Predicting Project Duration
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days. Draw a project network given the information below. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a penalty on this project?
ID| Description | Predecessor | Time/DaysA | Pour Foundation | None | 3B | Erect frame | A | 4C | Roof | B | 4D | Windows | B | 1E | Doors | B | 1F | Electrical | B | 3G | Rough-in frame | C,D,E,F | 2H | Door Opener | E, F | 1I | Paint | G,H | 2J | Clean up | I | 1
How much cash should the bank keep at an ATM if its annual cost of money is 10%? How often should the bank replenish an ATM?
Where do they originate? Can they be mitigated? Explain how. What are the consequences of ignoring a conflict within a project team?
What is meant by the term "business ethics?" Compare and contrast business ethics to the actions of organizational leaders at Target Corporation.
What are the four most important characteristics of high-performaning teams for project? Why are each so critical?
Develop a plan to calculate potential financial implications for a nationwide company of your choice. Provide a scenario in which a break-even sales analysis for reactive pricing would be the best option for a company.
What are some prerequisites for using Bayesian statistics?
What do you realize by term "trade-off"
What are the four alternatives a project organization can adopt in deciding how to address and respond to its risks?
Justify the influence of stakeholders in the project management plan and their role in communication planning.
What does this riddle have to do with project management?
What are the different types of risk that organizations face? What are the benefits of risk management?
Draw a CCPM network diagram and a Gantt Chart. How would these diagrams differ from the ones generated using traditional scheduling techniques.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd