Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These re to be combined into workstations to create an assembly line. The assembly line operates 7 1/2 hours per day. The output requirement is 1,000 units per day.
Task - Preceding tasks - Time (Seconds) -- Task - Procedural Tasks - Time (Seconds)A - ! - 15 -- G - C - 11B - A - 24 -- H- D - 9C - A - 6 -- I - E - 14D - B - 12 -- J - F,G - 7E - B - 18 -- K - H,I - 15F - C - 7 -- L - J,K - 10a. What is the workstation cycle time?b. Balance the line using the longest task time based on the 1,000 unit forecast, stating which tasks would be done in each workstation.c. For b, what is the efficiency of your line balance?d. after production was started, marketing realized that they understated demand and must increase output to 1,100 units. What actions would you take? BE specific in quantitative terms, if appropriate.
A worker-machine operation was found to involve 3.6 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker's time averaged 2.5 minutes per cycle
Code of Conduct in the European Union and Statement of Ethics discuss and compare the two codes from these marketing association. Discuss the similarities and differences between the two.
The Management Model (Planning, Organizing, Leading, Controlling ) is universal. In other words, managers at all levels of all departments in all kinds of organizations use this system
Elucidate what is the probability which a random number from the triangular distribution is less than 400. Elucidate what is this probability for the normal distribution.
An art dealer has a client who will buy the masterpiece Rain Delay for $50,000. The dealer can buy the painting now for $40,000 (making a prot of $10,000).
The subsequent tabulations are actual sales of units for six months also a starting forecast in January.Compute forecasts for the remaining five months utilizing simple exponential smoothing with.
Discuss chaos in health care systems today. In addition, discuss the role of insurance and billing, HMOs, varying drug costs across borders
Collect a small representative sample of secondary data related to career aspirations. Fifteen is the recommended sample size. The data can be collected from observations, surveys, or historical records.
Susan's Sub Shop makes customer submarine sandwiches to order. There are 4 workers. What is the current maximum output of Susan's Sub Shop in number of units per hour?
Consider the figure above and assume that the title search time has changed to 60 minutes. Based on the new data, determine the following
explanation for each question in case the response was negative, about how I would fix the issue raised. Can anyone help?
Describe a net-change system. It is usually run at the beginning of each month. The basic production plan is modified to reflect changes as they occur. It is used to authorize the execution of planned orders.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd