Reference no: EM131276884
In this homework assignment, you will be working through two crashing problems and four earned value problems. All the information you need is included within this Homework packet. Make sure you answer all parts of the questions in their entirety.
Once you have worked through the problems, please post your responses to the Dropbox. Please refer to the course Syllabus for the due date.
PROBLEM 1
Use the network diagram below and the additional information provided to answer the corresponding questions.
a) Give the crash cost per day per activity.
b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities?
c) Find the new budget (or cost of the project).
PROBLEM 2
Use the network diagram below and the additional information provided to answer the corresponding questions.
a) Give the crash cost per day per activity.
b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? What is the cost impact of crashing these activities?
PROBLEM 3
Month
|
AC
|
PV
|
EV
|
22
|
$540
|
$523
|
$535
|
a) Calculate the cost variance (CV).
b) Is the CV over or under budget?
c) Calculate the schedule variance (SV).
d) Is the SV ahead of or behind schedule?
PROBLEM 4
Month
|
AC
|
PV
|
EV
|
5
|
$34
|
$42
|
$39
|
a) Calculate the cost performance index (CPI).
b) Is the project cost efficient or not efficient?
c) Calculate the schedule performance index (SPI).
d) Is the schedule efficient or not efficient?
PROBLEM 5
Day
|
AC
|
PV
|
EV
|
65
|
$550
|
$735
|
$678
|
a) Calculate the cost variance (CV).
b) Calculate the cost performance index (CPI).
c) Calculate the schedule variance (SV).
d) Calculate the schedule performance index (SPI).
e) Given these data, what should a project manager do with respect to this project?
PROBLEM 6
Day
|
AC
|
PV
|
EV
|
65
|
$760
|
$735
|
$678
|
a) Calculate the cost variance (CV).
b) Calculate the cost performance index (CPI).
c) Calculate the schedule variance (SV).
d) Calculate the schedule performance index (SPI).
e) Explain the project performance in terms of efficiency, budget, and schedule. What should the project manager do for the project?
Reasonable accommodating and work-life conflicts
: Using the e-Activity, summarize the outcome of the selected case. Then, outline a corrective action plan geared toward mitigating the unfair reasonable accommodation practices within the organization in question.
|
The digital divide seems to be a prevailing issue
: The digital divide seems to be a prevailing issue in today's rapidly changing world. What responsibility do e-marketers have in closing this divide? What about government responsibility? Select a country to bring forward supporting your discussion.
|
Role and possibility of creativity in strategy work
: This week, the focus has been on reflecting on different approaches to strategy and the capability of those to utilize existing positions and strengths versus their encouragement of the development of alternative or creative outcomes.
|
About procurement-contract and partnership
: If you have seen the film "Atlas Shrugged part 1" (released to theaters in 2011), or seen the film “Atlas Shrugged part 2” (released to theaters in 2012), or have seen the film “Atlas Shrugged part 3” (released to theaters in 2014) or if you have rea..
|
Crashed to meet a project deadline
: a) Give the crash cost per day per activity. b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities?
|
Occurring to our workers or the products they produce
: List one way that the meat packing industry in Chicago abused its workers. Provide one direct, multi-sentence quote from The Jungle, the lecture notes, or the textbook to support your answer. What protections do we have in place today to keep similar..
|
What were the ramifications
: Examples are the Duke Lacrosse case and the Richard Jewell Olympic bombing case. What went wrong and why? What were the ramifications? What should have been done differently?
|
What question would you ask samantha base upon david account
: What questions would you ask Samantha based upon David's account? What are some very important questions that you would ask each of them?
|
Organizational structure is factor in implementing your plan
: Organizational Chart and Operations Chart (Topic 4) Organizational structure is a factor in implementing your plan. Using a graphic organizer, create an organization chart. Be sure the graphic organizer describes the relationships between people. Com..
|