Develop a loading chart for the project resources

Assignment Help Project Management
Reference no: EM131131576

Question:

Not sure how to do backwards and forwards network?

1122_Figure.jpg

The book we use is Jeffrey K. Pinto.(2016). Project Management Acheiving Compettitve Advantage. 4th ed.Given this network plan, complete the following activities:

1. Complete the network diagram by conducting a forward and backward pass through the network. Compute the early/late start time, early/late finish time, and slack time for each activity

2. What is the project duration?

3. What is the critical path of this network?

4. Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.

5. Using the resource loading chart, now compute the early/late start time, early/late finish time, and slack time for your project. Illustrate this new resource constrained network in a network diagram.

6. Complete the resource activity schedule.

7. For the new network, what is the new project duration?

8. Which activities are now critical?

Reference no: EM131131576

Questions Cloud

Examine which position you support and defend your position : Evaluate both the advocates' position and the critics' position. Determine which position you support and defend your position.
Calculate the magnitude of this induced emf : The automobile travels at 68.0 km/h on a horizontal road where Earth's magnetic field is 50.0 µT, directed toward the north and downward at an angle of 65.0° below the horizontal.Calculate the magnitude of this induced emf. V
Define the negotiating goal : List the major issues in the negotiation related to achieving the goal. Define their relative importance of each issue, and define the bargaining crux. Define the interests.
Explain the current market conditions facing your product : Write a 2,000-word analysis of the current market conditions facing your product. Introduce what you are going to write about,write about it and then in the conclusion highlight a few specifics from the body of your paper.
Develop a loading chart for the project resources : Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E).
Find the acceptable range of prices in terms of cars : Find the acceptable range of prices in terms of cars that 10 pianos will trade for. Show your work. Make sure your answer is clearly labeled
Do you believe immigrants really hurt us workers wages : Do you believe immigrants really hurt US workers wages? Why or why not? Is our current immigration laws costing the US our competitive edge in innovation? Should immigration laws be reformed or toughened?
What is the final temperature of the mixture : If the heat absorbed by the water in Part (5) came from the condensation of steam initially at 100 oC, how much steam condensed?
Explain the concept of of the theory of consumer behavior : In more than 500 words explain the concept of of the theory of consumer behavior

Reviews

Write a Review

Project Management Questions & Answers

  Ensuring success on projectswhat are some issues that

ensuring success on projectswhat are some issues that project managers need to be mindful of during the final stages of

  The new restaurant and dining agenda

The new Restaurant and dining agenda

  Software packages for the firms mrp

Consider the following scenario: As part of the management team for PPQ Parts manufacturing company, you are tasked with selecting the best software packages for the firm s materials requirements planning

  Question about project choicesthe new financial analyst

question about project choicesthe new financial analyst does not like the paybak approach in - 35091 - and determines

  Asset management strategic planning

You are an asset manager for a medium sized company, the primary purpose of which is to provide services or products to industrial and/or domestic consumers. Some examples of such an organisation include, but are not limited to:

  Project management for acme development corporation

Project Management for ACME Development Corporation: Procurement process

  Risk mitigation in projectsin most organizations most

risk mitigation in projectsin most organizations most project members are assigned rather than selected by the project

  Evaluate the number of surfboards

Evaluate the number of surfboards to be produced in March and evaluate the number of pounds of fiberglass to be purchased in March.

  Explain about pert and cpm

Important information about PERT and CPM - In what situations should the PERT estimation technique be used?

  Question related to replacement projectto be honest at

question related to replacement projectto be honest at least something that could get me started and allow me to check

  Identify primary characteristics of product

Discuss the type of product the company will offer and identify its primary characteristics.

  Principles of project managementperhaps more than any other

principles of project managementperhaps more than any other of the knowledge areas integration management is of primary

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd