Project Management Exercise -

The Beta project team has started gathering the information necessary to develop the project network diagram - predecessor activities and durations in weeks. The results of their meeting are found in the following table.

Activity

Description

Duration

Predecessor

1

Define Scope

6

None

2

Define Customer Problems

3

1

3

Define data records and relationship

5

1

4

Mass Storage Requirements

5

2, 3

5

Consultant Needs Analysis

11

2, 3

6

Prepare Installation Network

3

4

7

Estimate Costs and Budgets

2

4

8

Design Section Point System

1

4, 5

9

Write Request Proposal

5

5

10

Compile Vendor List

2

5

11

Prepare MGMT Control System

5

6, 7

12

Prepare Comparison Report

5

9, 10

13

Compare System Philosophies

5

8, 12

14

Compare Total Installation

2

8, 12

15

Compare Cost of Support

3

12

16

Compare Customer Satisfaction Level

8

12

17

Assign Philosophies Points

1

13

18

Assign Installation Cost

1

14

19

Assign Support Cost

1

15

20

Assign Customer Satisfaction Points

1

16

21

Select Best System

2

11, 17, 18, 19, 20

22

Order System

1

21

The project team has requested that you create a network diagram for the project, identify the critical path, and determine if the project can be completed in 50 weeks.

You are to first do a "hand drawn" solution, and then use Microsoft Project to create network diagram again. Assumptions: Start date is October 3, 2016, one shift per day, no overtime, no weekends, and all traditional holidays to be observed.

Reference no: EM131227678

Questions Cloud

Create it department to support agcredit future architecture : What new internal IT capabilities will have to be developed in order to create an IT department to support AgCredit's future business architecture?
Type of packet filter : What type of packet filter would you be most likely to recommend: stateless, stateful, or one that looks at packet content? Why?
Important aspect of maintaining business longevity : Physical security is a very important aspect of maintaining business longevity. Picture the following example: a building located downtown holds the information on numerous businesses run by an overhead business within the same building.
Evaluate and describe any cultural considerations : This person might be a political, business, human rights, education, or entertainment figure. Examine the major theoretical approaches studied in the class so far (psychodynamic, behavioral, learning, trait and type, and humanistic). Briefly descr..
Create a network diagram for the project : The Beta project team has started gathering the information necessary to develop the project network diagram - predecessor activities and durations in weeks. The project team has requested that you create a network diagram for the project, identif..
Find the electric field intensity at a point : 1. If V=2x2-3y2+z2 represents the electrostatic potential at a joint, find the electric field intensity at a point (3, 2, -3). A vector field is given as, F=iy+j(x+y2)+k(yz+zx) Find: (i) div (F) (ii) curl (F). Show that F=i(x+y)+j(x+y)+(y-z) represen..
Digital evidence collection : Like most people, you probably travel familiar paths every day. When you walk down a street in your neighborhood or drive to work, do you feel that you could travel these routes easily while blindfolded? How would you feel if fog covered your fami..
Identity affects an individual''s life-span development : Add to your colleague's explanation of how gender identity affects an individual's life-span development. Explain whether you might use your colleague's strategy for applying the concept of gender identity to social work practice. Provide support f..
Experimental traceroute that uses fewer messages : Traceroute uses 2n messages each time it's run; find an experimental traceroute that uses fewer messages and explain how it works. Run traceroute for the gwu.edu and amazon.com for mac, and explain the results. Again, an explanation is needed fo..

Reviews

Write a Review

 

Project Management Questions & Answers

  Shoe-tek walking shoe evaluate annual sales for a

shoe-tek walking shoe evaluate annual sales for a projectshoe-tek inc. is a leading manufacturer of running shoes. with

  What is the purpose of the project charter

What is the purpose of the project charter? Discuss the advantages that you will have as you work on your own project by developing this charter early in the project.

  How confident are you in the analysis

How confident are you in the analysis - How might you address any concerns affect your confidence level?

  1 list four methods used for the distribution of

1. list four methods used for the distribution of end-of-meeting reports to senior management or ceo.2. list four

  Which of the following is an extension to pert/cpm

Which of the following is an extension to PERT/CPM? a) CERT b) FMEA

  Examine the organizations basic legal and social issues

Project Management - Examine the organizations basic legal, social and economic issues

  Should a project manager continue patting team members

Based on your experiences of working with a team member from a different culture, should a project manager continue to pat team members on the back in a gesture of appreciation for a great job done or is it best to avoid this gesture?

  Find five journals in the field of project management

Find five journals in the field of project management after you have found them examine them to determine

  A document that formally recognizes the existence of a proje

A document that formally recognizes the existence of a project and provides direction on the project's objectives and management

  What cost contingency reserves might be needed

As a result, you are quantifying the project's risk exposure and determining what cost and schedule contingency reserves might be needed. You performed a schedule risk analysis using Monte Carlo analysis.

  What should the organization do with regard to marketing

What can you tell about their business health? What should this organization do with regard to marketing? This is where all those years of education start to pay off.

  Mastering virtual teamsevaluate which factor is influencing

mastering virtual teamsevaluate which factor is influencing the team dynamics and why.petes team consists primarily of

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd