Q1.

Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table

Activity

Description

Duration (wks)

Precedence

A

Requirement Gathering

27

-

B

Business Analysis

24

-

C

Systems Analysis

21

-

D

Coding

21

A

E

Unit Test

22

B

F

Module Testing

27

C

G

Systems Testing

22

F

H

User Acceptance Testing

22

G,E

J

Implementation

22

H

K

Handover

23

D, J

(a) Construct a network diagram identifying the following:

i. Earliest Start Time(EST)
ii. Latest Finish Time (LFT)
iii. Total Float on each activities D, F & J
iv. Critical Path for the project

b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.

Q2.

The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?

Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.

Word count:1500




Put your comment
 
Minimize


Ask Question & Get Answers from Experts
Browse some more (Project Management) Materials
Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the
Compare and contrast a progress report versus a status report. Describe the means and timing by which each is delivered. Your response should be at least 75 words in lengt
PPMP20008 - Initiating and Planning Projects - You are to develop and complete the documents as the project manager for the project described in your case. The framework for
In a separate Word document, provide an analysis of unexpected events using the Project Schedule Template below (the unexpected events are located in Tab 2 of the document).
The Chief Financial Officer of a hospital needs to determine the present value of $120,000 investment received at the end of year 5. What is the present value if the discoun
Define the term Conflict and describe how conflict can interfere with the goals and objectives of a project team. How, as the project manager, do you recognize Team Conflict(s
Proposed a detailed plan for how you will manage the project going forward. Include any new project management related processes that you feel must be implemented to see th
In many organizations, each integrated project team uses the same economic analysis tool to develop financial projections for alternative solutions to performance improvemen