Reference no: EM13738424
Question: You have just started your new job as a junior programmer at Wrigh's Design House. The Project Manager has asked you to develop a program to determine the estimated time needed to complete a design project.
To evaluate the estimated time the Design House uses the calculations entered for an optimistic time, a realistic time and a pessimistic time. The program allows the staff to enter and keep track of the number of projects, then prints the results based on the data entered.
Data Entry
A five digit project number
A two digit optimistic time
A two digit realistic time
A two digit pessimistic time
Data Output
Each project number
The optimistic time
The realistic time
The pessimistic time
The expected time use the formula ET = ( OT + 4RT + PT) / 6
The total number of projects and the activity that takes the longest time and the activity that takes the shortest time.
Rationalize your answer by math, measurement or example, something convincing.
Compute the quantity of ice
: How much ice at a temperature of -17.7 C must be dropped into the water so that the final temperature of the system will be 220 C ?
|
Write a program that reads in a single record
: Write a program named printRecord.py that reads in a single record from the first logfile, prints it, and exits - Write the final version of your program; it does what merger.py does and then loops through the records accumulating the op costs. It t..
|
What products are being offered by a shop
: Using the broad definition of a product, identify and explain what products are being offered by a shop that specializes in bicycles; by a travel agent; by a supermarket; and, by a new car dealer
|
Find the percent uncertainty in answer
: What is the percent uncertainty in your answer? The uncertainty of the force is 10 N and the uncertainty of the acceleration is 0.01 m/s2.
|
Determine the estimated time needed
: You have just started your new job as a junior programmer at Wrigh's Design House. The Project Manager has asked you to develop a program to determine the estimated time needed to complete a design project.
|
Determine the distance of the second post from you
: A fence post is 56.0m from where you are standing, in a direction 39.0? north of east. What is the distance of the second post from you, if the distance between the two posts is 90.0m ?
|
Divide-and-conquer two-dimensional closest-pair algorithm
: Suppose the version of the divide-and-conquer two-dimensional closest-pair algorithm in which, instead of presorting input set P, we simply sort each of the two sets Pl and Pr in nondecreasing order of their y coordinates on each recursive call.
|
Technical meaning of conflict of interest
: Question 1: The technical meaning of conflict of interest is that:
|
Parallel numeric arrays
: Create and code a program that uses three parallel numeric arrays of size 6. The program searches one of the arrays and then displays the corresponding values from the other two arrays.
|