The project manager on a project to construct a flyover in the city to ease traffic congestion. Flyover construction should cause minimum disruption to the traffic until it is complete. Ensuring safety of the commuters and workers at the site is the responsibility of your company. The date of completion of the project is six months from now. This date cannot be extended because of an upcoming international summit in the city.

To achieve theoverall project time lines, the following milestones must be achieved:

· Identifying a temporary alternate route and making it ready for the commuters—within two weeks of the project start

· Getting a final approval for the design and layout of the flyover, including a structural analysis—within four weeks of the project start

· Completing all construction activities by the end of the fifth month

· Cleaning up the construction infrastructure and finishing and painting the flyover by the end of five months and two weeks

· Opening the flyover for a trial in the third week of the sixth month and gathering feedback

· Placing traffic signs—entry and exit—in the fourth week of the sixth month

·

You have to acquire resources for the project. What type of resources will you require to successfully execute the project?

Out of the factors that influence decisions on acquiring human resources, which factors do you consider to be the most decisive in the choice of human resources for this project?




Put your comment
 
Minimize


Ask Question & Get Answers from Experts
Browse some more (Project Management) Materials
Read the given scenario and identify the type of meeting required in the given circumstances, propose the type of meeting interaction continuum, and recommend a technology t
Where would you locate a clothing manufacturer that makes light-weight jackets out of cotton and what factors would influence your decision on where to locate that facility?
Produce a detailed project plan, including some of the key headings given below, and any other information such as recommendations to the Project Board that you consider app
What is meant by the phrase integrated delivery system? What are some examples of the changes taking place in U.S. healthcare under this heading? Is project management importa
Develop a contingency plan for two to four identified risks. Estimate costs. Assign contingency reserves. How much reserve would your team estimate for the whole project? Ju
Choose a company for this project and consider the initial steps in creating a security policy. Develop security goals and components that make up a quality Executive Summar
Identify 6 potential risks for this project and write the risk register for all of them. Ensure one of your risks is a positive risk and construct the Probability/ Impact Mat
What is the critical path of this project now? (i.e., list the tasks on the critical path of this project in order.) Suppose task G runs late. Change its duration to 8 in M