1. Building aswimming pool
Task
WorkerCategory
PersonDays
#ofWorkers
ElapsedTime(days)
Materials($)
Excavate
MachineOperator
6
2
0
1,500.00
Framethewalls
Masons
8
4
800.00
InstallInternalPlumbing
Plumber
700.00
InstallElectricity
Electrician
500.00
Pour concrete
2,000.00
Installpumpandfilter
1
3,000.00
Total
8,500.00
Category
Wage Rate$/Day
200.00
Mason
160.00
120.00
Createa Gantt chart from the work break down structure.
Createa PERT/CPM network showing the interdependencies of the different activities. How long will the project take?(Note:Don't forget to take "elapsedtime" into account.)
Using the information in your Gantt chart, as well as the information on wage rates and cost of materials, put together a budget showing planned to talexpenditures for the project. Following are cost and schedule data for aproject that isunderway.
Project Cost Data
Month
Planned
Actual
30
12
35
23
3
42
55
46
5
40
53
52
60
7
45
75
48
80
9
50
10
11
15
Project Schedule Data
PlannedStartingMonth
Duration(months)
startingmonth
ActualDuration(mths)
A
B
C
sofar
D
E
Notyetbegun
F
1. Using the cost data inthe cost table above, create acumulative cost curve comparing actual versus planned costs
2. Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance
3. Summarize in words what you see project status to beat this time.What do you predict regarding the final cost and final schedule for the project?
Show how project management principles were used to reach project goals in the face of adversity.
Compute Breakeven cash inflows for Etsitty Arts, Incs new project - How would the minimum yearly cash inflow change if the company required a 10% return on its investment?
Identify "Risk" in project management
Most effective strategy for reducing a project's duration and the specific reasons supporting your choice
Calculate the annual holding cost rate for FFF?
3. A PERT project has an ending completion time of 62 weeks with a variance of 16 weeks. Determine the following probabilities: a) The project is completed in 68 weeks. b) The project takes longer than 70 weeks. c) The project is completed between 60..
Proprietary funds utilize what basis of accounting?
planned order releasewhen should planned order releases take place for the material requirements planning mrp data
In Blockbusters, Professor Anita Elberse argues that a blockbuster strategy a board formula that assumes investing in big potential winners account for a disproportionate share of returns.
project baselinewe have now moved from the planning stage to the doing part of project management. following good
Identify TWO examples of conflict that could be expected to result fromstaff adopting a strict adherence to only their current perceived primaryroles. One example should evidence negative conflict, while the otherexample should evidence positive c..
i need best professional and quality work with no plagiarism and write citation and references in apa 6th edition. all
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd