Determine the minimum height of the hump to produce critical

Assignment Help Civil Engineering
Reference no: EM13545544

A rectangular concrete channel 10 m wide has a bed slope of 1 m/km and surface roughness equivalent to a Manning n of 0.02. It is proposed to use a hump on the channel bed for the purpose of flow measurement. If the maximum discharge is 150 m3/s:

(a) determine the minimum height of the hump (?x) to produce critical flow over the hump, and

(b) if the actual height of the hump is 0.5 m calculate the depth of flow immediately upstream of the hump.

Reference no: EM13545544

Questions Cloud

Prepare the journal entry to record the april return : Prepare the journal entry to record the April 8 return of merchandise and prepare the journal entry to record the April 10 payment to Reece Company.
List some of the advantages and disadvantages of rectangular : List some of the advantages and disadvantages of rectangular primary sedimentation tanks over circular sedimentation tanks which must be considered prior to the selection.
Determine the depth of flow if the flow is to be non-erosive : Trapezoidal channel is to be excavated in alluvial material on a bed slope of 1:10000. The side slopes will be 1(vertical) : 2(horizontal). Details of the bed material are as follows:
Identify the errors in the accountants adjusting entries : The accountant for Rooster Laundry prepared the following unadjusted and adjusted trial balances. Assume that all balances in the unadjusted trial balance and the amounts of the adjustments are correct. Identify the errors in the accountant's adju..
Determine the minimum height of the hump to produce critical : A rectangular concrete channel 10 m wide has a bed slope of 1 m/km and surface roughness equivalent to a Manning n of 0.02. It is proposed to use a hump on the channel bed for the purpose of flow measurement. If the maximum discharge is 150 m3/s:
Accounting system and method of revenue recognition : Simona Amanar Industries has two operating divisions-Gina Construction Division and Chorkina Securities Division. Each division maintains its own accounting system and method of revenue recognition.
Estimate the force on the chimney and the bending moment : Estimate the force on the chimney and the bending moment at the bottom of the chimney. You may assume that the effect of the wind on the first 1 m height of the chimney has a negligible effect on the force and the moment.
Identify each corner by a suitable description on the sketch : When using the rectangular surveying system, under what circumstances is there an exception to the general law that an identified original section corner controls the positions of the boundary lines meeting at or passing through the corner ?
Design a rectangular channel contraction from width b1 : Design a rectangular channel contraction from width b1 (upstream) to width b2 (downstream). Assume uniform flow approaches the contraction (i.e. normal depth approaching the channel contraction).

Reviews

Write a Review

 

Civil Engineering Questions & Answers

  Calculate the forces exerted by the water on the bend

Water flows through a horizotal 45 deg reducing bend with a 36 inch. diameter upstream and a 24 inch diameter downstream, at the rate of 20 cfs under a pressure of 15 psi at the upstream end of the bend. Neglecting head loss in the bend, calculate..

  Largest acceptable value of distance for removing a nail

To remove a nail, a small block of wood is placed under a crowbar, and a horizontal force P is applied as shown. Knowing that the maximum vertical force needed to extract the nail is 2600 N and that the horizontal force P is not to exceed 290 N, d..

  How long must diameter be for mallet to balance at a point 6

A wood mallet has a cylindrical head 6 inches long and 3 inches in diameter. If the cylindrical head is 1 inch in diameter how long must it be for the mallet to balance at a point 6 inches from where the handle enters the mallet

  Determine how far apart must two diameter tanks be placed

How far apart must two 18 , diameter tanks be placed such that their stress overlap is not greaer than 10% of the contact stress at depths of 10, 20, and 30 m

  Many years ago well-known architect frank lloyd wright

many years ago well-known architect frank lloyd wright nbspdesigned a mile-high skyscraper which has never been built.

  Determine the water depth at 30 m upstream of the brink

The channel entrance is rounded and smooth (negligible head loss at entrance), and the reservoir water surface is 2.5 m above the bed of the channel at the entrance. hf=0.00019*Q2, where Q (in m3/s) is the discharge in the channel.

  How man n of water must be added to the sample to increase

A moist soil sample weighing 22.2 N has a moisture content of 20%. How man N of water must be added to the sample to increase the moisture content to 30%

  Calculate the final pressure temperature when the nitrogen

Calculate the final pressure, temperature when the nitrogen isreduced to that volume. What is the modulus of elssticity at thebeginning and end of the compression. k=1.4

  What is the maximum height

The height (in meters) of a projectile shot vertically upward from a point 2 m above ground level with an initial velocity of 24.5 m/s is h2+24.5t-4.9t^2 after t seconds. a) When does the projectile reach its maximum height? b) What is the maximum..

  Why is the substrate that is reduced first preferred

In what sequence are these oxidized compunds reduced by the bacteria, and why is the substrate that is reduced first preferred by the hydrogen acceptor. When do obnoxious odors appear

  Convert the bearings to azimuths from north

Convert the bearings to azimuths from north and compute theangle . smaller then 180 degree. between successive bearings.

  Find wall friction head loss and the friction force on duct

Water at 60 degrees Fahreneit flows at 3 cfs through a 150-ft-long duct of 6 in X 9 in cross section. The pressure at the inlet end is 15 psig, and at the outlet, 20 ft higher than the inlet, it is 4 psig.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd