Critical path that resulted from crashing the project

Assignment Help Supply Chain Management
Reference no: EM13217288

Based on the material covered in class and using the following information about the activities of a project, please identify:

1. the shortest amount of time in which the project schedule can be crashed without exceeding $7K and

2. the project critical path that resulted from crashing the project

Activity

ID

Predecessor

Estimated Optimistic Time

Estimated Most

Likely Time

Estimated Pessimistic Time

Reduction

Time

Goal

Normal Costs

Costs of Reduction

a

-

15

20

85

10

$1,000

$867

b

a

25

40

235

20

$400

$262

c

b

60

100

500

140

$400

$347

d

a, b

25

30

125

25

$800

$560

e

c

45

50

145

45

$200

$120

f

e

30

50

220

65

$100

$53

g

d, f

20

30

130

15

$1,000

$1,600

Notes:

  • An activity should not be crashed if there is not a reduction in the duration of the project. Remember that crashing is investing financial resources to speed up the project. So why invest if there is not a reduction in the duration?
  • The term "Slope" creates some confusion with mathematical calculations of slope, which are different from what has been shown in the class. The "Slope" as discussed in class is really a "Ratio". You should calculate it using the equations taught in class, not the mathematical slope equation.
  • No partial crashing allowed
  • No optimality analysis allowed
  • The reduction is the amount of time we are seeking to gain from the originally estimated time.
  • "Cost of reduction" is the amount of money required to reduce the duration of the activity by the amount defined in "reduction time". In other words it is what we need to invest to reduce the duration of the activity.

Reference no: EM13217288

Questions Cloud

Primary duty to manage the company : Director have a primary duty to manage the company and not to answer to individual shareholders - Use australian company and association law 2013.
Opportunity for implementing corrective measures : Duffy and Thomas (1989) advocated that project reviews should be 3-phases. Pre-project reviews assess the feasibility of the project from all aspects, in-project reviews provide feedback on ongoing issues and provide an opportunity for implementin..
Analyzing and managing projects that are in pipeline : Iimplemented a software system that would serve as a tool to tracking, analyzing and managing projects that are in the pipeline.
Implement to enhance project management : Information dissemination; a situation where communication across the stakeholders was not encouraged and outdated procedures that was no longer in sync with the current trend
Critical path that resulted from crashing the project : The shortest amount of time in which the project schedule can be crashed without exceeding $7K and the project critical path that resulted from crashing the project
Most significant challenges facing you as manager : what are the most significant challenges facing you as manager of this store and what steps would you take during the first 90 days as manager to address these challenges?
Conduct a comprehensive external environmental scan : Conduct a comprehensive external environmental scan of your business unit, including a five forces analysis, to identify the relevant trends that pose opportunities or threats to your business.
Establishment of customer service department : Establishment of customer service department to address client's issues and requirements and conducting daily meeting for particular projects to review the progress of the project and to open the floor for new idea and suggestions.
Explain cost-based and value-based pricing : What are the differences between cost-based and value-based pricing. Pricing is based on customer perceptions of value and costs in addition to other internal factors. Discuss these other internal factors and how they might affect the pricing of a..

Reviews

Write a Review

 

Supply Chain Management Questions & Answers

  Demonstrate an understanding of the importance

Demonstrate an understanding of the importance of procurement for global organisations operating in complex market environments Locate, synthesise and critically evaluate recent/current information

  Estimate the frequencies of the other two possible genotypes

Albanism is a tratit caused by homozygosity for a recessive allele a. In Humans , the frequency of albino individuals is about1 in 20,000 or 0.00005. Use A for the dominant non-albinoallele.

  Financial and legal implications of international trade

Financial and legal implications of international trade focus on business and capitalisation of both companies, and how they would fit into chinas socio-economic system.

  What is the total annual cost

What is the total annual cost

  Discussion and thoughts

One of the key decisions a company must make on contemplating a new site, or a new operation at an existing site, is its capacity. What are your thoughts?

  Address several key areas of scm

Supply Chain Managment and Please give a write-up addressing several of the following key areas of SCM:

  Embraced lean throughout organization

What other industries are led by a company that has embraced lean throughout their organization?

  Discusses approaches to achieving time compression

The journal article discusses approaches to achieving time compression in the supply chain and how similar are those approaches to the application of lean principles to elimination of waste through channeling value stream flows?

  Explain principle of supply chain management

Which of the following is not a principle of supply chain management? Choose one answer.Segment customers by service needs and then tailor services to those particular segments

  What is public sector internal auditing

What is Public Sector internal auditing

  World bank has an impact upon globalization?

Do you feel that the World Bank has an impact upon globalization? Do you feel that this financial instrument has helped or hindered globalization?

  Discussing the social and legal requirements

Discussing the social and legal requirements when it comes to Global Sourcing, however, since we know that corporate policy will vary from company to company, what about the law?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd