Tom Schriber, a director of personnel of Management resources, Inc. is in the process of designing a program that its customers can use in the job finding process. Some of the activites include preparing resumes, writing letters, making appointments to see prospective employers, researching companies and industries, and so on. Some of the infromation on the activites is shown in the following table:

Days Immediate

Activity a m b Process

A 8 10 12 -

B 6 7 9 -

C 3 3 4 -

D 10 20 30 A

E 6 7 8 C

F 9 10 11 B, D, E

G 4 7 10 B, D, E

H 14 15 16 F

I 10 11 13 F

J 6 7 8 G, H

K 4 7 8 I, J

L 1 2 4 G, H

(A) Construct a network for this problem.

(B) Determine the expected time and variance for each activity

(C) Determine ES, EF, LS, LF and slack fore ach activity

(D) Determine the critical path and project somple completion time

(E) Determine the probability that the project will be finsihed in 70 days or less

(F) Determine the probability that the project will be finished in 80 days or less

(G) Determine the probability that the project will be finsihed in 90 days or less

Reference no: EM131366997

Questions Cloud

Advantages and limitations of portfolio analysis : Advantages and limitations of portfolio analysis. What are the things a researcher should do and keep in mind while taking consent from an individual for research and innovative treatment?
Company specializing in climate-controlled pet houses : Juki Mara is Dallas based company specializing in climate-controlled pet houses. According to the company’s VP of Operations, their market segments basically compromise of high-end customers who are either dog or cat owners and who want to pamper the..
According to the research on the mcclelland theory : According to the research on the McClelland theory of needs. Remember, McClelland believes that individuals are motivated by achievement, power, and affiliation, yet they tend to favor one over the others. After reviewing and researching the theory, ..
Are all of the elements of a contract present in this case : Susan, a wealthy widow, invited an acquaintance, John, to her home for dinner on a specific date at a specific time. Jonathan told Susan that he would be delighted to come to dinner and, eager to impress Susan, spent lavishly in preparing for the eve..
Determine critical path and project somple completion time : Tom Schriber, a director of personnel of Management resources, Inc. is in the process of designing a program that its customers can use in the job finding process. Determine the expected time and variance for each activity. Determine ES, EF, LS, LF a..
How managing human capital : How MANAGING HUMAN CAPITAL course can assist you in achieving further professional goals. What is the most valuable concept you can learn by doing MANAGING HUMAN CAPITAL subject?
Explain the purpose of background investigations : Evaluate the relationship between the development strategy in one hand and recruiting and selection ? Explain why employee training is important? Also discuss Why career development is valuable to organizations? Explain the purpose of background inve..
What issues in channel conflict might arise : What issues in channel conflict might arise from Procter and Gamble’s special arrangements with Amazon.com? Would you recommend that Procter and Gamble use any mode of transportation other than trucks to transport cartons to retailers?
Two type of turkey cutlets for sale to fast-food restaurants : The Wild Turkey Company produces two type of turkey cutlets for sale to fast-food restaurants. Each type of cutlet consists of white meat and dark meat. Cutlet 1 sells for $4 per pound and must consist of at least 70% white meat. Determine how maximi..

Reviews

Write a Review

Operation Management Questions & Answers

  Total transportation cost necessary to meet customer demand

Reliable Beer Distribution In this problem, we will producing and transporting beer to customers in such a way that the resulting beer supply chain is robust to failures. Specifically, you are given a set I = {1, 2, . . . , m} of production facilitie..

  Experience the most dramatic changes

Of the five management functions, which do you expect will experience the most dramatic changes in the next decade? Defend your answer. Which will have the least amount of change? Explain your answer.

  How does a focused differentiation strategy differ

What are the keys to sustaining a focused low-cost strategy? How does a focused differentiation strategy differ from a broad differentiation strategy?

  Misrepresented her age and the motorcycle was damaged

Helen, age 17, wanted to buy a Harley-Davidson “Sportster” motorcycle. She did not have the funds to pay cash but persuaded the dealer to sell the cycle to her on credit. The dealer did so partly because Helen said that she was 22 and showed the deal..

  Two kinds of wine valley nectar and valley red

The Valley Wine Company produces two kinds of wine Valley Nectar and Valley Red. The wines are produced from 64 tons of grapes the company has acquired this season. A 1000-gallon batch of Nectar requires 4 tons of grapes and a batch of Red requires 8..

  What are the causes incidences and risk factors of a

1 what are the causes incidences and risk factors of a stroke?2 list alternate names of a stroke.3 what are the 2 major

  Conveyor-paced assembly line-machine-paced line flow

Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise. Assume a demand..

  Cooperation with the organization''s other disciplines

Human resources has been asked to put a plan together in cooperation with the organization's other disciplines (finance or accounting, administration, operations, customer service, marketing, and so on) for a four percent staff reduction.

  Believes the environmental regulations

HGR Chemical Company believes the environmental regulations for it's industry are much more stringent than necessary, which likely means

  Improve communication with your overloaded staff

Knowing you can't add employees to your staff in the short term, what are you going to do to improve communication with your overloaded staff?

  A distributor has heard that one of the major manufacturers

A distributor has heard that one of the major manufacturers from which it buys is considering going direct to the consumer

  Use transformational leadership to be more successful

Research has shown that transformational leadership can lead to a positive impact on performance and behavior. Discuss how this occurs and provide an example of a leader you have worked with who has done this successfully or who could use transformat..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd