McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities
OT
MT
PT
Activity 1
4
6
14
Activity 2
5
12
16
Activity 3
7
15
23
Activity 4
13
28
Activity 5
17
20
35
Activity 6
32
50
Activity 7
You must also do the following:
Review the five stage model of team development in the required reading of Chapter 11. Describe a project that you are involved with right now, and the stage that the project team is currently in.
As a small project team (3 - 4 members) you are to look at an Oil and Gas project (Option 1: Solar Panels OR Option 2: Knowledge Management System) and to apply project management learnings and techniques to deliver the following milestone:
Expalin the role of project management in modern organizations and function within a project team environment
the it department is implementing a new crm solution in its corporate offices. the hardware currently in use is out of
1.outline andwrite a verbal presentation for one of the benefits provided to you as a student at csu.your response
provide a brief description of the key elements of an employee appraisal system which will contribute to changes in
Choose a current or past project you have been involved with in your organization or community and prepare a paper that includes the elements.
define at least three measurements of oproductivity for the chain and calculate each store's productivity for each measurement that you developed.
Provide your thoughts on what the purpose of a problem solving meeting is and how would one be conducted?
Which of the following activities is not considered a project
What are the benefits of project management and give an example of how you have relied on project management.
stakeholder analysis for project communicationsmake a stakeholder analysis for project communications. assume your
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd