Differentiate between scope verification and scope control

Assignment Help Project Management
Reference no: EM13907633 , Length: 4000 Words

Read the Case study below and answer the questions that follow:

WESTERN OCEANOGRAPHIC INSTITUTE(WOI)

Western Oceanography Institute was independently funded research facility aligned with Western State University. Approximately 60 full and part time staff worked at the Institute. They worked on research grants funded by the National Science Foundation (NSF) and the United Nations (UN) as well as research financed by private industry.

Astrid Young, was a 27 year-old graduate of Western State University (WSU) with a Bachelor of Science degree in management information systems. After graduation Astrid worked for five years at Evergreen Systems in Seattle, Washington. While at Evergreen Astrid worked on Y2000 projects and installed NT servers and was very confident that she had the requisite technical expertise to excel at her new job at Western Oceanographic Institute (W01).

Young worked at the WOI for four months prior to initiating the NT conversion project. She made a point of introducing herself to the various groups of people upon her arrival at the institute. Still, her contact with staff had been limited. Astrid spent most of her time becoming familiar with WOI's information system, training her staff, responding to unexpected problems and planning the conversion project. The current WOI information system had been corrupted by viruses introduced over the internet and she devoted an entire weekend restoring the system. In addition to the virus attack, a recurring problem was one of the servers code named "Poncho" that would occasionally shut down for no apparent reason.

Her work was frequently interrupted by frantic calls from staff researchers who needed immediate help on a variety of computer related problems. She was equally shocked at how computer illiterate some of the researchers were and how she had to guide them through some of the basics of e-mail management and database configuration.

The Microsoft NT Conversion Project

Young laid the groundwork for the NT conversion project in her recruitment interview with the director by arguing that conversion was a critical skill she would bring to the position. Once hired, she was able to sell the director and his immediate staff on the project, but not without some resistance. Some associate directors questioned whether it was necessary to go through another conversion so soon after Windows 95 conversion 16 months ago. Against a backdrop of resistance, the director signed off the project after Young assured him that the conversion would be relatively painless and the Institute would then have a state-of-the art information system.

The conversion was scheduled to take eight weeks to complete and consisted of the major four phases: server setup, network installation, data migration and workstation conversion. The project would be completed during summer so that the student assistants could work full time on the project. Young and her student team would first need to purchase and set up seven new NT servers, thus creating a local area network (LAN). Next, they would migrate data to the new Oracle NT database; finally they would convert the existing 65 client computers into NT workstations capable of functioning on the new system. Young had been actively involved in four similar conversions whilst working for Evergreen Systems and was confident that she and her team would complete the project with minimum technical problems. She also believed that this conversion would not be traumatic to the staff at the Institute because NT interface was very similar to the Windows 95 interface.

Young knew that in order for the project to be successful, disruptions had to be minimised, hence she held a staff briefing meeting to outline the scope of the project and the impact it would have on the Institute's operations. She was disappointed by the 'light attendance' at the meeting. Several of the researchers were right owls who preferred to work late into the night. Other staff travelled frequently; thereby she ended up holding two briefing meetings including one in the evening. Still the attendance was less than desired.
The staff's major concerns were the amount of downtime that would occur and whether the software and catabases there were currently using would work on the new system. Young assured them that most of the downtime would occur on the weekends and would be posted well in advance. The only disruption would be tvo hours necessary to convert their existing computer into a workstation. Astrid invested extra energy in researching the compatibility issue and sent an email to everyone listing the software that was known not to work in the NT system. The only software problems involved specially written DOS v 2.1 or older programs that would not function in the new NT environment.

The first 6 weeks of the project went relatively smoothly. The NT servers arrived and were configured on time. However data migration took a little longer than planned. The project was in its final phase- conversion of client computers into NT workstations when the project began to experience nagging problems. Astrid staff had to delete old operating systems and install new operating software on each computer at the Institute. Some of the staff forgot when they were scheduled to be converted. The project team had to wait for them to abandon whatever they were doing so they could convert the computer. Second, the drivers on some of the computers were not compatible and again the team had to devote extra time downloading new drivers off the internet. Third, a few of the staff failed to create adequate hard drive space to accommodate the new NT system. In most cases, the team worked with staff members to delete or compress unnecessary files. To compound matters, midway through the third day, one of the student assistants, Steve Stills, was diagnosed v:ith a moderate case of carpal tunnel syndrome and was told to take two weeks off from the computer work.

The call

After three days, only 22 computers had been converted to NT stations. Young and her staff were working digently on converting computers into NT workstations when she received an urgent call from the director's secretary requesting her to drop everything and come downstairs to the staff meeting. The secretary's voice appeared tense, and Young wondered what was up. As she gathered her things, the student assistant, Eggerts, c.eared her throat and confided that there may be problems with the some of the Institute's websites. She discovered yesterday that some of the links in the Web pages created using Netscape were not working in the Microsoft environment. Young demanded to know why she wasn't told about this sooner. Eggerts confessed that she thought she had fixed the problem last night. Young told her that they would talk about it when she got back.

Young entered the meeting room and immediately recognised that there were more than the usual faces in attendance. The directors welcomed her by saying, "We are glad you could find time to visit with us. My staff meeting has just erupted into a series of complaints about your NT conversion project. As it turns, Dr. Phillips crer there, cannot access his documents because his Word Perfect file mysteriously disappeared. Dr. Simon's geothermal assessment program, which he has used for the past 7 years, doesn't seem to work anymore. Now it appears that the website we use to coordinate our research with the Oslo Institute is a mess. Everyone is complaining about how the revised installation schedule is going to disrupt work. I want to know why I wasn't informed about these problems. These guys want to lynch me for approving your project!"

Question 1-

1.1 "The project communications management plan is a guiding document, which provides communication channels, what to communicate, with whom and how is it going to be communicated among other things" Describe the contents of the Microsoft NT Conversion project communications management plan.

1.2 "Differentiate between scope verification and scope control of the Microsoft NT conversion project". Justify the importance of scope verification and scope control for the success of the project.

1.3 Describe a typical project life cycle for Astrid Young's project.

1.4 Compile a detailed draft business plan that Astrid Young (from the case study) could have presented to the director and his team prior to commencing with her project. Note: You may make REASONABLE assumptions of details not provided in the case study. (18)

Question 2- Discuss the decision making process for developing relevant quality standards for the satisfaction of project stakeholders. Use the WOI case study.

Question 3 - The setup of a computer laboratory entails the following list of activities that must be completed before the laboratory can be used. The activities, immediate predecessors and durations appear in the table below:

Activity

Duration in days

Immediate predecessor

A

5

-

B

2

A

C

4

A

D

5

B

E

5

B

F

5

 

G

2

E, F

H

3

D

I

5

G, H

3.1.1 Draw the AON network diagram for this project.

3.1.2 What is the critical path of the project?

3.2 Explain what a project kick-off meeting is and its purpose. Also provide an outline of a typical agenda for a project kick-off meeting, using an example.

3.3 Outline what a project procurement plan should contain.

Question 4

Activity

Optimistic
time (a)

Most likely
time (m)

Pessimistic
time (b)

Expected
time (t)

Immediate
predecessor

A

1

2

9

 

-

C

2

4

6

 

-

E

1

2

3

 

-

T

1

5

9

 

E

G

1

2

3

 

C, T

P

2

3

4

 

A, G

K

4

6

14

 

A, G

F

1

3

5

 

P

M

4

5

6

 

K

B

7

9

11

 

F, M

4.1 Using expected times (t) and assuming a start date of 3 May 2012, draw the Gantt chart for the project. (8) 4.2 Draw an AON network diagram for the above project.

Verified Expert

This report provides analysis of the WOI case and answers the questions posted at the end of the case study. The report also provides solution to specific questions asked in the assignment. The case is about implementation of a software program at Western Oceanographic Institute (WOI). WOI is a research institute with around 60 full-time and part-time staff working on various government and non-government funded projects. Astrid Young is in charge of a new project “NT conversion project”. The case discusses on how the project ended up in trouble because of lack of scope verification and lack of communication planning. This report will focus on all aspects of project management relevant to the assignment however to maintain the sequence of events, the project business plan will precede the communication plan and scope verification plan.

Reference no: EM13907633

Questions Cloud

Write an sql drop statements that will drop the all tables : Write an SQL DROP statements that will drop the all tables. Add these statements to the appropriate location within the script file - Write a SQL CREATE TABLE statement to create the ALLOCATION table. Add the SQL statement to the appropriate locati..
Analysis of flexible budgets and standard costs emphasizes : Analysis of flexible budgets and standard costs emphasizes the importance of a similar unit of measure for meaningful comparisons and evaluations.
Program that loads the keywords and definitions : 1) Develop the part of the program that loads the keywords and definitions from the external file
Folsom custom skis as discussed in the chapter opener : Folsom Custom Skis, as discussed in the chapter opener, uses a costing system with standard costs for direct materials,
Differentiate between scope verification and scope control : "Differentiate between scope verification and scope control of the Microsoft NT conversion project". Justify the importance of scope verification and scope control for the success of the project
Access the annual report of piaggio : The usefulness of its budgets, variances, and related analyses depends on the accuracy of management's estimates of future sales activity.
Advantages to having such a policy? : advantages to having such a policy?
Create on a horizontal surface : f1 is 30 degrees above x axis.  f2 is 15 degrees below x axis and 1500n. f3 is 15 plus 35 degrees below xaxis.  x axis is as per normal 90 degrees.Three cables are used to drag a heavy crate on a horizontal surface as shown in Figure 1(b).
What amount of ordinary income : What amount of ordinary income and separately stated items are allocated to them for years 1 and 2 based on the information above? Complete UpAHill's Form 1120S, Schedule K, for year 1.

Reviews

Write a Review

Project Management Questions & Answers

  Discussion on information technology

Create a single document with your initial post. Your document should be 350-500 words, though you will be marked based on the quality of your writing, not on the number of words.

  Five key characteristics use to group projects

What are five key characteristics a team can use to group projects into three basic categories?

  Describe issues in project cost estimating

Compare and contrast analogous, parametric, and bottom-up methods of estimating costs. Describe issues in project cost estimating and how to deal with each

  Is project management more of a science or art

Is project management more of a science or art - What do we really know about the project management process?

  Compute the growth duration of each company stock

Compute the growth duration of each company stock relative to the S&P Industrials, compute the growth duration of Company A relative to Company B and what determines your investment decision?

  Project analysis - explain

For evaluating the new equipment, would you please describe whether the following cash flows should be included in the analysis.

  Difference between primary and secondary research

Explain why you chose the criteria you chose and describe the difference between primary and secondary research.

  Describe how attitudes can affect your communication

Describe How Attitudes Can Affect your Communication with Non-Natives - Explain what are the prevailing attitudes in your culture

  Tools to reinforce ongoing monitoring activities

Explain the similarities and differences in your project management team and system maintenance team - Develop the following tools to reinforce ongoing monitoring activities. Also outline a list of system maintenance team members, along with their ..

  Identified twenty-five top key critical safety risk factors

Could you share with us whether any of these risks were specifically applicable to an infrastructure project (or any other project) you were involved with?

  System engineering and deployment of envirobat

Place the sensor under test in a closed chamber which will be filled by the gas to be detected and set the concentration of the gas to a known value and fill the closed chamber with the gas.

  Family plan to plant a vegetable garden

Imagine you and your family plan to plant a vegetable garden in your backyard. The purpose of the project is to reduce your family's food costs and ensure that your foods are grown organically. The space where you will plant the garden is currently o..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd