Determine the normal depth-velocity and the froude number

Assignment Help Civil Engineering
Reference no: EM13303505

A PVC pipe with a diameter of 30 inches will carry a flow of 20 cfs. the bottom slope is 0.005 and the roughness coefficient is 0.015. determine the normal depth, critical depth, velocity and the froude number.

Reference no: EM13303505

Questions Cloud

Find the weight of the spaceship on the martian surface : A spaceship with an earth weight of 3430 N is sent to Mars, which has radius, RM = 3.40 × 106 m, Find the weight of the spaceship on the Martian surface
What is the relative humidity for the final mixed parcel : Two parcels of air are mixed. The given properties of the two parcels and the final mixed parcel are as follows: parcel (1): volume = 1 Liter, Temperature = 10 Celsius, pressure = 1 atm, relative humidity = 50%, parcel (2): volume 1 Liter, Tempera..
Compute the size of a squeare concrete box culvert to handle : Compute the size of a squeare concrete box culvert to handle a discharge of 25.5 cms. The culvert will have a length of 45.7m with a slope of 0.01 and a maximum headwater depth of 4.57m.
Compute the index of refraction of the tube : Light inside an optical fiber tube hits the wall between the tube and air and is totally internally reflected. what is the index of refraction of the tube
Determine the normal depth-velocity and the froude number : A PVC pipe with a diameter of 30 inches will carry a flow of 20 cfs. the bottom slope is 0.005 and the roughness coefficient is 0.015. determine the normal depth, critical depth, velocity and the froude number.
Determine how far is the camera from the building : A pinhole camera takes a picture of a building 200 m tall. how far is the camera from the building
Determine critical depth in circular pipe of inches diameter : determine critical depth in a circular pipe of 36 inches diameter and roughness coefficient of 0.015. The flow rate is 15 cfs. So = 0.002
What cost of capital would you recommend the managers use : What cost of capital would you recommend the managers use to evaluate the proposed capital budgeting project?
How do you find the focal length : Take the largest image distance and calculate the focal length of the lens used. image distance = 226 mm object distance =100 mm focal length = ??? How do you find the focal length

Reviews

Write a Review

Civil Engineering Questions & Answers

  Water system design

Determine the corresponding error in the computed discharge

  What will be discharge delivered from the upper reservoir

A reservoir at elevation 700 ft will supply a second reservoir at elevation 460 ft. The reservoirs are connected by 1300 ft of 24-in cast-iron pipe and 2000 ft of 20-in cast iron pipe in series. What will be the discharge delivered from the upper ..

  Determine the volume of water infiltrated on the field

a 30-acre field received 4 inches of rain with 35% runoff.Determine the volume of water infiltrated on the field ( assume all the water that doesn't runoff infiltrates )

  Determine the depth of flow in the channel y2

Water flows down a spillway at the rate q = 15 m^3/s into a horizontal channel where v1 = 20 m/s. Determine the depth of flow in the channel y2 that will casue the hydraulic jump to occur in the channel. Determine the headloss hL in the jump.

  Determine the concentration of the sodium ion in solution

A mass of .525g of NaCl has been added to a cylinder containing water. The cylinder diameter is 1.5in and depth of water in 5inches. Determine the concentration of the sodium ion in solution, showing your ans in units of a) mg/L b) mass % and c) m..

  Determine what will be the new height of fluid column

A u-tube manometer is used to measure the pressure of a vessel under vacuum. Assume the manometer is open to atmospheric pressure (101.325 kPa) and the density of the fluid in the manometer is 12.0 g/cm3.

  Find the shortest ladder

a wall 8 ft high is 3/3/8 ft. from a house. find the shortest ladder which will reach from the ground house when leaning to the wall.

  Determine what is the present worth of benefit

A flood control project has a construction cost during the first year of $10 million, during the second year $6 million, and during the third year $2 million. It is completed at the end of the third year and thereafter incurs an annual operating c..

  Draw the shear diagram for the shaft

Draw the shear diagram for the shaft. The bearings at and exert only vertical reactions on the shaft

  Consolidation ratio of the soil at the unloaded condition

An increment of vertical stress of150kpa compress the sample to a void ratio of1.43. What is the over consolidation ratio of the soil at the unloaded condition.

  Determining the crest and sag vertical curves

Determine, for the crest and sag vertical curves required, the stationing and elevation of the PVCs and PVTs given that the PVC of the crest curve(on westernmost level highway section) is at station 0+00 and elevation 100 ft.

  Determine the force required to lift the block of stone

Determine the force required to lift the block of stone that weighs 200 lb. The rollers are frictionless and the static coefficient between all other surfaces is 0.3. Neglect the size and weight of the wedges.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd