Develop a table of costs for each task showing the slope

Assignment Help Software Engineering
Reference no: EM13835702

Assessment Part A

1. You have been asked by Billy the Banker at ANZ , to use Microsoft Project to develop the project schedule. Note that he has also asked you to include the milestones at the end of the task list in your schedule. These will be used for monitoring the cash flow of the project.

Based on the information in the case study description above, use Microsoft Project 2013 to produce a "Part A" schedule. Make sure that you:

a) Include the milestones grouped together at the end of the task list.

b) Include the resource allocation details on the schedule.

c) Have the project name (CQConstruction Supplier's Business upgrade) as the top of the task list and have all other tasks and summary tasks indented according to the given WBS.

d) Make sure that the holidays described in the "additional information" are not included in the available working days for your project.

e) Use the Microsoft Project software to make sure that the critical path(s) are automatically displayed in red on the bars of the Gantt chart view of you schedule.

At this point there may be resource over allocation issues. Do not attempt to resolve these before answering question 2. Save this version of your schedule in ms project file called CQContructionSupplysPartA1.mpp. You will be required to submit this file as part of your assignment submission.

2. At this point ignore any resource over allocations. Based on your CQContructionSupplysPartA1.mpp schedule (and assuming that you would have no resource constraints):

a) How long would the project take?

b) What are the start and finish dates of the project?

c) List all the tasks that are on the critical path.

d) Did the annual holidays make any difference to the end date of your project? Explain why/why not.

e) If you were asked to complete the project 3 weeks earlier by reducing the duration of some of the tasks in the project, what tasks would you target for reduction and why?

In your answer, include specific suggestions about how you could reduce the duration of those tasks.

3. Create a copy of CQContructionSupplysPartA1.mpp in another file called CQContructionSupplysA2.mpp. If there were any resource over-allocation issues resolve these in this new CQControllersPartA2.mpp without adding any additional resources. Save the "modified" version of CQContructionSupplysPartA2.mpp.

a) Describe how you used/would use Microsoft Project to resolve any resource over allocation issues?

b) In your Word document, list the tasks that are now displayed as "critical".

c) Do the resource constraints have any impact on your project duration and end date? Explain.

d) Sometimes it is possible to resolve resource over-allocation issues by levelling within available slack. What impact does this have on your project schedule?

4. CQContruction Supply's Purchasing department require 6 clear working days notice to authorise any purchase over $10,000 dollars. You have four such purchases that will require such notification falling within the project period. Answer the following questions based on your CQContructionSupplysPartA2.mpp schedule:

a) List the dates you expect to require the Delivery of robotic arms, Delivery of hydraulics, Geo Logistics Mapping Hardware and Software purchase for work on the project.

b) Add a "milestone" as a reminder of the last date you need to give notice to the Purchasing department for each of these acquisitions. Add this at the start of your list of milestones and highlight the milestone in the task list using the "background colour" icon on the task ribbon. This will make it easier for your marker to check your work.

c) According to your schedule, when is the last date you need to give notice to the purchasing for material for the project?

5. Write a memo to George Readymix outlining:

a) the expected completion date of the project, assuming it commences at M1 (5/10/15);

b) the total duration of the project;

c) an explanation of the main factors that cause the project to require that length of time and any recommendations that you might make if time was a priority for the project;

d) The estimated direct labour cost of the project (excluding the cost of your project management consultancy. Present the costs in a table showing the costs for the following:


Cost 
Robotics Pump System  
CRM  
Geo Logistics Mapping   
Customer Mobile Portal Design & Deployment  
Total for the Project:  

Assume that you will send the project schedule (CQContructionSupplysPartA2.mpp) as an attachment to the memo. The information in the memo should correspond to the attached schedule.

6. You have summarised the direct labour costs and some of the key hardware and software costs in question 5. What additional costs are associated with this project? Be as specific as possible in your answer.

7. Are there any other project related supporting activities, plans, events or tasks that your team might have overlooked? If they were overlooked describe how this could impact on the project. (Aim to identify and discuss at least two.)

Assessment Part B

Your project has now travelled forward in time and the project has now been underway for 2 months. To achieve this time travel in MS Project you must first set a baseline for the day of the Kick-off meeting and set a Status Date to 23/11/2015 Additional settings should be made under MS project Options as shown below.

You are required to update your project plan in accordance with the progress the project has made in the first 2 months. You contact all the key stakeholders and receive the following status update information for the tasks completed and those currently in progress up to the 23/11/2015.

Outline  Number   Task Name   Percentage complete    Actual duration where  different from the plan  
1.1 Project Kick off   100 -  
1.2.1.1         Truck mechanical requirements   100 5 weeks   
1.2.1.2         Truck Information Platform requirements   100 -  
1.2.1.3         Requirements specification  Document   100 -  
1.2.1.4   DVLA Approval   20 -  
1.3.1.1.1          Understanding the Q & A, CRM implementation templates  100 3wks  
1.3.1.1.2          Documenting & Reviewing Answers   100 2wks  
1.3.1.2.1          Prepare Solution Draft   50 -  
1.4.1    Purchase Hardware   100 -  
1.4.3    Purchase Software   100 -  
1.4.4    Configure and install   100 8 days  

1 a. Update the project file and Save this version of your schedule in CQontructionSupplysPartB1.mpp. You will also be required to submit this file (CQontructionSupplysPartB1.mp) as part of your assignment submission.

b. Describe the impact the delays in the schedule has had on your project.

c. Based on the progress as of 23/11/2015 calculate the CV, SV, SPI and CPI for the project.

d. Using CPI and SPI explain how the project is progressing

e. Give a forecast for the estimated completion cost of the project. Explain how you arrived at your forecast figure.

You have been advised by Ang Jolli the Business Analyst with VAR's r US that there will be a delay in the delivery of the requirements for the CRM system. She cites the belligerence of CQConstuctions Operation Manager as the cause. TASK 1.3.1.2.2 Final Process Confirmation is to be delayed one week. Ang Jolli has informed you that she has the backing of her management in insisting that all blue print tasks are too double in duration to relieve pressure on the project and to compensate for the stand idle time. Around this time you pick up an answer phone message from Gloria Jeans saying she needs to schedule a 2 day software upgrade before CRM integration testing can be conducted.

2. Create a copy of CQontructionSupplysPartB1.mpp in another file called CQontructionSupplysPartB2.mpp. Amend the project schedule in CQontructionSupplysPartB2.mpp incorporating the requested changes from Ang and Gloria Highlight all the changes (including changes to predecessor relationships in other tasks).

This is to aid your marker.

If necessary, resolve any resource over-allocation. You will also be required to submit this file (CQontructionSupplysPartB2.mp) as part of your assignment submission.

3. Describe the impact(s) of each the following on the project schedule:
a. The delay in Final Process Confirmation.
b. The change in duration of the Blue Print Tasks.
c. The requirement for the software upgrade. Explain your answers.

4. Describe the impact(s) of each the following on the project budget:
a. The delay in Final Process Confirmation.
b. The change in duration of the Blue Print Tasks.
c. The requirement for the software upgrade.

Assessment Part C

Concerned that the Customer mobile portal may become the critical bottle neck in the delivery of the project, your team investigate options for crashing that section of the project. Following a series of meetings with the mobile portal developers Bret Whitelee and Dot Perkins of "Web Moves" your team has ascertained that it is possible to crash the mobile portal deliverable portion of the project. As well as the following information about each task and the cost of assigning extra resources you have been informed that Web Moves will apply an indirect cost per day for their services for the duration of their contract. That is charged at $500 per working day. Table 7 Crash Costs

You may have used difference durations in Part and A and B to represent work effort of the tasks and derive a different critical path. For the purpose of this exercise use those discussed with Web Moves here.

1. Develop a table of costs for each task showing the slope. Then list the tasks in order that you would crash showing the total actual cost after any savings for each task crashed

2. State what duration you would choose for this deliverable and explain your answer.

3. Complete the stakeholder analysis template for each of the projects stakeholders adding any you feel may have been missed. Draw a Interest / Power grid matrix for these stackholders.

4. Write a report, seeking approval to crash this part of the project, to those stakeholders you think need to be informed. Mark it clearly for their attention. Explain the reason for crashing and sell the financial and non-financial benefits of your recommendation. Address the potential individual concerns of your stakeholders.


Attachment:- assessment item.rar

Reference no: EM13835702

Questions Cloud

Develop a generic communications plan and template : Develop a generic communications plan and template
Why necessary to monitor and control strategic plans : necessary to monitor and control strategic plans
Analyze strategic position and direction of the ford motor : Analyze the strategic position and direction of the Ford Motor Company. Evaluate its corporate strategy. In which market segments does the firm participate?
Implement a decision tree to illustrate decision making : Beta Mining owns a copper mine. The firm is going through a difficult period as the price of copper has tumbled in recent years. The annual revenue from the mine depends on the price of copper at the end of the year as shown in the table below.
Develop a table of costs for each task showing the slope : Develop a table of costs for each task showing the slope. Then list the tasks in order that you would crash showing the total actual cost after any savings for each task crashed
Differences between high- and low-context culture : differences between high- and low-context culture
Capital expenditures for medical care : Capital expenditures for medical care which permanently improve or better the taxpayer's property are deductible to the extent the cost exceeds the increase in fair market value to the property attributable to the capital expenditure.
Which of the following statements describes creativity : Which of the following statements describes creativity correctly
Write an analysis paper about motivation and leadership : Each student is required to conduct and document a "Critical Analysis" of two of the topics (e.g., motivation and leadership) covered in Organisational Behaviour

Reviews

Write a Review

Software Engineering Questions & Answers

  Iterative development life cycle

Question: How can we avoid analysis paralysis with an iterative development life cycle approach?

  Study guide - ip address

Discuss when a person types in a domain name such as IBN . COM, how is this recognized by the computer as an IP address and explain ow are IP addresses used?

  Program to calculate the average salary and years employed

Construct a program that determines how many consonants are in an entered string of fifty characters or less. Output the entered string and the number of consonants in the string.

  Es systems are the classic two-edged sword that is they

es systems are the classic two-edged sword. that is they promise and can deliver great benefits through increased

  Methodology for use in the gdtc is the project

Your supervisor is a aware of many different system life cycle models and requires you to describe, using diagrams and an appropriate range of at least two models and to distinct approaches that are common usage.

  Relationship between programming languages and applications

A corporation is about to start a new project but before they start they would like to implement a new filing system. They have employed a consulting corporation to advise them

  Production support system developed a problem

Last Monday morning, the production support system developed a problem. When a screen display for certain parts was requested, the displayed values were garbled. When she was alerted to the situation, Marsha Stryker, Tarheel's IT manager, immediat..

  Creating context diagram for new system

Create a context diagram for new system. Create a diagram 0 DFD for new system. Write brief memo that describes the significance of leveling a set of DFDs.

  Describe the applicable process model

Can you describe the Applicable process model, and data models - the Analysis Phase.

  Compare and contrast agile and waterfall models

Compare and contrast agile and Waterfall models of managing a project in the context of building an e-Commerce Website.

  Where the sdlc do we most commonly search for requirements

What are some of the techniques in discovering the requirements (fact finding) for a system? Which ones work best? Which ones are the most economical? Where in the SDLC do we most commonly search for requirements

  Create state transition diagram that describe patient state

Create a state transition diagram that describes typical patient states and how they change based on specific actions and events.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd