Determine the critical path and the expected duration time

Assignment Help Operation Management
Reference no: EM131128409

Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer. Chris’s college instructor assigned a paper due next week. Chris decided that she will prepare the paper on the new computer. She made a list of the activities she will need to do and their estimated times.

c. Determine the critical path and the expected duration time.

d. What are some possible reasons for the project to take longer than the expected duration? Use Excel for both and the critical path method on c.

Estimated Time (hrs.) Activity (abbreviation)

0.8 Install software (Inst)

0.4 Outline the paper (Out)

0.2 Submit paper to instructor (Sub)

0.6 Choose a topic (Ch)

0.5 Use grammar-checking routine andmake corrections (Ck)

3.0 Write the paper using the word-processing software (Write)

2.0 Shop for a new computer (Sh)

1.0 Select and purchase computer (Sel)

2.0 Do library research on chosen topic (Lib)

Reference no: EM131128409

Questions Cloud

Healthcare services can be rationed governmental rationing : Healthcare services can be rationed by governmental rationing or by allowing those who can afford the services to purchase the services. A forty-six-year-old unemployed auto worker with a history of alcohol use and smoking suffered a heart attack and..
Do you agree with the statement do not criticize : Do you agree with the statement, "Don't criticize"? Do managers tend to give criticism or coaching feedback? Explain. How can managers improve? What percentage of time do you think that a manager can actually use the collaborating conflict management..
Pay cash for the transplant procedure and follow-up care : Healthcare services can be rationed by governmental rationing or by allowing those who can afford the services to purchase the services. A seventy-six-year-old nonsmoker with good pulmonary and renal function is a good candidate for a heart transplan..
Proposal to analyze the cultural values of your organization : Superb Consultants has submitted a proposal to analyze the cultural values of your organization. The proposal states that Superb has developed a revolutionary new survey to tap the company’s true culture. The survey takes just 10 minutes to complete,..
Determine the critical path and the expected duration time : Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer. Chris’s college instructor assigned a paper due next week. Chris decided that she will prepare the paper on th..
Components of effective performance appraisal system : What are the principal components of an effective performance appraisal system? How can a performance appraisal system effectively address employee-related challenges in the workplace such as performance problems, unsatisfactory conduct, and/or viola..
Single-period inventory system-what is target service level : Single-Period Inventory System. The hospital cafeteria makes one large batch of macaroni and cheese each morning. If the cafeteria runs out of macaroni and cheese, the last few customers are less than satisfied, but if the cafeteria makes too much, i..
What is most that you would be willing to pay for insurance : Your utility function is U = ln(2C) where C is the amount of consumption you have in any given period. Your income is $40,000 per year and you have no savings. There is a 2% chance that you will be involved in a catastrophic accident that will cost y..

Reviews

Write a Review

Operation Management Questions & Answers

  A machine can operate for an average

A machine can operate for an average of 8 weeks before it needs to be overhauled, a process which takes 9 days. The machine is operated 5 days a week. Compute the availability of this machine. (Round your answer to 3 decimal places.)

  Analyze the problem and hypothesize potential solutions

Organize your thoughts, research, and explanation of the solution for presentation to your colleagues. Analyze the problem and hypothesize potential solutions. In a PowerPoint presentation, provide a summary of the problem, along with possible sol..

  The setup cost when switching production

Charles Cycles produces bicycles and tricycles. The setup cost when switching production from one to the other is $1,800. On average, retail customers order 230 tricycles per day (consider a 250-day year). The daily production rate for tricycles is 6..

  Differences between data warehouses and data marts

Discusses the differences between data warehouses and data marts. Also, discuss how organizations can use data warehouses and data marts to acquire data. You must use the CSU Online Library to locate at least two sources for your paper.

  Primary goal for most management negotiators in bargaining

The primary goal for most management negotiators in bargaining is to ________.

  How many cars per hour pass through the 5 mile strip

A group of city planners are looking at a 5 mile strip of highway to measure its throughput during rush hour. At any point in that there are 60 cars, on average, on the 5 mile strip and they are moving at an average of 40 miles per hour. How many ..

  Compile the change management imperatives

Compile the change management imperatives which will go into making this a successful change project. Construct a set of strategies which managers can use to help employees cope with complex change.

  Capital constraint-then the total net present value

Assume that your capital is constrained, so that you only have $500,000 available to invest in projects. If you invest in the optimal combination of projects given your capital constraint, then the total net present value (NPV) for all the projects y..

  What are specific people risks associated with citi bank

You will further research the Citi bank you chose as the subject of your project. Write the next section of your risk management plan in which you discuss the key people, financial, and operation risks associated with your bank. What are specific ..

  Company may develop an emergent strategy

A company may develop an emergent strategy due to

  Develop strategies for entering the target market

Describe the specific target market. Develop strategies for entering the target market. Create a plan for entering the target market

  Determine the annual inventory carrying cost for each item

Compute the dollar values for the information in the above table, determine the annual inventory carrying cost for each item, and the total annual inventory carrying cost.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd