PROBLEM 1

Use the network diagram below and the additional information provided to answer the corresponding questions.

a) Give the crash cost per day per activity.

b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities?

c) Find the new budget (or cost of the project).

PROBLEM 2

Use the network diagram below and the additional information provided to answer the corresponding questions.

a) Give the crash cost per day per activity.

b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? What is the cost impact of crashing these activities?

PROBLEM 3

Month

AC

PV

EV

22

$540

$523

$535

a) Calculate the cost variance (CV).

b) Is the CV over or under budget?

c) Calculate the schedule variance (SV).

d) Is the SV ahead of or behind schedule?

PROBLEM 4

Month

AC

PV

EV

5

$34

$42

$39

a) Calculate the cost performance index (CPI).

b) Is the project cost efficient or not efficient?

c) Calculate the schedule performance index (SPI).

d) Is the schedule efficient or not efficient?

PROBLEM 5

Day

AC

PV

EV

65

$550

$735

$678

a) Calculate the cost variance (CV).

b) Calculate the cost performance index (CPI).

c) Calculate the schedule variance (SV).

d) Calculate the schedule performance index (SPI).

e) Given these data, what should a project manager do with respect to this project?

PROBLEM 6

Day

AC

PV

EV

65

$760

$735

$678

a) Calculate the cost variance (CV).

b) Calculate the cost performance index (CPI).

c) Calculate the schedule variance (SV).

d) Calculate the schedule performance index (SPI).

e) Explain the project performance in terms of efficiency, budget, and schedule. What should the project manager do for the project?

Reference no: EM131276884

Questions Cloud

Reasonable accommodating and work-life conflicts : Using the e-Activity, summarize the outcome of the selected case. Then, outline a corrective action plan geared toward mitigating the unfair reasonable accommodation practices within the organization in question.
The digital divide seems to be a prevailing issue : The digital divide seems to be a prevailing issue in today's rapidly changing world. What responsibility do e-marketers have in closing this divide? What about government responsibility? Select a country to bring forward supporting your discussion.
Role and possibility of creativity in strategy work : This week, the focus has been on reflecting on different approaches to strategy and the capability of those to utilize existing positions and strengths versus their encouragement of the development of alternative or creative outcomes.
About procurement-contract and partnership : If you have seen the film "Atlas Shrugged part 1" (released to theaters in 2011), or seen the film “Atlas Shrugged part 2” (released to theaters in 2012), or have seen the film “Atlas Shrugged part 3” (released to theaters in 2014) or if you have rea..
Crashed to meet a project deadline : a) Give the crash cost per day per activity. b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities?
Occurring to our workers or the products they produce : List one way that the meat packing industry in Chicago abused its workers. Provide one direct, multi-sentence quote from The Jungle, the lecture notes, or the textbook to support your answer. What protections do we have in place today to keep similar..
What were the ramifications : Examples are the Duke Lacrosse case and the Richard Jewell Olympic bombing case. What went wrong and why? What were the ramifications? What should have been done differently?
What question would you ask samantha base upon david account : What questions would you ask Samantha based upon David's account? What are some very important questions that you would ask each of them?
Organizational structure is factor in implementing your plan : Organizational Chart and Operations Chart (Topic 4) Organizational structure is a factor in implementing your plan. Using a graphic organizer, create an organization chart. Be sure the graphic organizer describes the relationships between people. Com..

Reviews

Write a Review

Business Management Questions & Answers

  Adequate incentives for executives

How do you make a business executive have the same feeling of ownership in his or her organization as the small business owner? I am afraid there is no way in light of how stock-options and other incentives have played out.

  Provide a rationale to support recommendations

Write a six to eight (6-8) page paper in which you: Compare and contrast the promotional strategies used by two (2) different companies for a similar product within the category that you selected. Recommend two (2) ways in which a company within the ..

  Omitting the lottery losses and gains

Assume Brenda decides to go along with Vincent and omits the lottery losses and gains  Next year the same situation arisesn but now it with gambling losses and gains If you were Brenda  and Vincent asked you to do the same thing you did last year reg..

  Discuss some potential ethical mishandlings

Classify also discuss some potential ethical mishandlings when it comes to cross selling, like targeting a demographic more likely to accept the suggested purchase like the elderly.

  Is the design appropriate to address the research question

Select a peer-reviewed journal article about a quantitative research study related to human services management that is also related to the Research Proposal topic selected by your Learning Team. Make sure the article includes information on stati..

  What was the initial question

What was the initial question you wanted to answer when you started thinking about your topic? How do your three main ideas answer that question? How does the evidence you found help to support those answers? at least 75 words for your opnion

  Analyze advantages in employing just-in-time philosophy

Analyze three advantages in employing the just-in-time philosophy in Honda's organization. Evaluate three to five means in which the philosophy could potentially impact quality assurance.

  Important to address each of the questions presented

Prepare a paper (700 to 1,050 words) discussing the case and incorporating answers to the questions below. It is important to address each of the questions presented.

  Production method for its new office shelfcan you help me

production method for its new office shelfcan you help me get started with this assignment?creative cabinets inc. needs

  Relationship between the amount buyers

Create a supply and demand graph in Excel that demonstrates the relationship between the amount buyers are willing to purchase and the quantity available. You may select your own data points, but you must discuss the relationship between supply an..

  Returns an array in which elements

Given a sorted array of 100 scores, the quartiles are at index 25, 50, and 75, which divide the data into even rankings each of which are the bottom, 2 middle, and top 25% of all scores. Write an algorithm with expected running time of O(n) that, ..

  How analytics and cloud technology could align with company

Create a workflow diagram to illustrate how analytics and cloud technology could align with the company's business processes. Note: The graphically depicted solution is not included in the required page length but must be included in the design do..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd