Q1.

Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table

Activity

Description

Duration (wks)

Precedence

A

Requirement Gathering

27

-

B

Business Analysis

24

-

C

Systems Analysis

21

-

D

Coding

21

A

E

Unit Test

22

B

F

Module Testing

27

C

G

Systems Testing

22

F

H

User Acceptance Testing

22

G,E

J

Implementation

22

H

K

Handover

23

D, J

(a) Construct a network diagram identifying the following:

i. Earliest Start Time(EST)
ii. Latest Finish Time (LFT)
iii. Total Float on each activities D, F & J
iv. Critical Path for the project

b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.

Q2.

The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?

Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.

Word count:1500




Put your comment
 
Minimize


Ask Question & Get Answers from Experts
Browse some more (Project Management) Materials
Write a paper showing your understanding of work in modern America. Included in this paper must be an analysis of positive and negative aspects of our relatively new service
Describe the circumstances under which a partnership would offer greater tax advantages than a corporation.- What is a single tax advantage of a limited liability company?
Suppose Smith had delivered the corn to the railroad in Toledo. After the corn was loaded on a freight car but before the train left the yard, the car was broken open and it
Reflect on a project in which you recently participated, either school-related or in a past job or community organization. Describe the extent to which this project followed,
Project Constraints - Analyzing possible project constraints and how to manage them. Identifying (with rationale) whether the project is time-constrained, resource-constraine
List two main implementation categories of the "supplier Partnership Critical Success Factors in the Phases of Implementation". Include the key elements that are associated
Explain project life-cycle management and the benefits of project management to an organization. Explain project organizations and the importance of leadership and sponsorship
Find the critical path and project duration in days. Given that each resource is assigned 100% to each task, identify the resource constraints.