Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
ACTIVITY
TIME (WEEKS)
A
6
E
4
B
7
F
C
3
G
10
D
2
H
The activities needed to build a prototype laser scanning machine at Dave Fletcher Corp. are listed in the following table. Construct an AON network for these activities.
IMMEDIATE PREDECESSOR(S)
-
C, E
D, F
A product has average daily demand of 10, a daily standard deviation of 1.5, a lead time of 2 days, and there are 25 on hand. The lead time is 2 days and the order Interval is 7 days. If the company desires a 90% service level, calculate the reorder ..
What is an organization that has successfully utilized the six sigma process? What was the purpose of the project? What was the outcome of the project? What were the major accomplishments or milestones associated with each of the five steps?
Develop a Quality Management Plan. Review the goals of your project and determine the anticipated deliverables for each milestone
Common problems that can jeopardize reliabilty or validity can include non comparable data,tenuous proximate measures, and instument decay. What suggestions for handling each type ?
If a firm’s net income (profit before taxes) is $360,000 and it has total assets of $1.2 million, what is its return on assets? If a firm’s cost of goods sold is $2.5 million and its average inventory is $800,000, what is the inventory turnover?
Identify several sources of errors as a student, employee, business owner, or in your personal life. Develop/discuss some Poka-Yokes that might prevent them
If you were developing an information system for an independent living facility that will track clients over time and place what clinical, financial, and management challenges and barriers do you anticipate will be encountered in planning and impleme..
Where do organizational missions originate? How do you explain the evolution of organizational missions as the organization grows and matures? If mission statements are “relatively enduring,” how often should they be changed?
A local chemical manufacturing plant contacted you to assist with OSHA compliance matters. Describe how you would go about determining if the plant must comply with the OSHA Methylene Chloride standard. Note: The plant uses methylene chloride in t..
The total output from a production system in one day is 900 units and the total labor necessary to produce the 900 units is 900 hours.
Using the expected activity times as the normal times and the following crashing information, determine the activity crashing decisions and revised activity schedule for the warehouse expansion project.
The first edition hardcover of a new book by a popular writer has a demand which is uniformly distributed between 1 and 2 million. The production and transportation costs per hardcover are $10, and the sale price in bookstores is $25. When the paperb..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd