Calculate the per day costs for crashing

Assignment Help Project Management
Reference no: EM13321191

ACME HOSPITAL TRAUMA WING PROJECT

Chris Michaels is the Chief Project Coordinator employed by a large private hospital group, AHE Healthcare. His primary responsibility is to ensure hospital construction and heavy-duty equipment installation projects involving any one of their 58 hospitals are successfully completed within the allocated budgets and timeframes. His job also involves coordinating the appointment of the project teams, project human resources management and project resources planning.

The construction supervisor's work is critical as all other work is dependent on the successful, timeous and progressive completion of the construction component. The engineers primarily serve as consultants and source the necessary supplies for the building contractor. The construction supervisor is also responsible for managing the largest proportion of people working on the project, the 32 construction workers required to complete the project on time. Although the builders will be employed and paid by the building contractor, the Project Manager can influence the choice of them. If new builders are selected, they may have to be trained.

ACME Hospital is AHE Healthcare's flagship hospital located in the city of Riversdale. It consists of 950 beds, 12 operating theatres, an emergency department, 14 general and specialist wards, ancillary medical and surgical departments and 1850 staff. The Hospital is planning to build new a new trauma wing consisting of a 6 bed trauma ward, one trauma theatre, one intensive care unit (ICU) and most importantly, a skywalk that links the existing hospital to the new wing which will be located across a major road.

The road is very busy and would require the project team to coordinate traffic during the skywalk construction, using their own resources. The proposed site of the new wing is unfortunately heavily-laden with rocks which have to be removed using heavy duty equipment. There are only two contractors for plant hire in Riversdale, and the limited amount of machinery may slow down the project. Another major challenge for the project team is the 18 month timeframe that the Managing Director of AHE Healthcare has allowed for the completion of the project. The reason is that an international sports organisation committee has selected Hemingway Hospital as the "standby" hospital of choice for any emergencies that may arise during an upcoming international sports tournament commencing in 20 months in Riversdale. The sports stadium is located 3 kilometers away from the hospital and may have to deal with trauma patients in the event of a catastrophe. The outcomes of not having a completed trauma wing on time could be disastrous.

The financial manager reports that the project has been allocated a budget of R65 million, which includes R150 000 for a project team reward and recognition programme. No further funds will be provided by AHE Healthcare, since this is the budget that the project sponsor motivated for at the outset. The project would have to comply with SANS standards, union contracts and government and Basic Conditions of Employment regulations.

The project is set to commence in three days time and cannot be delayed by even a week, but to everyone's dismay, the construction supervisor reports that his 32 construction workers are all reluctant to work. They have decided to go on strike as they have not been paid a fair wage and are demanding an increase. Fortunately, after a brief consultation with the worker's unions, the problem was quickly resolved and the workers will commence the project as scheduled, but some of them seem very lethargic and de-motivated. There is concern from the project team that this may result in project delays and diminished quality of work. Furthermore, some of the builders may resign, leaving the team with limited builders.

QUESTION 1

1.1 Based on the information provided in the case study above, draft a concise staff and management plan for the ACME Hospital trauma wing project.

1.2 How would you ensure that the construction workers do not delay the project or decrease the quality of work due to lethargy and de-motivation?

1.3 Describe two (2) earned-value management indices that you could use to understand how well or poorly the ACME trauma wing project is performing.

QUESTION  2

The Critical Path Method (CPM) is a schedule network analysis technique that is performed using the schedule model.

2.1 Prepare an activity on node (AON) diagram from the project information presented in the table below.

Activity No

Preceding Activity

Duration (Weeks)

100

Start

2

200

100

3

300

100

4

400

300

 

400

200

4

500

400

2

500

200

3

600

500

7

End

600

-

2.2 What is the duration of each path through the network diagram?

2.3 Identify the critical path.

2.4 Explain why this is called the critical path.

 

2.5 The PERT methodis used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates.

Calculate the expected time (t) for each activity below.

Activity

Optimistic time
(a)

Most likely time
(m)

Pessimistic time
(b)

Expected time
(t)

Immediate
predecessor

A

1

2

9

 

-

C

2

4

6

 

-

E

1

2

3

 

-

T

1

5

9

 

E

G

1

2

3

 

C, T

P

2

3

4

 

A, G

K

4

6

14

 

A, G

F

1

3

5

 

P

M

4

5

6

 

K

B

7

9

11

 

F, M

QUESTION 3

Using relevant examples, discuss some ways in which project teams can improve their performance.

QUESTION 4  

4.1 Using the above network diagram and the activity durations (in days) in the nodes calculate the slack time for each activity showing all workings.

4.2 Identify the critical path of the project

4.3 Construct and clearly label the Gantt chart for the above project, assuming the project starts on the 1st of May.

QUESTION 5

You are considering the decision of whether or not to crash your project. After asking your operations manager to conduct an analysis, you have determined the "pre-crash" and post-crash" activity duration costs as shown in table below:

Activity

Normal

Normal

Crashed

Crashed

 

Duration (days)

Cost

Duration (days)

Cost

A

4

R1000

3

R2000

8

5

R2500

3

R5000

C

3

R750

2

R1200

0

7

R3500

5

R5000

E

2

R500

1

R2000

F

5

R2000

4

R3000

G

9

R4500

7

R6300

5.1 Calculate the per day costs for crashing each activity.

5.2 Which is the most attractive activity to start crashing? Why?

5.3 Calculate project costs by all possible project durations. Display this information in a clearly labelled TABLE.

5.4 Assuming that your allocated project budget is capped at R18000, using the TABLE constructed in 5.3 above, determine at what point it no longer makes cost sense to continue crashing activities? Explain why?

Reference no: EM13321191

Questions Cloud

Depict structures of amines and classify each as 1 degree : Draw the structures of the following amines and classify each as 1 degree, 2 degree, 3 degree, or 4 degree amine. Include Hydrogen Atoms.
Determine the variation of jet are with elevation : A stream of liquid moving as low speed leaves a nozzle pointed directly downward. The velocity may be considered uniform across the nozzle exit and the effects of friction may be ignored.
Determine the maximum possible mass flow rate of air : Assume that the upstream pressure is 60 psi and that the flow is isothermal at 68F, determine the maximum possible mass flow rate of air for which the assumption of incompressible flow is a vaild engineering approximation.
Determine at a steady state the inlet and exit velocities : Air at 400 kPa, 270 Kelvin, enters a well-insulated, horizontal pipe having a diameter of 2cm and exits at 90kPa, 200 Kelvin. Ideal gas model for air, determine at a steady state The inlet and exit velocities, in m/s
Calculate the per day costs for crashing : Calculate the per day costs for crashing each activity and which is the most attractive activity to start crashing? Why - How would you ensure that the construction workers do not delay the project or decrease the quality of work due to lethargy and..
What is the rotational inertia of this object : A large metal ring has a radius of 0.30 m and a mass (uniformly distributed) of 2.5 kg. The ring hangs from a nail as shown. What is the rotational inertia of this object
Determine the corresponding value of the normal stress : a 60 -m- long steel wire must not strech more than 48mm when the tension in the wire is 6 kn. determine the corresponding value of the normal stress.
Explain why your chosen product would be a good candidate : Identify a product that could be promoted using a social networking site such as Facebook. In about 100 words, explain why your chosen product would be a good candidate for a social networking-based promotion strategy.
Find length of pipe needed to bring water to saturated vapor : Saturated liquid water at 1000 kPa flows at 2 kg/s inside a 10 cm outer diameter steel pipe and outside of the pipe is a flow of hot gases at 1000 K with a convection coefficient of h = 150 W/m2 K.

Reviews

Write a Review

Project Management Questions & Answers

  What are the types of business ownership

What are the four types of business ownership and describe each of them Your response should be at least 200 words in length. You are required to use at least your textbook as source material for your response

  Using the cut-and-try method for aggregate operations

Using the cut-and-try method for aggregate operations planning we can determine the production requirement in units of product. If the beginning inventory is 100 units

  The reflection process as a mindmap

Alternative submission method

  Participate in management and entitled to compensation

Lynda will be allowed to participate in management and is entitled to compensation.

  How project managers can control projects

List and describe the different levers that project managers use to exert control over projects and provide an example of how each lever can be used in project control.

  Responsibility of project manager-matrix-type organization

What are the responsibilities of a project manager in a matrix-type organization? What about project-type organizations?

  Developing comprehensive project scope analysis

Develop a comprehensive project scope analysis. The conceptual development process, scope statement and statement of work that will clearly detail the projects.

  Show the challenges of communication

Compare and contrast the communication methods used to manage a virtual team as opposed to a face-to-face team. Also, show the challenges of communication often faced with each type of team.

  Risks introduced by change in plans

What are the risks (adverse effect) that are introduced by this change in plans?

  Deming-s theory on quality embraced by japanese industry

Why was Deming's theory on quality embraced by the Japanese auto industry and rejected by the American auto industry?

  Risk management component of successful project management

Risk management is a major component of successful project management.

  Completion time for project if duration of activity is given

What is the revised completion time for the project if duration of activity E is 3 weeks?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd