Construct a project network for problem

Assignment Help Accounting Basics
Reference no: EM13786379

Instead, you should focus on solving using the project management capabilities within Excel QM/POM QM.

Linear programming

A series of activities must be completed in a coordinated fashion to complete a landscaping overhaul. The following table shows the activities their optimistic, most likely and pessimistic durations and their immediate predecessors DAYS Activity A m b

Immediate Predecessors A 4 8 12 --- B 4 10 13 A C 7 14 18 B D 9 16 20 B E 6 9 12 B F 2 4 6 D,E G 4 7 13 C,F H 3 5 7 G I 2 3 4 G,H A- Determine the expected times and variances for each activity

B- Construct a project network for this problem

C- Determine the EST, EFT, LST, LFT and slack for each activity.

Also determine the critical path and project completion time.

D- What is the probability that the project will be finished in less than 57 days?

E- What is the probability that the project will need at least 50 days?

The expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 6.

What is the probability that the project will:

a. Require at least 17 months?

b. Be completed within 20 months?

c. Require at least 23 months?

d. Be completed within 25 months?

Bowman Builders manufactures steel storage sheds for commercial use, Joe Bowman, president of Bowman Builders, is contemplating producing sheds for home use.

The activities necessary to build an experimental model and related data are given in the table on the next page. The project completion time using standard times is 14 weeks. How much does it cost to reduce the duration of this project from 14 weeks to 10 weeks?

Activity Immediate Predec.

Standard time Stand. Cost Crashtime(weeks) CrashCost A -- 3 1,000 2 1,600 B -- 2 2,000 1 2,700 C -- 1 300 1 300 D A 7 1,300 3 1,600 E B 6 850 3 1,000 F C 2 4,000 1 5,000 G D,E 4 1,500 2 2,000 # ***** Getting a degree from a college or university can be a long and difficult task.

Certain courses must be completed before other courses may be taken. Develop a network diagram in which every activity is a particular course that you must take for your degree program.

The immediate predecessors will be course prerequisites. Don't forget to include all university, college, and departmental course requirements.

Then try to group these courses into semesters or quarters for your particular school.

A. How long do you think it will take you to graduate?

B. Which courses, if not taken in the proper sequence, could delay your graduation?

Reference no: EM13786379

Questions Cloud

Identify and discuss the history of modern policing : Identify and discuss the roots/history of modern policing. What are the major challenges facing law enforcement agencies today
Case study on small business mangement : Small Business mangement
Expanding product offerings and quality : A major producer of passenger tires has launched an advertising campaign in which it is trying to market windshield wipers to the public under its brand name, which has been highly successful in the passenger tire market. Explain why the passenger ti..
How much gross income did beverly recognize in year 12 : ACCT 323 7380 INCOME TAX I (Summer 2015) WEEK 4 HOMEWORK 1) In the current tax year, Gunther earned $125,000 from his job as a civil engineer. In addition, he received $30,000 of income from Activity A, and lost $40,000, and 20,000 from Activities B ..
Construct a project network for problem : How long do you think it will take you to graduate - Which courses, if not taken in the proper sequence, could delay your graduation - Construct a project network for problem and Determine the EST, EFT, LST, LFT and slack for each activity.
Do a search for overtime pay : Go to the website of the Department of Labor: http://www.dol.gov. Do a search for "overtime pay." Select a topic from the list of regulations. Take notes on what you find. Be ready to share your findings later in the week
Translating if and and statements : This exercise will help you become more proficient at recognizing, translating, and evaluating if and and statements. In this assignment, find two examples for the exercise; translate the claims of the example into symbolic form; identify an if or..
What is the wi-fi alliance : Wireless Networking Technologies, What is the Wi-Fi Alliance, Give the numeric prefix IEEE standards use for Wi-Fi networks.
Exemplifies market penetration or market development : First, elaborate on one organization that exemplifies Market Penetration or Market Development! Second, Chapter 8 highlights at least one failure with respect to unrelated diversification/implementation, offer another example?

Reviews

Write a Review

Accounting Basics Questions & Answers

  Computing amount of gross profit

What is the amount of gross profit? Show calculations. What is the amount of operating income? Show calculations. What is the amount of pretax income?Show calculations

  Level of accounts receivable needed to support sales

a. What is the level of accounts receivable needed to support this sales expansion? b. What would be Collins's incremental aftertax return on investment?

  The times interest earned ratio is one measure used to

the times interest earned ratio is one measure used to assess the long-term debt ability of the firm. when computing

  On april 1 the accounts receivable ledger of grider company

grider companys chart of accounts includes the following selected accounts101 cash 401 sales112 accounts receivable 414

  Sissie owns two iteams of business equipment they were both

sissie owns two iteams of business equipment. they were both purchased in 2009 for 100000 both have a seven year

  Queens co is considering starting a multimedia advertising

the queens company had revenues of 930000 last year with total variable costs of 399900 and fixed costs of

  You are auditing the accounts receivable balance of a cable

you are auditing the accounts receivable balance of a cable television provider. individual accounts receivables tend

  How much will you have to pay in interest for a credit

how much will you have to pay in interest for a credit card balance of 9135 that is one month overdue if a 28 annual

  In september bellfont expects to produce 100000 door

bellfont company produces door stoppers. august production costs are belowdoor stoppers

  Arthurs auto repair shop is considering the purchase of a

arthurs auto repair shop is considering the purchase of a new computer system for diagnosing engine problems. the

  Aberge companys manufacturing overhead is 40 of its total

aberge companys manufacturing overhead is 40 of its total conversion costs. if direct labor is 88200 and if direct

  Calculate the predetermined overhead application rate

nautical accessories inc. manufactures womens boating hats. manufacturing overhead is assigned to production on a

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd