Two straight sections of freeway cross at a right angle. At the point of crossing, the east-west highway is at elevation 150 ft and is a constant +5.0% grade (upgrade in the east direction), the north-south highway is at elevation 125 ft and is a constant -3.0% grade (downgrade in the north direction). Design a 90-degree ramp that connects the northbound direction of travel to the eastbound direction of travel.
Design the ramp for the highest design speed (to the nearest 5 mph) without exceeding a minimum D of 8.0. (Assume the PC of the horizontal curve is at station 15+00, and the vertical curve PVIs are at the PC and PT of the horizontal curve). Maximum allowed superelevation by design standards is 12%.
Determine the following:
Stationing and elevations of the horizontal curve PC and PTHorizontal curve radius and lengthStationing and elevations of the vertical curve PVCs and PVTsVertical curve lengthsLength of constant grade in between the 2 vertical curves (if any)
The volume flow rate of streams into the pipe is given by QA = 0.02t m 3 /s and that of stream B by QB = 0.008t 2 m 3 /s, where t is in seconds. The exit area of the pipe is 0.01m 2 . Find velocity and acceleration of the flow at exit at t = 1s.
Assume that there were 1,100,000 vehicles making a 28.5-mi round trip per day, the average vehicle emission rate for VOCs is 1.3 g/VM , and the molecular weight of the VOC emissions from the mobile sources can still be represented by that of metha..
The long-term average January precipitation in the Colorado River basin is 1.11 inches, with a standard deviation of 0.60 inches. Assuming a normal distribution, what is the probability that less than 0.5 inches of precipitation will occur in any ..
what is the uniform deterministic arrival rate if the vehicle queue is cleared in 35 minutes after vehicles begin to arrive (in veh/min.)?
A car travelling at 60 mph in a construction area skids into a stack of concrete barriers. Skid marks leading to the crash measures 150 ft .
How do you calculate the force of water hitting a concrete cylindrical pole. The velocity of the water is 2 ft/s, the depth of the water is 10 ft, and diameter of the pole is 3 ft. So what would be the total force exerted on the pole by the water?
what are the factors affecting the hydraulic conductivity?
Determine the rate at which heat is added in the boiler, the power required to operate the pumps, the net power produced by the cycle, and the thermal efficiency.
A falling-head permeability test was carried out on a clay soil of diameter 100 mm and length 150 mm. In 4 minutes the head in the standpipe of diameter 5mm dropped from 680 to 350 mm.
Determine the slenderness ratio of a 5 m column with built in ends if its cross- section is (a) circular with a radius of 40mm and (b) 50 mm square. Use the concept of effective length.
A constant power of 1.5 hp is supplied to the motor while it operates with an efficiency of ε = 0.8. Determine the velocity of the 200-lb crate in 15 seconds, starting from rest. Neglect friction.
The height (in meters) of a projectile shot vertically upward from a point 2 m above ground level with an initial velocity of 24.5 m/s is h2+24.5t-4.9t^2 after t seconds. a) When does the projectile reach its maximum height? b) What is the maximum..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd