate the variance of the activity time for each activity.
Encryption in investigations : Encryption in Investigations-Discuss in your own words the effects that encryption can have on incident response activities, and explain how the use of encryption technologies could prove to be detrimental to an investigation
Components must be considered in plan implementation : Discuss why each of the following components must be considered in plan implementation:
Explain the role of staffing : Explain the role of staffing to support an organization's strategy and improve productivity.
Determine its likely effectiveness : A plan must be tested to determine its likely effectiveness. Do an Internet search on "disaster recovery" and share your findings. Look for something fascinating and unique on which to report. What types of disaster recoveries have been documented? W..

Reviews

Write a Review

 

Project Management Questions & Answers

  Assessing project worth through present and annual worthyou

assessing project worth through present and annual worthyou are considering two mutually exclusive alternatives with

  Pmi chapter meetingyou are attending your local pmi chapter

pmi chapter meetingyou are attending your local pmi chapter meeting. fortunately it draws project managers from many

  Using the appropriate productivity measure

Using the appropriate productivity measure, which of the following numbers represents the resulting productivity ratio?

  Hierarchy structure of flat organization

If a project manager took a hierarchy structure when the company is generally used to a very flat organization, people could feel there is a lot of red tape and take more time to complete tasks.

  Project stakeholders and sponsorscan you give me a sample

project stakeholders and sponsorscan you give me a sample of how to answer these questions?who are your stakeholders

  Project integration

Project Integration

  Developing rfp for a real-world project

Develop a RFP for a real-world project that you have participated in. Optimally, this would be an actual business or government project.

  Project management concepts and applications papercan you

project management concepts and applications papercan you help me get started on this project?gt select a current or

  Company risks vs project risksboth eastman chemical company

company risks vs. project risksboth eastman chemical company a large natural gas user and van oil a major natural gas

  Describing non-numerical factors cause fluctuations

Identify and briefly describe some of the "non-numerical" factors that cause fluctuations in demand for the iPhone 4.

  Planned order release

When should planned order releases take place for the material requirements planning (MRP) data shown below?

  Ges healthymagination project

Show the potential positive and negative effects of the GE project on both GE and on the country in which it is located.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd