You are 4 months into a 6 month project. The project is linear, which means that the progress and spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going. Our accounting department has provided the following data at the end of month 4:

Actual cost to date = $88,800

Planned expenditures to date = $101,000

The CFO is excited and has sent you an email congratulating you for being 12.07% under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers look good but how are we ‘really' doing? To understand the true project performance, we need to apply earned value techniques.

The missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 7 tasks scheduled to be complete by the end of month 4 have actually been completed. Task 7 isn't even started! This information gives you the final data you need to apply ‘Earned Value' and develop an objective analysis.

1. What are the PV, EV, and AC for the project at the end of month 4?
2. What are the SV, CV, SPI, and CPI for the project?
3. Assess the project performance to date? Do you get to have the celebration?

 

Reference no: EM13254705

Questions Cloud

Which is the maximum attenuation in db allowed : The transmitter has a power of 7 watts and the receiver needs at least 266 milliwatts to operate. Which is the maximum attenuation in dB allowed (value must be negative)
Analyze 14th amendment which claims equal protection : What are the three level of scrutiny used to analyze 14th amendment which claims equal protection?
Which is the maximum noise allowed in the receiver : A radio link receiver has a signal sensitivity of 100 milliwatt. The SNR required is at least 14 dB. Which is the maximum noise allowed in the receiver.
The phosphate ion forms insoluble precipitates with calcium : The phosphate ion forms insoluble precipitates with calcium and magnesium ions, removing them from solution. Suppose that a solution is 4.5×10?2 in calcium chloride and 8.5×10?2 in magnesium nitrate.
Develop an objective analysis : The missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 7 tasks scheduled to be complete by the end of month 4 have actually been completed.
Calculate the total number of kbps needed in the adc : An analog signal has a bandwidth of 37 kHz and must be digitized in an ADC. The peak voltage is 7V and you need to maintain a resolution of 0.078V. Find the number of bits per sample and then
Explain lightning from thunderstorms strike the earth : Lightning from thunderstorms strike the Earth 100 times each second. 2400 deaths have been caused by lightning strikes over the past 25 years. How many strikes occur before a death occurs
What is the density of the fluid : A rectangular metal block is 0.6 m long, 0.2 m wide, and 0.1 m tall. The block weighs 270 N. What is the density of the fluid
Develop a master production schedule for the breadmaker : Develop a master production schedule for the breadmaker. What do the projected ending inventory and available-to-promise numbers look like? Has Realco "overpromised"? In your view, should Realco update either the forecast or the production numbers..

Reviews

Write a Review

Operation Management Questions & Answers

  What is the workstation cycle time

Balance the line so that only four workstations are required. Use whatever method you feel is appropriate.

  What are the characteristics of a self-organizing system

What are the characteristics of a self-organizing system? How can self-organize principles be utilized to interface with a marketplace? What are the benefits of doing so?

  Discuss the advantages and disadvantages of an alternative

prepare a comprehensive case analysis of SWOT matrix to justify the strategies you will be recommending. Discuss the advantages and disadvantages of an alternative strategy.

  What part of the interview provides an opportunity

What part of the interview provides an opportunity for the interviewer and the interviewee to increase their knowledge of each other, clarify the purpose of the interview, and explain the direction of questioning?

  What is the probability that rich will go to each store

EarsPlus, 10 minutes away; ICantBelieveYouBoughtHeraTrombone, 15 minutes away; and KidNoise, 20 minutes away. According to the gravity model, what is the probability that Rich will go to each store?

  Describe the elements of valid contract

Explain the elements of valid contract, and describe how consumers and banks each have a duty of good faith and fair dealing in the banking relationship.

  What advancement in operations management in other countries

Why has it become so important for companies to become competitive in the global business environment?

  Determine the best possible way to account for inflation

Determine the best possible way to account for inflation when considering where to invest your money. Provide specific examples to support your response.

  Creating crashing schedule

Chuck's Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a mysterious New York lawyer (Mr. T).

  What internet business model would be appropriate

What Internet business model would be appropriate for the company to follow in creating a Web site and why?

  Identify leadership styles associated with path goal theory

Identify four leadership styles associated with path-goal theory. Explain each style and relate it to styles described in other theories. Can leaders exhibit more than one style?

  What is the hourly production rate of the current process

What is the hourly production rate of the current process Customer demand is 90 units per hour. What does the cycle time need to be to be able to meet demand (what is the takt time)?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd