Complete numbering the work breakdown structure

Assignment Help Project Management
Reference no: EM131250827 , Length:

You and your spouse have purchased a foreclosure you hope to flip for a profit. The two bathrooms had been recently remodeled by the previous owners. The three bedrooms need only cosmetic work - something you decide to undertake yourself. The majority of your budget will be used for remodeling the kitchen, the dining room, and the family room.

Since this is your first flip, you've hired an experienced home inspector to help you scope the project. You want to track costs carefully to stay as close to budget as possible and to give you an accurate baseline for similar work in future flips. Rather than doing a hierarchical decomposition of the project into various products/outcomes and then adding work package descriptors for each lowest-level product/outcome, you chose to list the components that needed work and then describe the work that must be completed for each of these components. NOTE: Assume your descriptions of the work that must be completed for each of the components are work package descriptors and that these work package descriptors are NOT decomposed into lower level elements.

Some of the work may have to take a higher priority if cost issues arise during the renovation. The higher priority work includes modifications to the electrical, HVAC, and plumbing systems, removal of two walls to provide an open concept arrangement, and common flooring throughout the kitchen, family room, and dining room areas. The quality of other finishes in the kitchen, dining room, and/or family room may have to be reduced if the cost of the higher priority work becomes an issue.

You decide to work backwards from your current list of work (shown below) to develop a WBS. You start by adding an element that represents the entire project and numbering it zero. You also decide to add several control accounts so that you can monitor and manage costs more effectively. These control accounts include:
- Higher Priority Work
- Lower Priority Work
- Utilities and Services (Electrical, HVAC, and Plumbing)
- Wall Removals
- Kitchen
- Dining Room (DR)
- Family Room (FR)

1. Without otherwise modifying the WBS structure, add the control accounts listed above.

2. Complete numbering the work breakdown structure so that Microsoft Project will automatically roll up work package costs to these control accounts.

NOTE: Your WBS must not violate any WBS core characteristics.

WBS No.

WBS Element

0

Three-Room Renovation

 

Electrical System

 

Upgrade the electrical service to 200 amps

 

Replace the electrical panel

 

Rerun electrical circuits affected by wall removals

 

Run four new electrical circuits to the kitchen area

 

HVAC

 

Install new furnace and air conditioning units

 

Rerun heating and ventilation ducts affected by wall removals

 

Install ventilation duct for new kitchen range hood

 

Install ventilation duct for new kitchen microwave

 

Plumbing Systems

 

Install larger diameter water pipe from water meter to the house

 

Install tank-less hot water heater

 

Rerun water pipes affected by wall removals

 

Rerun vent pipes affected by wall removals

 

Install water supply pipe for refrigerator ice maker

 

Wall 1 Removal - Between Kitchen and Dining Room

 

Demolish existing wall 1

 

Install new beam 1 to accept existing structural loads

 

Repair ceiling in way of the new beam 1

 

Wall 2Removal - Between Dining Room and Family Room

 

Demolish existing wall 2

 

Install new beam 2 to accept existing structural loads

 

Repair ceiling in way of the new beam 2

 

Flooring

 

Install new laminate flooring in the kitchen, dining room, and family room

 

Kitchen Window (Over Sink)

 

Remove existing window over the sink

 

Install new energy efficient window over the sink

 

Replace/repair drywall as necessary around the kitchen window

 

Install kitchen window trim

 

Kitchen Lighting

 

Replace existing can lights

 

Install new pendant lights over the island

 

Kitchen Cabinets, Island, and Countertops

 

Kitchen Cabinets

 

Install upper cabinets

 

Install lower cabinets

 

Install cabinet hardware

 

Kitchen Island

 

Install island

 

Install island hardware

 

Kitchen Countertops

 

Install cabinet countertops

 

Install island countertop

 

Kitchen Painting

 

Repair any remaining drywall defects in the kitchen

 

Paint the kitchen

 

Kitchen Appliances

 

Install range top

 

Install oven

 

Install microwave

 

Install refrigerator

 

Install dishwasher

 

DR Window

 

Remove existing DR window

 

Install new energy efficient DR window

 

Replace/repair drywall as necessary round the DR window

 

Install DR window trim

 

DR Lighting

 

Install new DR chandelier

 

DR Painting

 

Repair any remaining drywall defects in the DR

 

Paint the DR

 

FR Windows

 

Remove three existing FR windows

 

Install three new energy efficient FR windows

 

Replace/repair drywall as necessary around FR windows

 

Install FR window trim

 

FR Sliding Door

 

Remove existing FR sliding door

 

Reframe as necessary for new French door

 

Install new energy efficient French door

 

Replace/repair drywall as necessary around the door

 

Install door trim

 

FR Painting

 

Repair any remaining drywall defects in the FR

 

Paint the FR

Birdhouse Construction Plan

Week

No. by Design

First

Second

Third

1 7 4 2
2 4 4 3
3 7 3 3
4 4 4 4
5 3 5 3

 

 

 

 

Total 25 20 15

3. Calculate the planned budget for each week of the project and for the total project.

Week 1 = 5*7 + 10*4 + 15*2 = $ 105
Week 2 = 5*4 + 10*4 + 15*3= $ 105
Week 3 = 5*7 + 10*3 + 15*3=$ 110
Week 4 = 5*4 + 10*4 + 15*4=$ 120
Week 5 = 5*3 + 10*5 + 15*3=$ 110
Planned budget for total project = 105 + 105 + 110 + 120 + 110 = $ 550

4. At the end of week 2, you look at your actual progress and find the following:

 

Actual Progress (end of week 2)

Week

No. by Design

First Second Third
1

6

4

2

2

4

4

4

Calculate Earned Value (EV) for the first two weeks of the project and the project to-date.

5. Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why?

6. Is the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why?

7. Assuming you continue working as you are without making any changes to your processes or materials, what is the forecast of total project cost? Will you exceed your total available funds?

8. Assuming you continue working as you are without making any changes to your processes or materials, what is the Variance at Completion (VAC)?

9. At the end of week 3 you discover you that SV is still positive but SPI is 0.95. What does this mean?

Verified Expert

In the give solution a letter is prepared to Laura Sanchez, a professor who entered to US. The solution deals with determination of residential status of laura and filing of tax return. The footnotes are properly provided. The final conclusion is that laura has 2 options. Option 1 is to claim as resident under first year choice option and option 2 is to file as non-resident alien.

Reference no: EM131250827

Questions Cloud

White clothes using the production function : Mark launders his white clothes using the production function q=3 B+G where B is the number of cups of Clorox bleach and G is the number of cups of a generic bleach, where Clorox bleach is three times as potent.
What is the investment grade of your company''s bonds : What is the investment grade of your Company's bonds? Within their Notes to the Financial Statements can you identify any discussions on financial risk? If your Company has issued Bonds look at terms and identify the interest rates they are paying.
Explain the formation of stereotypes : According to the textbook, fundamental attribution error occurs when we focus less on the situation we are in and more on personal characteristics to describe behavior. Provide one (1) example of the primary manner in which situational and disposi..
Define the expected payoff associated with this action : Assuming that the biotechnology company acts as a risk-neutral decision maker, what action should it choose? What is the expected payoff associated with this action?
Complete numbering the work breakdown structure : Calculate Earned Value (EV) for the first two weeks of the project and the project to-date - Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why?
Calculate the fair present value of the the given bonds : Calculate the fair present value of the following bonds, all of which have a 10 percent coupon rate (paid semiannually), face value of $1,000, and a required rate of return of 8 percent.
What your views are concerning legalizing suicides : Discuss in detail what your views are concerning legalizing suicides. Do you feeleuthanasia or physician-assisted suicide be legal with terminally ill individuals?
What is the author argument : What is the author's argument, and how is it communicated in the written content of the text? What key examples are used? What concepts can you relate to your own practice as a designer
What ways is this cleaning service different from se : Considering what you have read about predictors of vocational success and quality vocational services, evaluate the options presented. Describe a SE program design that incorporates what you have learned about vocational issues and quality services..

Reviews

len1250827

10/21/2016 3:03:38 AM

I have to finish all of my work. However, it is proving to be difficult doing this in and out of the hospital with my mother who has stage 3 breast cancer. Any help you can lend me would be more than appreciated. If my price was too low please let me know. And I will try to adjust my budget. Thank you in advance.

Write a Review

Project Management Questions & Answers

  Project acceptancerejectionjackson corporation is

project acceptancerejectionjackson corporation is evaluating the following four independent investment

  Enterprise project management systems

Explain the enterprise project management systems view of a project and how it differs from other project management approaches. If you have participated in information technology projects where EPM was employed, describe your experience. Addition..

  Explain situations where communication between cultures

Expalin situations where communication between cultures can sometimes be misunderstood and Can you find in a newspaper or magazine, 2 sentences containing words and expressions that a non-native English speaker would not be likely to understand. R..

  Prepare a detailed systems implementation plan

You are required to prepare a detailed Systems Implementation Plan. To ensure that the document is consistent you are to use the template provided.

  Critical path of a pert chart

Project Timelines - Critical Path and PERT - In terms of creating a timeline, what is understand by the critical path of a PERT chart

  Project managementcompany a works in a business environment

project managementcompany a works in a business environment of rapid and drastic change together with strong

  What you need to know about project management

What you need to know about Project Management - Contingency allowances have not been built into the budget

  Explaining post-project evaluations

Why do you think organizations tend to ignore post-project evaluations? How could the concept of making such evaluations mandatory be implemented?

  Project managementin regards to top-down versus bottom-up

project managementin regards to top-down versus bottom-up budgeting in the newsgroup. there are advantages as well as

  Formulate resource estimates and project budgets

To build an effective project plan, one of the many components is the estimate of resources that will be required, when the resources will be required and the formulation of project-based budgets.

  Information about hardware and system software

What is an RFP, and how do analysts use one to gather information about hardware and system software?

  What is the difference between data and information

What is the difference between data and information? What are characteristics of good information? How does technology improve the decision making process?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd